[HISTORY: Adopted by the Town Board of the Town of Collins 11-8-2017 by L.L. No. 1-2017.[1] Amendments noted where applicable.]
GENERAL REFERENCES
Joint Planning Board — See Ch. 42.
Zoning Board of Appeals — See Ch. 76.
Uniform construction codes — See Ch. 121.
Site plan review — See Ch. 206.
Subdivision of land — See Ch. 220.
Zoning — See Ch. 265.
[1]
Editor's Note: This local law was adopted as Ch. 158, but
was renumbered to maintain the organization of the Code.
This chapter is adopted pursuant to §§ 261 through
263 of the Town Law of the State of New York, which authorizes the
Town of North Collins to adopt laws which advance and protect the
health, safety and welfare of the community and to make provisions
for the accommodation of solar energy systems and equipment.
The Town Board of the Town of North Collins makes the following
findings:
A.
Solar energy is a clean, readily available and renewable energy source
that decreases energy costs and provides local business and job opportunities.
B.
However, there is a growing need to properly site solar energy systems
within the boundaries of the Town of North Collins in order to protect
residential, business areas and other land uses, to preserve the overall
beauty, nature and character of the Town of North Collins and to promote
the effective and efficient use of solar energy resources as well
as the health, safety and general welfare of the citizens of the Town
of North Collins.
C.
Prior to the adoption of this chapter, no specific procedures existed
to address the siting of solar energy systems. Accordingly, the Town
Board finds that the promulgation of this chapter is necessary to
govern the location and construction of these systems.
D.
Solar energy systems need to be regulated for removal when no longer
utilized.
The following definitions shall apply to this chapter:
- APPLICANT
- The person or entity filing an application and seeking an approval under this chapter; the owner of a solar energy system or a proposed solar energy system project; the operator of solar energy system or a proposed solar energy system project; any person acting on behalf of an applicant, solar energy system or proposed solar energy system.
- BUILDING-INTEGRATED SOLAR ENERGY SYSTEM
- A solar energy and/or thermal heat system, including but not limited to photovoltaic building components, such as vertical facades, including glass and other facade material, semitransparent skylight systems, roofing materials and shading over windows.
- BUILDING-MOUNTED SOLAR ENERGY SYSTEM
- A solar energy and/or thermal heat system that is affixed to the side(s) of a building or other structure, either directly or by means of support structures or other mounting devices, but not including those mounted to the roof or top surface of a building. Said system is designed and intended to generate electricity or heat primarily for use on said lot, but potentially for multiple tenants.
- GROUND-MOUNTED SOLAR ENERGY SYSTEM
- A solar energy and/or thermal heat system that is affixed to the ground either directly or by support structures or other mounting devices. Said system is an accessory structure, designed and intended to generate electricity or heat primarily for use on said lot, but potentially for multiple tenants. Ground-mounted solar energy systems not meeting the definition as outlined in this chapter will be treated as utility-scale solar energy systems and the requirements of such.
- ROOFTOP-MOUNTED SOLAR ENERGY SYSTEM
- Any solar energy and/or thermal heat system that is affixed to the roof of a building and wholly contained within the limits of the roof surface. Said system is designed and intended to generate electricity or heat solely for use on said lot, but potentially for multiple tenants.
- SOLAR ENERGY SYSTEM FOR AGRICULTURAL USE
- Any solar energy and/or thermal heat system that is used solely for agricultural production as defined in Agriculture and Markets Law § 301(4).
- UTILITY-SCALE SOLAR ENERGY SYSTEM
- Any solar energy system that is designed and intended to supply energy exceeding 50 kw primarily into a utility grid for sale to the general public or to any utility.
The requirements of this chapter shall apply to all solar energy
systems installed or modified after the effective date, excluding
general maintenance and repair of solar energy systems. Subject to
the provisions of this chapter, solar energy systems shall be allowed
in the Town of North Collins as follows:
A.
Rooftop-mounted and building-mounted solar energy systems are permitted
in all zoning districts within the Town through the building permit
application process.
B.
Building-integrated solar energy systems are permitted in all zoning
districts within the Town under the building permit application process
for new building construction or building renovations.
C.
Ground-mounted solar energy systems.
