[Ord. 2-2013, 4/2/2013]
The Legislature of the Commonwealth of Pennsylvania has, by
the passage of the Pennsylvania Flood Plain Management Act of 1978, delegated the responsibility to local governmental units
to adopt floodplain management regulations to promote public health,
safety, and the general welfare of its citizenry. Therefore, the Board
of Supervisors of Stroud Township does hereby order the following.
[Ord. 2-2013, 4/2/2013]
This chapter supersedes any other conflicting provisions which
may be in effect in identified floodplain areas. However, any other
ordinance provisions shall remain in full force and effect to the
extent that those provisions are more restrictive. If there is any
conflict between any of the provisions of this chapter, the more restrictive
shall apply.
[Ord. 2-2013, 4/2/2013]
Unless specifically defined below, words, phrases and terms
not herein defined which are defined in the Pennsylvania Municipalities
Planning Code (MPC) or Chapter
27, Zoning, shall have the meanings assigned in the MPC or Chapter
27, Zoning. Terms not defined in this chapter, the MPC or Chapter
27, Zoning, shall have the meaning customarily assigned to them as found in the most recent edition of Webster's New World College Dictionary.
[Ord. 2-2013, 4/2/2013]
As used in this chapter, the following terms shall have the
meanings indicated:
ACCESSORY USE OR STRUCTURE
A use or structure on the same lot with, and of a nature
customarily incidental and subordinate to, the principal use or structure.
BASE FLOOD
A flood which has a one-percent chance of being equaled or
exceeded in any given year (also called the "one-hundred-year flood"
or "one-percent annual chance flood").
BASE FLOOD DISCHARGE
The volume of water resulting from a base flood as it passes
a given location within a given time, usually expressed in cubic feet
per second (cfs).
BASE FLOOD ELEVATION (BFE)
The elevation shown on the Flood Insurance Rate Map (FIRM)
for Zones AE, AH, A1-30 that indicates the water surface elevation
resulting from a flood that has a one-percent or greater chance of
being equaled or exceeded in any given year.
BASEMENT
Any area of the building having its floor below ground level
on all sides.
BUILDING
A combination of materials to form a permanent structure
having walls and a roof. Included shall be all manufactured homes
and trailers to be used for human habitation.
DEVELOPMENT
Any man-made change to improved or unimproved real estate,
including but not limited to the construction, reconstruction, renovation,
repair, expansion, or alteration of buildings or other structures;
the placement of manufactured homes; streets, and other paving; utilities;
filling, grading and excavation; mining; dredging; drilling operations;
storage of equipment or materials; and the subdivision of land.
EXISTING MANUFACTURED HOME PARK OR SUBDIVISION
A manufactured home park or subdivision for which the construction
of facilities for servicing the lots on which the manufactured homes
are to be affixed (including, at a minimum, the installation of utilities,
the construction of streets, and either final site grading or the
pouring of concrete pads) is completed before the effective date of
the floodplain management regulations adopted by a community.
EXPANSION TO AN EXISTING MANUFACTURED HOME PARK OR SUBDIVISION
The preparation of additional sites by the construction of
facilities for servicing the lots on which the manufactured homes
are to be affixed (including the installation of utilities, the construction
of streets, and either final site grading or the pouring of concrete
pads).
FLOOD
A temporary inundation of normally dry land areas.
FLOOD INSURANCE RATE MAP (FIRM)
The Official Map on which the Federal Emergency Management
Agency has delineated both the areas of special flood hazards and
the risk premium zones applicable to the community.
FLOOD INSURANCE STUDY (FIS)
The official report provided by the Federal Emergency Management
Agency that includes flood profiles, the Flood Insurance Rate Map,
the Flood Boundary and Floodway Map, and the water surface elevation
of the base flood.
FLOODPLAIN AREA
A relatively flat or low land area which is subject to partial
or complete inundation from an adjoining or nearby stream, river or
watercourse; and/or any area subject to the unusual and rapid accumulation
of surface waters from any source.
FLOODWAY
The channel of a river or other watercourse and the adjacent
land areas that must be reserved in order to discharge the base flood
without cumulatively increasing the water surface elevation more than
one foot.
HIGHEST ADJACENT GRADE
The highest natural elevation of the ground surface prior
to construction next to the proposed walls of a structure.
HISTORIC STRUCTURES
Any structure that is:
A.
Listed individually in the National Register of Historic Places
(a listing maintained by the Department of Interior) or preliminarily
determined by the Secretary of the Interior as meeting the requirements
for individual listing on the National Register;
B.
