[Adopted 1-24-2017 by Res. No. 2017-18]
A. 
The fees listed in the attached schedule of fees, which are to be charged for the various applications and services associated with the UDC and which are designed to partially defray the costs of administering and enforcing the UDC, are hereby adopted, to be effective along with the UDC on February 2, 2017.
Community Development Fee Schedule
Service
Fee
Special use permit
Noncommercial
$350
Commercial
$600
Appeal
Noncommercial
$200
Commercial
$200
Variance
Noncommercial
$150
Commercial
$250
Zone change
Noncommercial
$350
Commercial
$600
Business registration
$35
Subdivision plat
$800
Plus, per lot
$15
Subdivision replat
$200
Subdivision summary
$200
Claim of exemption
$25
Driveway permit
$20
Construction permit
$600 or 4%, whichever is greater
Master Plans and community types
$350
Renotification fee
$100
Site plan review for nonresidential (commercial)
$350
Amendments to approved site plan: r
Minor
$50
Major
$250
Zoning verification letter
$35
Sign permit (based on square feet)
0 to 49
$15
50 to 99
$20
100 to 149
$25
150 to 199
$30
200 to 249
$35
250 to 299
$40
300 to 349
$45
350 or more
$50
Fire Marshal permit
$25
Road maintenance request
$250
Stormwater Pollution Prevention Plan (SWPPP)
Single residential lot with less than 1 acre of proposed ground disturbance
$0
Commercial/industrial parcel with less than 1 acre of proposed ground
$100
Parcels with 1 to 5 acres of proposed ground disturbance
$200
Parcels with greater than 5 up to and including 10 acres of proposed ground disturbance
$300
Parcels with greater than 10 up to and including 20 acres of proposed ground disturbance
$400
Parcels with greater than 20 acres of proposed ground disturbance
$500
Application processing for appeal of ruling on SWPPP to County Commission
$200
B. 
Postage fees apply for all applications that require mailing notification.