(1)
Ground-mounted solar energy systems which comply with all of the
requirements and criteria of this chapter, and are located on lots
of two or more acres, are permitted in all zoning districts within
the Town under the building permit application process.
(2)
Ground-mounted solar energy systems which exceed any of the stated
requirements or criteria of this chapter, or which are proposed upon
lots which are less than two acres, shall require site plan approval
by the Town Planning Board in addition to the building permit application
process.
D.
Utility-scale solar energy systems are permitted only in the R-A
(Residence Agricultural) District and require a special permit from
the Town Board, site plan approval from the Planning Board and a building
permit.
E.
Any inconsistent provisions contained in any other provision of the
Town Code are hereby superseded by this chapter.
The placement, construction and/or major modification of all
solar energy systems within the boundaries of the Town of North Collins
shall be permitted as follows:
A.
Residential solar energy systems up to 12 kw shall be permitted in
all zoning districts upon issuance of a building permit, subject to
compliance with the requirements and criteria of this chapter. Any
residential solar energy system exceeding 12 kw, but less than 25
kw, may be permitted upon issuance of a building permit, provided
the applicant first obtains a variance and site plan approval from
the Town Planning Board and otherwise complies with the requirements
of this chapter.
B.
Commercial solar energy systems up to 25 kw shall be permitted in
all commercial zoning districts upon issuance of a building permit,
subject to compliance with the requirements and criteria of this chapter.
Any commercial solar energy system exceeding 25 kw, but less than
100 kw, may be permitted upon issuance of a building permit, provided
the applicant first obtains a variance and site plan approval from
the Town Planning Board and otherwise complies with the requirements
of this chapter.
C.
Rooftop-mounted and building-mounted solar energy systems shall be
allowed in all zoning districts upon issuance of a building permit,
subject to compliance with the requirements and criteria of this chapter.
D.
Ground-mounted solar energy systems situate on lots of two or more
acres in size and which otherwise comply with all of the requirements
and criteria of this chapter shall be allowed in all zoning districts
upon issuance of a building permit.
E.
Ground-mounted solar energy systems situate on lots less than two
acres in size may be allowed in all zoning districts, conditioned
upon site plan approval by the Town Planning Board and upon issuance
of a building permit, subject to compliance with all provisions of
this chapter as determined by the Town Planning Board. The Town Planning
Board shall have the sole discretion as part of the site plan review
process to determine whether a variance from the requirements of this
chapter may be allowed.
F.
Utility-scale solar energy systems shall be allowed only by special
permit and only in the R-A (Residence-Agricultural) District in accordance
with the criteria established in this chapter, after SEQRA review
and concurrent site plan approval by the Town Planning Board and upon
issuance of a building permit.
G.
All solar energy systems existing on the effective date of this chapter
shall be allowed to continue usage as they presently exist. Routine
maintenance (including replacement with a new system of like construction
and size) shall be permitted on such existing systems. New construction
other than routine maintenance shall comply with the requirements
of this chapter.
H.
Any application for a solar energy system which is pending on the
effective date of this chapter shall be subject to the provisions
of this chapter.
I.
This chapter shall take precedence over any inconsistent provision
contained in any other provision of the Town Code of the Town of North
Collins.
A.
Rooftop-mounted and building-mounted solar energy systems shall not
be more than three feet higher than the finished roof to which they
are mounted and in no instance shall any part of the system extend
within three feet of the edge of the roof. All rooftop-mounted and
building-mounted solar energy systems shall meet all building permit
requirements, including the New York State Uniform Fire Prevention
and Building Code standards.
B.
Ground-mounted solar energy systems.
(1)
Ground-mounted solar energy systems (not utility-grade systems) shall
be subject to the following requirements:
(a)
The location of the solar energy system shall be located in
the side or rear yard of the property and not in the front yard.
(b)
The location of the solar energy system shall be placed at least
50 feet from any side yard property line and at least 50 feet from
any rear property line.
(c)
The location of the solar energy system shall be placed at least
200 feet from any structure which is regularly occupied by humans,
including accessory structures, regardless of whether said structure(s)
are located on the applicant's lot or on any adjoining lot.
(d)
The location of the solar energy system shall be placed at least
200 feet from any roadway, right-of-way, school, playground or park.
