In addition to the general requirements of Article
IV, the requirements of this article shall:
A. Apply in flood hazard areas, including special flood hazard
areas along nontidal waters of the state.
B. Apply to all development, new construction, substantial
improvements (including repair of substantial damage), and placement,
replacement, and substantial improvement (including repair of substantial
damage) of manufactured homes.
Within areas defined by flood protection setbacks along nontidal
waters of the state:
A. No new buildings, structures, or other development shall
be permitted unless the applicant demonstrates that the site cannot
be developed without such encroachment into the flood protection setback
and the encroachment is the minimum necessary after consideration
of varying other siting standards such as side, front, and back lot
line setbacks.
B. Disturbance of natural vegetation shall be minimized, and
any disturbance allowed shall be vegetatively stabilized.
C. Public works and temporary construction may be permitted.
New residential structures and residential portions of mixed-use structures, and substantial improvement (including repair of substantial damage) of existing residential structures and residential portions of mixed-use structures shall comply with the applicable requirements of Article
IV and this section. See §
79-35 for requirements for horizontal additions.
A. Elevation requirements.
(1) Lowest floors shall be elevated to or above the flood
protection elevation.
(2) In areas of shallow flooding (Zone AO), the lowest floor
(including basement) shall be elevated at least as high above the
highest adjacent grade as the depth number specified in feet on the
FIRM plus two feet, or at least four feet if a depth number is not
specified.
(3) Enclosures below the lowest floor shall meet the requirements of Subsection
C.
B. Limitations on use of fill to elevate structures. Unless otherwise restricted by these regulations, especially by the limitations in §
79-32A,
B and
C, fill placed for the purpose of raising the ground level to support a building or structure shall:
(1) Consist of earthen soil or rock materials only.
(2) Extend laterally from the building footprint to provide
for adequate access as a function of use; the Floodplain Administrator
may seek advice from the State Fire Marshal's Office and/or the
local fire services agency;
(3) Comply with the requirements of the building code and
be placed and compacted to provide for stability under conditions
of rising and falling floodwaters and resistance to erosion, scour,
and settling;
(4) Be sloped no steeper than one vertical to two horizontal,
unless approved by the Floodplain Administrator;
(5) Be protected from erosion associated with expected velocities
during the occurrence of the base flood; unless approved by the Floodplain
Administrator, fill slopes shall be protected by vegetation if the
expected velocity is less than five feet per second, and by other
means if the expected velocity is five feet per second or more; and
(6) Be designed with provisions for adequate drainage and
no adverse effect on adjacent properties.
C. Enclosures below the lowest floor.
(1) Enclosures below the lowest floor shall be used solely
for parking of vehicles, building access, crawl/underfloor spaces,
or limited storage.
(2) Enclosures below the lowest floor shall be constructed
using flood-damage-resistant materials.
(3) Enclosures below the lowest floor shall be provided with
flood openings which shall meet the following criteria:
(a)
There shall be a minimum of two flood openings on
different sides of each enclosed area; if a building has more than
one enclosure below the lowest floor, each such enclosure shall have
flood openings on exterior walls.
(b)
The total net area of all flood openings shall be
at least one square inch for each square foot of enclosed area (nonengineered
flood openings), or the flood openings shall be engineered flood openings
that are designed and certified by a licensed professional engineer
to automatically allow entry and exit of floodwaters; the certification
requirement may be satisfied by an individual certification or an
evaluation report issued by the ICC Evaluation Service, Inc.
(c)
The bottom of each flood opening shall be one foot
or less above the higher of the interior floor or grade, or the exterior
grade, immediately below the opening.
(d)
Any louvers, screens or other covers for the flood
openings shall allow the automatic flow of floodwaters into and out
of the enclosed area.
(e)
If installed in doors, flood openings that meet requirements of Subsection
C(3)(a) through
(d) are acceptable; however, doors without installed flood openings do not meet the requirements of this section.
New nonresidential structures and nonresidential portions of mixed-use structures, and substantial improvement (including repair of substantial damage) of existing nonresidential structures and nonresidential portions of mixed-use structures shall comply with the applicable requirements of Article
IV and the requirements of this section. See §
79-35 for requirements for horizontal additions.
A. Elevation requirements. Elevated structures shall:
(1) Have the lowest floor (including basement) elevated to
or above the flood protection elevation; or
(2) In areas of shallow flooding (Zone AO), have the lowest
floor (including basement) elevated at least as high above the highest
adjacent grade as the depth number specified in feet on the FIRM plus
two feet, or at least four feet if a depth number is not specified;
and
(3) Have enclosures below the lowest floor, if any, that comply with the requirements of §
79-33C; or
(4) If proposed to be elevated on fill, meet the limitations on fill in §
79-33B.
B. Floodproofing requirements.
(1) Floodproofing of new nonresidential buildings is not allowed
in nontidal waters of the state [COMAR 26.17.04.11(B)(7)].
(2) Floodproofing for substantial improvement of nonresidential
buildings is allowed in nontidal waters of the state.
(3) If floodproofing is proposed, structures shall:
(a)
Be designed to be dry floodproofed such that the
building or structure is watertight with walls and floors substantially
impermeable to the passage of water to the level of the flood protection
elevation plus 1.0 foot; or
(b)
If located in an area of shallow flooding (Zone AO),
be dry floodproofed at least as high above the highest adjacent grade
as the depth number specified on the FIRM plus three feet, or at least
five feet if a depth number is not specified; and
(c)
Have structural components capable of resisting hydrostatic
and hydrodynamic loads and effects of buoyancy;
(d)
Have floodproofing measures that are designed taking
into consideration the nature of flood-related hazards; frequency,
depth and duration of flooding; rate of rise and fall of floodwater;
soil characteristics; floodborne debris; at least 12 hours of flood
warning time from a credible source; and time necessary to implement
any measures that require human intervention;
(e)
Have at least one door above the applicable flood
elevation that allows human ingress and egress during conditions of
flooding;
(f)
Have an operations and maintenance plan that is filed
with local emergency management officials and that specifies the owner's/occupant's
responsibilities to monitor flood potential; the location of any shields,
doors, closures, tools, or other goods that are required for implementation;
maintenance of such goods; methods of installation; and periodic inspection;
and
(g)
Be certified by a licensed professional engineer or licensed architect, through execution of a floodproofing certificate that states that the design and methods of construction meet the requirements of this section. The floodproofing certificate shall be submitted with the construction drawings as required in §