[Ord. 2013-01, 2/11/2013]
1.
Persons desiring to undertake any new construction, structural or site alteration, or changes in the use of a building or lot shall apply to the Township Zoning Officer for a zoning permit by filling out the appropriate application form and by submitting the required fee.
2.
The Zoning Officer shall either issue the zoning permit or shall refuse the permit, indicating in writing the reason for refusal and citing the Part of this chapter upon which such refusal was made. Certain construction, alterations, and uses require approval of the Zoning Hearing Board, the Board of Supervisors, and/or the recommendations of the Planning Commission.
3.
If refused a permit by the Zoning Officer, the applicant may appeal to the Zoning Hearing Board for further consideration.
4.
After the zoning permit has been received by the applicant, he may undertake the action permitted by the zoning permit.
5.
Upon completion of such action, the applicant may apply to the Township Zoning Officer for an occupancy permit, where such a permit is required.
6.
If the Zoning Officer finds that the action of the applicant is in accordance with the zoning permit and any other required permits, he shall issue an occupancy permit allowing the premises to be occupied.