(e)
A remote disconnect shall be provided and shown on the site
plan.
(f)
The height of the solar energy system shall not exceed 15 feet
when oriented at maximum tilt.
(g)
The total surface area of the solar panels on the solar energy
system shall not exceed 500 square feet.
(h)
The total area occupied by the solar energy system on a lot
shall not exceed 10% of the total area of the lot upon which the system
is proposed.
(i)
The design, construction, operation and maintenance of the proposed
system shall prevent the misdirection and/or reflection of solar rays
onto neighboring properties, public roads, parks, schools and rights-of-way
in excess of that which already exists.
(j)
The application should include evidence that the system shall
be used solely to reduce the on-site consumption of electricity. Remote
net metering shall be permitted if all locations (host and satellite)
are geographically located within North Collins.
(2)
Any proposed solar energy system that meets all of the above general
criteria shall be allowed upon issuance of a building permit. Any
proposed solar energy system that does not meet all of the above criteria
shall be allowed only upon site plan approval by the Town Planning
Board and issuance of a building permit.
C.
Site plan requirements for a ground-mounted solar energy system.
(1)
If site plan approval is required by this chapter for a ground-mounted
solar energy system, the applicant shall submit a site plan application,
including the following:
(a)
Plans and drawings of the solar energy system showing the proposed
layout of the solar energy system along with a description of all
components, existing vegetation, any proposed clearing and grading
of the lot involved, any stormwater or erosion disturbances, and utility
lines, both above and below ground, on the site and adjacent to the
site;
(b)
A recently dated (within one year) survey of the property showing
all lot lines and the location and dimensions of all existing structures
and uses on the property;
(c)
The location of any residence or structure on any other property
located within 300 feet of the proposed solar panels or of any park,
school, playground or public roadway within 300 feet of the proposed
solar panels;
(d)
Copies of the owner's deed and property tax bill;
(e)
Any proposed fencing and/or screening for the project; and
(f)
Any such additional information as may be required by the Town's
professional engineer or consultant, Town Planning Board, Building
Inspector or other agent/employee of the Town.
(2)
The design, construction, operation and maintenance of ground-mounted
solar energy systems shall prevent the misdirection and/or reflection
of solar rays onto neighboring properties, public roads, parks, schools
and roadways in excess of that which already exists.
D.
Solar storage batteries. When solar batteries are included as part
of any solar energy system, they shall be placed in a secure container
or enclosure meeting the requirements of the New York State Building
Code.
E.
All solar energy systems shall adhere to all applicable federal,
state, county and Town laws, regulations and building, plumbing, electrical
and fire codes.
F.
All solar energy systems shall be accessible for all emergency service
vehicles and personnel.
G.
All structures and devices used to support solar collectors shall
be nonreflective and/or painted a subtle or earth tone color. The
design, construction, operation and maintenance of any solar energy
system shall prevent the misdirection and/or reflection of solar rays
onto neighboring properties, public roads and public parks in excess
of that which already exists.
H.
The development and operation of a solar energy system shall not
have a significant adverse impact on fish, wildlife, or plant species
or their critical habitats, or other significant habitats identified
by the federal, state or local governments or their agencies.
I.
Artificial lighting of any solar energy systems shall be limited
to lighting required for safety and operational purposes and shall
be shielded from all neighboring properties and public roads.
J.
If the use of an approved solar energy system is discontinued, the
owner or operator shall notify the Building Inspector within 30 days
of such discontinuance. If a solar energy system is to be retained
and reused, the owner or operator shall further inform the Building
Inspector of this, in writing, at such time and obtain any necessary
approvals within one year; otherwise, it shall automatically be deemed
abandoned (and removed per this chapter).
K.
In deciding whether to issue a site plan approval of the proposed
solar energy system, the Planning Board shall have the discretion
to vary from and/or waive stated criteria where appropriate in meeting
the goals and objectives of this chapter.
L.
The Planning Board shall meet in public, and any person interested
in the application may attend said meetings. The Town Clerk shall
make legal posting and advertising of the public meetings. Additionally,
the Town Clerk shall provide written notice (by regular first-class
mail to the address contained on the Town tax bill) of said meetings
to all adjoining property owners at least 10 days prior to said meeting.
All persons shall have the right to speak in favor or against said
application.