Certified or preliminarily determined by the Secretary of the
Interior as contributing to the historical significance of a registered
historic district or a district preliminarily determined by the Secretary
to qualify as a registered historic district;
C.
Individually listed on a state inventory of historic places
in states which have been approved by the Secretary of the Interior;
or
D.
Individually listed on a local inventory of historic places
in communities with historic preservation that have been certified
either:
(1)
By an approved state program as determined by the Secretary
of the Interior; or
(2)
Directly by the Secretary of the Interior in states without
approved programs.
LOWEST FLOOR
The lowest floor of the lowest fully enclosed area (including
basement). An unfinished, flood-resistant partially enclosed area,
used solely for parking of vehicles, building access, and incidental
storage, in an area other than a basement area, is not considered
the lowest floor of a building, provided that such space is not designed
and built so that the structure is in violation of the applicable
nonelevation design requirements of this chapter.
MANUFACTURED HOME
A structure, transportable in one or more sections, which
is built on a permanent chassis, and is designed for use with or without
a permanent foundation when attached to the required utilities. The
term includes park trailers, travel trailers, recreational and other
similar vehicles which are placed on a site for more than 180 consecutive
days.
MINOR REPAIR
The replacement of existing work with equivalent materials
for the purpose of its routine maintenance and upkeep, but not including
the cutting away of any wall, partition or portion thereof, the removal
or cutting of any structural beam or bearing support, or the removal
or change of any required means of egress, or rearrangement of parts
of a structure affecting the exitway requirements; nor shall minor
repairs include addition to, alteration of, replacement or relocation
of any standpipe, water supply, sewer, drainage, drain leader, gas,
oil, waste, vent, or similar piping, electric wiring, mechanical or
other work affecting public health or general safety.
MPC
Pennsylvania Municipalities Planning Code, as may be amended.
NEW CONSTRUCTION
Structures for which the start of construction commenced
on or after the effective start date (April 7, 2013) of this Floodplain
Management Ordinance and includes any subsequent improvements to such
structures. Any construction started after April 15, 1977 and before
the effective start date (April 7, 2013) of this Floodplain Management
Ordinance is subject to the ordinance in effect at the time the permit
was issued, provided the start of construction was within 180 days
of permit issuance.
NEW MANUFACTURED HOME PARK OR SUBDIVISION
A manufactured home park or subdivision for which the construction
of facilities for servicing the lots on which the manufactured homes
are to be affixed (including at a minimum, the installation of utilities,
the construction of streets, and either final site grading or the
pouring of concrete pads) is completed on or after the effective date
of floodplain management regulations adopted by a community.
PA DEP
Pennsylvania Department of Environmental Protection.
PERSON
An individual, partnership, public or private association
or corporation, firm, trust, estate, municipality, governmental unit,
public utility or any other legal entity whatsoever, which is recognized
by law as the subject of rights and duties.
POST-FIRM STRUCTURE
A structure for which construction or substantial improvement
occurred after December 31, 1974, or on or after the community's
initial Flood Insurance Rate Map (FIRM) dated April 15, 1977, whichever
is later, and, as such, would be required to be compliant with the
regulations of the National Flood Insurance Program.
PRE-FIRM STRUCTURE
A structure for which construction or substantial improvement
occurred on or before December 31, 1974, or before the community's
initial Flood Insurance Rate Map (FIRM) dated April 15, 1977, whichever
is later, and, as such, would not be required to be compliant with
the regulations of the National Flood Insurance Program.
RECREATIONAL VEHICLE
A vehicle which is:
A.
Built on a single chassis;
B.
Not more than 400 square feet, measured at the largest horizontal
projections;
C.
Designed to be self-propelled or permanently towable by a light-duty
truck;
D.
Not designed for use as a permanent dwelling but as temporary
living quarters for recreational, camping, travel, or seasonal use.
REGULATORY FLOOD ELEVATION
The base flood elevation (BFE) or estimated flood height
as determined using simplified methods plus a freeboard safety factor
of 1 1/2 feet.
REPETITIVE LOSS
Flood-related damages sustained by a structure on two separate
occasions during a ten-year period for which the cost of repairs at
the time of each such flood event, on average, equals or exceeds 25%
of the market value of the structure before the damages occurred.
SPECIAL FLOOD HAZARD AREA (SFHA)
An area in the floodplain subject to a one-percent or greater
chance of flooding in any given year. It is shown on the FIRM as Zone
A, AO, A1-A30, AE, A99, or AH.
