[Code 1992, §§ 13.14, 13.16; amended 3-13-2017 by Ord. No. 17-04]
(a) 
Meters will be furnished and placed by the Utility Commission. All meters shall be so located that they shall be safeguarded from obstructions and frost and to allow easy access thereto for reading and inspection. The location shall be designated by proper employees of the Utility Commission. No bypass or other connection between the meter and the main shall be maintained, unless specifically authorized by the Utility Commission.
(b) 
In setting meters, all connections shall be made according to the rules and regulations of the Utility Commission. Water lines from outside the building to the meter shall be a minimum of one inch in diameter and free of any soldered joints. Meter horn or setters shall be required in installation of all meters up to and including one inch. Shutoff valves shall be installed before and after the meter setter. A sealed bypass shall be required on all meters over one inch in size.
(c) 
Where a service is to be metered and there is no basement, or where it is impossible to properly set a meter in the consumer's basement, the Utility Commission will provide at the consumer's expense the proper frostproof box of an approved design to be located outside the consumer's building at a cost of labor, material and expense plus 10% to cover overhead charges.
[Code 1992, § 13.17; amended 3-13-2017 by Ord. No. 17-04]
All water which has passed through the meter shall be paid for. If it is believed that the meter is registering incorrectly or if there is a sound of running water, the consumer shall notify the office of the Utility Commission, and a qualified employee will be sent to examine the service and advise the consumer without a charge therefor.
[Code 1992, § 13.18; amended 3-13-2017 by Ord. No. 17-04]
Where a property owner requests a change in the location of the meter, such meter may be relocated as directed by the Utility Commission at the expense of the property owner.
[Code 1992, § 13.19; amended 3-13-2017 by Ord. No. 17-04]
All new meters purchased and all old meters which have been repaired or removed from service for any cause shall be tested and adjusted to show not more than a two-percent error before again being placed in service. All meters shall be tested at least once every three years. A complete record shall be kept of each meter, noting all repairs and inspections made and the results of each test.
[Code 1992, § 13.21; amended 3-13-2017 by Ord. No. 17-04]
The Utility Commission shall make a test of the accuracy of any water meter not greater than two inches in size upon the written request of a consumer filed at the office of the Utility Commission, provided the consumer does not request such test more frequently than once in 12 months. Tests shall only be made more frequently upon order of the state Public Service Commission or at the expense of the consumer when the meter is within the tolerance of 2%. Meters greater than two inches in size will be tested at the instance and direction of the Utility Commission, but not less often than once every two calendar years. All tests are to be made in conformity with the rules provided by the Public Service Commission.
[Code 1992, § 13.20; amended 3-13-2017 by Ord. No. 17-04]
All water meters while in service shall be kept under seal affixed by an authorized employee or officer of the Utility Commission. The person responsible for water bills for water supplied through a meter whose seal has been tampered with or broken shall be deemed prima facie guilty of the offense.
[Code 1992, § 13.30; amended 3-13-2017 by Ord. No. 17-04]
(a) 
When premises are to be vacated, the Utility Commission shall be notified in writing at once so that the meter may be read and removed if necessary, and the water supply shut off at the curb box. The owner of the premises shall be liable for damage to any property belonging to the City by reason of failure to notify the Commission of the vacancy. A change of tenants in any unit of service within any quarterly meter reading period will not be construed as a vacancy, and the entire billing for the period will be submitted to the owner. Any adjusting by way of apportioning the amount of the bill between the outgoing and incoming tenants shall be made by the owner.
(b) 
Premises which are entirely vacant, the service to which has been cut off at the curb box by the Utility Commission, shall be considered permanently vacant.
[Code 1992, § 13.45; amended 3-13-2017 by Ord. No. 17-04]
(a) 
Installation costs. Remote register or touch pad water meter attachments will be installed by the Utility Commission. The costs shall be borne by the utility.
(b) 
Determination of priority of installations. The Utility Commission shall determine the priority of such installations for the purpose of efficiency as follows:
(1) 
All new construction.
(2) 
Presently difficult place to read.
(3) 
All other installations desirable for the benefit of the utility.
(4) 
Residences where occupants habitually or necessarily are absent.
(c) 
Location. The location of the remote register meter is to be determined by the utility.
(d) 
Compliance with section. Each owner of any building constructed hereafter which is or is required to be served by a public water utility shall comply with the provisions of this section. Prior to final approval of construction by the Building Inspector and issuance of any certificate of completion or remodeling, the provisions of this section shall be complied with.
(e) 
Installation of conduit by owner. Each owner of premises to whom this section applies shall install or cause to be installed a conduit of at least one-half-inch diameter from the present water meter if such is installed upon the premises or from the area where a water meter would be installed to the exterior of the building where gas meters are located or to be located or where the utility designates. The requirements of this section shall also apply to owners who remodel existing structures when such remodeling takes place in an area as to permit installation of the conduit as a part of the remodeling project. This determination shall be made by the Building Inspector.
(f) 
Installation to be determined by Utility Commission. Owners of existing structures shall permit installation as determined by representatives of the Utility Commission.