Applications for special permits for utility-scale solar energy
systems under this chapter shall be made as follows: Applicants for
a special permit to place, construct, or to make a major modification
to a utility-scale solar energy system within the Town of North Collins
shall submit six sets of the following information to the Building
Inspector, who shall first present the application to the Town Board.
The Town Board shall initially review the application and shall then
refer the matter to the Town Planning Board for review and recommendation
and for concurrent site plan review. At any time in the process, the
Building Inspector, the Town Board or the Planning Board may request
that a professional engineer or consultant review the matter and act
as consultant to the Town in the permitting process. The Planning
Board may make such additional referrals and requests as it deems
appropriate. No such application shall be deemed filed until all required
application fees and related costs have been paid by the applicant.
In the event a consultant is hired by the Town, the applicant shall
pay the costs thereof. The following information shall be contained
in the initial application:
A.
A completed full environmental assessment form (EAF) under the State
Environmental Quality Review Act (SEQRA)[1] which shall fully describe the proposed system, its location,
purpose and potential environmental impact. The Town Planning Board
shall be designated as the lead agency for the SEQRA process.
[1]
Editor's Note: See Environmental Conservation Law § 8-0101
et seq.
B.
The following additional information shall be required:
(1)
Name, address, telephone number of the property owner and the section,
block, lot (SBL) tax number of the parcel(s) involved. Copies of the
deed and a current survey shall be included. If the property owner
is not the applicant, the application shall include the name, address
and telephone number of the applicant and a letter of authorization
signed by the property owner authorizing the applicant to represent
the property owner; and
(2)
Documentation of access to the project site, including location of
all access roads, gates, parking areas, etc.; and
(3)
Documentation of the clearing, grading, stormwater and erosion control
plans; and
(4)
Utility interconnection data and a copy of written notification to
the utility of the proposed interconnection; and
(5)
One- or three-line electrical diagram detailing the solar energy
system installation, associated components, and electrical interconnection
methods, with all disconnects and over-current devices; and
(6)
A property owner or applicant who has installed or intends to install
a utility-scale solar energy system may choose to negotiate with other
property owners in the vicinity for any necessary solar skyspace easements
or other applicable easements. The issuance of a special use permit
does not constitute solar skyspace rights, and the Town shall not
be responsible for ensuring impermissible obstruction to the solar
skyspace as a result of uses or development performed in accordance
with the Town Code.
C.
A site plan drawn in sufficient detail as follows:
(1)
Plans and drawings of the solar energy system installation signed
by a professional engineer registered in New York State showing the
proposed layout of the entire solar energy system along with a description
of all components, whether on site or off site, existing vegetation
and proposed clearing and grading of all sites involved, and utility
lines, both above and below ground, on the site and adjacent to the
site; and
(2)
Property lot lines and the location and dimension of all existing
structures and uses on site and off site which are within 500 feet
of the solar panels; and
(3)
Proposed fencing and/or screening for said project; and
D.
A decommissioning plan to ensure the proper removal of utility-scale
solar energy systems. The decommissioning plan is to be submitted
as part of the special permit application to the Building Inspector
for approval and must specify that after the utility-scale solar energy
system is no longer in use (as determined by the owner/operator or
the Building Inspector), it shall be removed by the applicant or any
subsequent owner. The decommissioning plan shall identify the anticipated
life of the project. The plan shall demonstrate how the removal of
all infrastructure and restoration shall be conducted to return the
parcel to its original state prior to construction. The plan shall
also include an expected time line for execution and a cost estimate
for decommissioning prepared by a professional engineer or qualified
contractor. Cost estimates shall take inflation into consideration
and be revised every five years during the operation of the system
and include any salvage value. Removal of the large-scale solar energy
system must be completed in accordance with the approved decommissioning
plan and the standards provided as follows:
(1)
All structures and foundations associated with the large-scale solar
energy systems shall be removed;
(2)
All disturbed ground surfaces shall be restored to original conditions,
including topsoil and seeding as necessary; and
(3)
All electrical systems shall be properly disconnected, and all buried
cables and wiring shall be removed.
E.
A bond or other approved security shall be provided to cover the
cost of removal and restoration of the area impacted by the solar
system. Security shall be in an amount equal to 150% of the estimated
cost to restore the property as presented in the approved decommissioning
plan.