START OF CONSTRUCTION
Includes substantial improvement and other proposed new development
and means the date the permit was issued, provided the actual start
of construction, repair, reconstruction, rehabilitation, addition,
placement, or other improvement was within 180 days after the date
of the permit and shall be completed within 12 months after the date
of issuance of the permit unless a time extension is granted, in writing,
by the Floodplain Administrator. The "actual start" means either the
first placement of permanent construction of a structure on a site,
such as the pouring of slab or footings, the installation of piles,
the construction of columns, or any work beyond the stage of excavation;
or the placement of a manufactured home on a foundation. Permanent
construction does not include land preparation, such as clearing,
grading, and filling; nor does it include the installation of streets
and walkways; nor does it include excavation for a basement, footings,
piers, or foundations or the erection of temporary forms; nor does
it include the installation on the property of accessory buildings,
such as garages or sheds not occupied as dwelling units or not part
of the main structure. For a substantial improvement, the "actual
start of construction" means the first alteration of any wall, ceiling,
floor, or other structural part of a building, whether or not that
alteration affects the external dimensions of the building.
STRUCTURE
Any man-made object having an ascertainable stationary location
on or in land or water, whether or not affixed to land including,
but not limited to, a walled and roofed building, a gas, liquid or
storage tank of any kind that is principally above ground or would
be subjected to adverse impacts caused by flood conditions as determined
by the Township Engineer, as well as a manufactured home.
SUBDIVISION
The division or redivision of a lot, tract, or parcel of
land by any means into two or more lots, tracts, parcels or other
divisions of land, including changes in existing lot lines for the
purpose, whether immediate or future, of lease, partition by the court
for distribution to heirs, or devisees, transfer of ownership or building
or lot development; provided, however, that the subdivision by lease
of land for agricultural purposes into parcels of more than 10 acres,
not involving any new street or easement of access or any residential
dwelling, shall be exempted.
SUBSTANTIAL DAMAGE
Damage from any cause sustained by a structure whereby the
cost of restoring the structure to its before-damaged condition would
equal or exceed 50% or more of the market value of the structure before
the damage occurred.
SUBSTANTIAL IMPROVEMENT
Any reconstruction, rehabilitation, addition, or other improvement
of a structure, of which the cost equals or exceeds 50% of the market
value of the structure before the "start of construction" of the improvement.
This term includes structures which have incurred "substantial damage"
or "repetitive loss" regardless of the actual repair work performed.
The term does not, however, include any project for improvement of
a structure to correct existing violations of state or local health,
sanitary, or safety code specifications which have been identified
by the local code enforcement official and which are the minimum necessary
to assure safe living conditions. Historic structures undergoing repair
or rehabilitation that would constitute a substantial improvement
as defined in this chapter, must comply with all ordinance requirements
that do not preclude the structure's continued designation as
a historic structure. Documentation that a specific ordinance requirement
will cause removal of the structure from the National Register of
Historic Places or the State Inventory of Historic places must be
obtained from the Secretary of the Interior or the State Historic
Preservation Officer. Any exemption from ordinance requirements will
be the minimum necessary to preserve the historic character and design
of the structure.
TOWNSHIP ENGINEER
A professional engineer licensed as such in the Commonwealth
of Pennsylvania, duly appointed or retained as the engineer for the
Township or an alternate professional engineer appointed or retained
by the Board of Supervisors.
UNIFORM CONSTRUCTION CODE (UCC)
The statewide building code adopted by the Pennsylvania General
Assembly in 1999 applicable to new construction in all municipalities
whether administered by the municipality, a third party or the Department
of Labor and Industry. Applicable to residential and commercial buildings, the
code adopted the International Residential Code (IRC) and the International
Building Code (IBC), by reference, as the construction standard applicable
with the state floodplain construction. For coordination purposes,
references to the above are made specifically to various sections
of the IRC and the IBC, as may be amended.
VIOLATION
The failure of a structure or other development to be fully
compliant with the community's floodplain management regulations.
A structure or other development without the elevation certificate,
other certifications, or other evidence of compliance required in
44 CFR 60.3(b)(5), (c)(4), (c)(10), (d)(3), (e)(2), (e)(4), or (e)(5)
is presumed to be in violation until such time as that documentation
is provided.
WATERCOURSE
A channel or conveyance of surface water having defined bed
and banks, whether natural or artificial, with perennial or intermittent
flow.