F.
Any such additional information as may be required by the Town's
professional engineer or consultant, Town Planning Board or other
agent or employee of the Town.
Special permits issued for a utility-scale solar energy system
shall meet the following minimum conditions:
A.
Minimum lot area: The minimum lot area shall be 25 acres.
B.
Maximum lot area: none.
C.
Setbacks: Any utility-scale solar energy system shall adhere to the
following setbacks:
(1)
A minimum of 300 feet from all property lot lines.
(2)
From all buildings or structures: a minimum of 300 feet from any
inhabited building or structure, except for buildings and structures
located on the proposed project lot.
(3)
From any public roadway, park, playground or school: a minimum of
300 feet from any public roadway, park, playground or school.
D.
Maximum overall height: The height of a utility-scale energy system
shall not exceed 20 feet when oriented at maximum tilt.
E.
A utility-scale solar energy system shall only be located in a rear
yard if there is a principal structure or dwelling on said lot. It
shall not be allowed in the front yard.
F.
A utility-scale solar energy system shall adhere to all applicable
federal, state, county and Town of North Collins laws, regulations,
building, plumbing, electrical and fire codes.
G.
Development and operation of a utility-scale solar energy system
shall not have a significant adverse impact on adjoining property
owners, wildlife, fish or plant species or their critical habitats
or other significant habitats.
H.
The design, construction, operation and maintenance of a utility-scale
solar energy system shall prevent the misdirection and/or reflection
of solar rays onto neighboring properties, public roads and public
parks in excess of that which already exists.
I.
All structures and devices used to support solar collectors shall
be nonreflective and/or painted in a subtle or earth tone color.
J.
All transmission lines and wiring associated with a utility-scale
or solar energy system shall be buried and include necessary encasements
in accordance with the National Electric Code and state and local
code requirements. The applicant is required to show the locations
of all proposed overhead and underground electric utility lines, including
substations and junction boxes and other electrical components for
the project on the site plan.
K.
All transmission lines and electrical wiring shall be in compliance
with the utility company's requirements for interconnection.
L.
Lighting on any structure associated with the system shall not be
allowed, except to the extent it may be required by state or federal
law.
M.
No advertising signs shall be permitted on the solar energy system.
Signage shall be included which provides twenty-four-hour emergency
contact phone numbers to the owner of the system and in accordance
with state or federal law.
N.
Any site containing a utility-scale solar energy system shall contain
fencing or other device acceptable to the Town enclosing all solar
energy system components.
O.
A berm, landscape screen or other opaque enclosure, or any combination
thereof acceptable to the Town capable of screening the site may be
required along any property line that abuts an existing roadway or
residence.
P.
After completion of a utility-scale solar energy system, the applicant
shall provide a post-construction certification from a professional
engineer registered in New York State that the project complies with
all applicable codes and industry practices and is operating according
to the design plans.
Q.
The applicant is required to obtain all necessary and required regulatory
approvals and permits from all federal, state, county and local agencies
having jurisdiction and approval related to the completion of a utility-scale
solar energy system.
R.
A bond or other appropriate form of security shall be offered by
the applicant as part of the decommissioning plan to cover the cost
of the removal and site restoration, and said proof of appropriate
form of security shall be filed prior to construction and on an annual
basis with the Town Clerk.
S.
Clearing, grading, stormwater and erosion control. Before the Town
of North Collins shall issue a building permit for a utility-scale
solar energy system, the applicant shall submit a stormwater and erosion
control plan to the Town Planning Board for its review and approval.
The plan shall minimize the potential adverse impacts on wetlands
and Class I and Class II streams and the banks and vegetation along
those streams and wetlands and minimize erosion or sedimentation.
A.
Within 30 days after completion of its review of the application
and completion of the site plan review process, the Planning Board
shall send the Town Board written findings and recommendations and
site plan approval, disapproval or approval with conditions. Following
receipt of the Planning Board's written recommendations on the
application, together with a final site plan approval, at the next
regularly scheduled meeting of the Town Board, the Town Board shall
schedule a public hearing on the application. The purpose of the public
hearing shall be on the topic of whether or not to issue a special
permit to construct a utility-scale solar energy system. The public
hearing before the Town Board shall be held within 60 days after receipt
of the written recommendations of the Town Planning Board. Legal posting
and advertising of the public hearing shall be made by the Town Clerk.
Written notice (by regular first-class mail to the address contained
on the Town tax bill) of said public hearing shall be given to all
adjoining property owners by the Town Clerk at least 10 days prior
to said public hearing. Within 60 days after completion of the public
hearing, the Town Board shall render a final decision, in writing,
to the applicant. The Town Board may vote to grant a special permit,
deny a special permit, or grant a special permit with stated conditions.
The Town Board may, but is not required to, follow the recommendations
of the Town Planning Board.
B.
Time limit on completion. After the granting of a special permit
of a utility-scale solar energy system by the Town Board, the applicant
shall obtain a building permit within six months after the date the
special permit was approved. The project shall be completed within
12 months after issuance of the building permit. A six-month extension
to obtain a building permit and/or the completion time may be approved
by the Planning Board upon request by the applicant. If the system
is not constructed within the above time frame, or if no application
for extension is filed, the special permit, building permit and site
plan approval shall automatically lapse 12 months after the date of
the approval of the special permit by the Town Board.
C.
Inspections. Upon reasonable notice, the Town Building Inspector
may enter a lot on which a solar energy system has been approved for
the purpose of ensuring compliance with any requirements or conditions.
Twenty-four hours' advance notice by telephone shall be deemed
reasonable notice. Furthermore, a utility-scale solar energy system
shall be inspected annually by the Town Building Inspector or a licensed
professional engineer that has been designated by the Town, and a
copy of the inspection report shall be submitted to the Town Building
Inspector. Any fee or expense associated with this inspection shall
be borne entirely by the permit holder.
D.
General complaint process. During construction, the Town Building
Inspector can issue a stop order at any time for any violations of
a special permit or building permit. After construction is complete,
the permit holder shall designate a contact person, including name,
address and phone number, for receipt of any complaint concerning
any permit or operational issues.
E.
Continued operation. A solar energy system shall be maintained in
operational condition at all times, subject to reasonable maintenance
and repair outages. "Operational condition" includes meeting all approval
requirements and conditions. Furthermore, the Building Inspector shall
also have the right to request documentation from the owner for a
solar energy system regarding the system's usage at any time.
F.
Removal. All solar energy systems shall be dismantled and removed
immediately from a lot when the special permit or approval has been
revoked by the Town of North Collins Planning Board or the solar energy
system has been deemed inoperative or abandoned by the Building Inspector
for a period of more than 365 days, at the cost of the owner. If the
owner does not dismantle and remove the said solar energy system as
required, the Town Board may, after a hearing at which the owner shall
be given an opportunity to be heard and present evidence, dismantle
and remove said facility and place the cost of removal as a tax lien
on said parcel.
G.
Determination of abandonment or inoperability. A determination of
the abandonment of or inoperability of a solar energy system shall
be made by the Town Building Inspector, who shall provide the owner
with written notice by personal service or certified mail. Any appeal
by the owner of the Building Inspector's determination of abandonment
or inoperability shall be filed with the Town Board within 30 days
of the Building Inspector causing personal service or mailing by certified
mail his written determination, and the Board shall hold a hearing
on same. The filing of an appeal does not stay the following time
frame unless the Town Board or a court of competent jurisdiction grants
a stay or reverses said determination. At the earlier of the 365 days
from the date of determination of abandonment or inoperability without
reactivation or upon completion of dismantling and removal, any approvals
for the solar energy system shall automatically expire.
H.
Application and annual fees.
(1)
Utility-scale solar energy system. The applicant shall pay an initial
application fee in an amount as set by the Town Board, upon filing
its special permit and site plan application, to cover the cost of
processing and reviewing the application. If approved, the owner shall
thereafter pay an annual fee in the amount as set by the Town Board
to cover the cost of processing and reviewing the annual inspection
report and for administration, inspections and enforcement.
(2)
Site plan application for freestanding and ground-mounted solar energy
systems. An applicant shall pay the standard site plan review fee
as determined and established from time to time by the Town Board.
(3)
The Town of North Collins reserves the right to provide, by local
law or otherwise, that no exemption pursuant to the provisions of
the New York State Real Property Tax Law (RPTL) § 487 shall
be applicable within its jurisdiction.
I.
Upon completion of its deliberations, the Town Planning Board shall send a written recommendation to the Town Board. The Planning Board may recommend that a special permit be issued, or may recommend a denial of a special permit, or may recommend that a special permit be issued subject to conditions, as determined by the Planning Board. The Planning Board's recommendations shall be in writing and shall include all findings and conclusions deemed relevant by the Planning Board. Special permits for utility-scale solar energy systems granted under this article shall be issued by the Town Clerk at the direction of the Town Board, following a public hearing held by the Town Board, as required for all special use permits under Chapter 265, Article XIII, of the Town Code.
J.
The Town Board shall conduct a public hearing on the application.
Within 60 days after the conclusion of the public hearing, the Town
Board may vote to grant a special permit, deny a special permit or
grant a special permit with written stated conditions. The decision
of the Town Board shall be by written decision based upon substantial
evidence considered by the Board. Special permits for utility-scale
solar energy systems granted under this chapter shall be issued by
the Town Clerk after approval and at the direction of the Town Board.
Upon issuance of a special permit, the applicant shall then obtain
a building permit from the Building Inspector for the construction
of a utility-scale solar energy system.
K.
Any changes or alterations post-construction to any solar energy
system shall be done only by amendment to the applicable special permit
and/or site plan (if required) subject to all requirements of this
chapter.
L.
Special permits for utility-scale solar energy systems shall be assignable
or transferrable so long as the applicable system is in full compliance
with this article and all of the conditions imposed thereon, and the
Building Inspector is notified, in writing, of the proposed assignment
or transfer at least 30 days prior thereto.
M.
In addition to the requirements of this chapter, the special permit
application shall be subject to any other site plan approval requirements
set forth in the Town Code.
Applications for solar energy systems which are to be used solely
for agricultural production [as defined in Agriculture and Markets
Law § 301(4)] located in a state or county agricultural
district shall include the following information:
A.
Name and address of the applicant.
B.
Evidence that the applicant is the owner of the property involved
or has the written permission of the owner to make such application.
C.
A drawing or diagram drawn in sufficient detail to show the following:
D.
Environmental assessment form (short form) pursuant to 6 NYCRR 617.
E.
Such additional information as may be reasonably requested by the
Town Planning Board for a complete understanding of the proposed system.
F.
The Planning Board may determine that not all of these requirements
are necessary for a particular proposed project.
G.
A permit fee, in an amount as established by the Town Board from
time to time.
H.
The applicant shall include evidence that the system will be used
solely to reduce the on-site consumption of electricity. Remote net
metering shall be permitted if all agricultural locations (host and
satellite) are geographically located within North Collins.
I.
Evidence that the electrical output from the solar energy system
will not exceed 110% of the farm's anticipated electrical needs.
If the applicant and/or owner of any solar energy system violates
any of the conditions of its special permit or site plan approval
or violates any other federal, state, county or local law, rule or
regulation, this shall be grounds for the revocation of the applicable
special permit, site plan approval or building permit previously issued
to the applicant. Revocation may occur after the applicant and/or
owner is notified, in writing, of the violations and the Town Planning
Board holds a hearing on same.
In the interpretation and application of this chapter, the provisions
of this article shall be held to be minimum requirements, adopted
for the promotion of the public health, safety and general welfare
of the residents of the Town of North Collins. It is not intended
to interfere with, abrogate, or annul other rules, regulations or
laws, provided that whenever the requirements of this article are
at variance with the requirements of any other lawfully adopted law,
rule or regulation, the most restrictive, or those which impose the
highest standards, shall govern.
If any section, subsection, phrase, sentence or other portion
of this article is for any reason held invalid, void, unconstitutional
or otherwise unenforceable by any court of competent jurisdiction,
such portion shall be deemed a separate, distinct and independent
provision and such holding shall not affect the validity of the remaining
portions thereof.
Solar energy systems shall be exempt from assessment/taxation as provided under Real Property Tax Law § 487. However, the Town of North Collins reserves the right to require the owner of a utility scale solar energy system to enter into a contract for payments in lieu of taxes (PILOT) as a requirement for receiving a special permit under § 212-7.