[Amended 6-22-2020 by
Art. 11]
The primary intent of this bylaw is to establish guidelines
and regulate the removal, importation, and filling of any material
for the protection of human health, public safety, welfare, and the
integrity of the natural resources, including aquifers, bodies of
water and the wetlands of the Town of Dudley.
The following definitions shall apply to this bylaw:
BOARD
The Board of Selectmen.
EARTH
Soil, loam, sand, gravel, borrow, rock, sod, peat, humus,
clay, coal or other earth material.
EXCAVATE
To dig out and remove material.
FILL
To deposit, use, redistribute or move any material on or
within any land area or water body. Also, any material which is used
for this purpose.
IMPORT
To bring any material from outside of the Town to any land
area or water body within the Town.
MATERIAL
Any geologic, man-made, recycled or processed material including
in its entirety or as a proportion containing clay, rock, sand, gravel,
topsoil, loam, humus, peat, sod, borrow rock, sediment, wood, plant
or animal matter, glass, paper, plastic, metal, bituminous pavement,
or concrete.
The removal, importation or filling of any material to or from
any parcel of land in the Town of Dudley is prohibited unless a written
permit therefor is obtained first from the Board. If said fill project
is in excess of 100,000 cubic yards over the life of the project or
projects, an Administrative Consent Order from the Massachusetts Department
of Environmental Protection or successor agencies or their equivalent
is required as part of the permitting process as herein provided.
A. No permit shall be necessary when material must be removed, imported
or filled for the following:
(1) To
construct a single- or multi-family building being built in accordance
with a permit issued by the Building Inspector. The importation or
removal of up to 1,500 cubic yards of material shall be exempt from
permitting. A permit from the Board is required for importation or
removal of material in excess of 1,500 cubic yards.
(2) To
construct a commercial building or facility that has met Board and
Town approvals for a permit. Importation or removal of material for
the purpose of such construction is permitted up to the amounts necessary
to complete the project according to approved plans. Additional importation
or removal beyond the scope of construction of over 3,000 cubic yards
shall require a permit from the Board, except for municipal or school
buildings or facilities.
(3) To
construct a public or private way within the Town that has met all
requisite Town approvals and after the developer has put a covenant
in place and recorded said covenant along with the conditions of approval
by the Board, or by the Planning Board, as apt. Additional importation
or removal of the material beyond the scope of construction of over
3,000 cubic yards shall require a permit from the Board. Definitive
subdivision plans approved by the Planning Board pursuant to the Subdivision
Control Law are exempt from this bylaw.
(4) To
operate a licensed landscape/materials facility to sell/remove materials
produced off site and hauled into said facility.
(5) General
property improvement or maintenance, such as the installation of swimming
pools, landscaping, construction of septic systems, and/or other property
improvement or maintenance. The importation or removal of up to 1,500
cubic yards of material for the purpose of such improvement or maintenance
shall be exempt from permitting. A permit from the Board is required
for importation or removal beyond 1,500 cubic yards. Removal, importation,
or filling of materials is not considered part of a normal operation
of a farm or garden and is not exempt from this bylaw.
B. Any project or series of projects which involves over the lifetime
of the project the importation or filling of greater than 100,000
cubic yards of material as referenced in the beginning of this section
for the purpose of reclamation or any other purpose may be regulated
by Administrative Consent Order (ACO) and/or other state or federal
regulations. (See Interim Policy on the Re-Use of Soil for Large Reclamation
Projects, Policy # COMM-15-01.) If the project is in compliance with
an ACO and/or other state or federal regulations, the Board may deem
that the requirements of this bylaw are satisfied and shall issue
a permit stating that the project is in compliance with this bylaw.
Such a permit must be issued before a project can commence. If at
any time during the project the Board determines that there are violations
of the terms of the ACO and/or any other applicable state or federal
regulations, the Board shall issue a cease-and-desist order and suspend
or revoke the permit.
Every permit issued shall be subject to the following conditions:
A. The portions of the permitted premises which have been filled or
excavated shall be graded and leveled to conform to the approved final
contour plan at least annually.
B. After final grading and leveling and not later than October 15 of
each year, the filled or the excavated portion shall be covered with
not less than four inches of suitable topsoil, and shall be seeded
and planted with suitable ground cover within 200 feet of current
excavation operations. All final contour slopes will conform to a
two to one maximum. That is for every two feet of horizontal travel
only a one-foot drop maximum is allowed.
C. No fill or excavation shall be undertaken within 100 feet of a public
or private way or within 150 feet of a building or structure, unless
the Board specifically finds that such fill or excavation will not
undermine the way or structure or otherwise be seriously detrimental
to the neighborhood and such finding is endorsed on the permit.
D. No swamp, pond, watercourse, or other wetland will be altered or
polluted in any way without all necessary permits, and no watercourses,
drains, swales, culverts or other water channeling contours or structures
shall be constructed unless shown on the plan submitted and approved.
E. For all filling projects, materials shall include only sand gravel,
clay stone, quarried rock or other subsurface products free from solid
waste, with an aggregate size of six inches or less, and have no solid
waste, refuse, junk, industrial waste, or volatile, explosive or flammable
materials. This material shall have no concentration of oil or hazardous
material, toxic substance or infectious biological material greater
than federal, state or local reportable or action criteria or greater
than pre-fill concentration of oil or hazardous material, toxic substance
or infectious biological material prevailing in the area to be filled.
The fill material shall also be free from organic material, such as
trees, stumps, waste, building materials, and construction and demolition
debris and shall contain 10% or less of total organic carbon by lab
analysis.
F. For all filling projects, the Board may require such borings and
test pits, inspections, monitoring, certifications, reports and test
by licensed site professionals, engineers, laboratories and/or other
qualified persons needed to evaluate the application and/or to monitor
performance under a permit and/or establish compliance with the conditions
of a permit and this bylaw. It shall be a condition of all permits
that the applicant pay for all such borings and test pits, inspections,
monitoring, certifications, reports and tests and that they be conducted
by persons selected by and responsible to the Board. Failure of any
applicant or permit holder to make timely payment for any borings
and test pits, inspection, certification, monitoring, report or test
or to carry out any step or to submit any information required by
the Board shall be grounds for denial of a permit and/or for issuance
of a cease-and-desist order and/or for revocation of the permit.
G. No fill or excavation will begin until security by surety bond, cash,
or other approved method is provided to ensure that the excavation
will be carried out in accordance with the permit and that the final
grades and cover are provided. Such security shall not be less than
$2,000 for each acre of the proposed site. The security shall be released
when suitable vegetation has been reestablished on the portion of
the site for which it was provided.
Every permit granted under this bylaw shall be valid for a period not to exceed one year. Any permit issued may be renewed by the Board, without hearing, if the proposed fill or excavation will be conducted in accordance with a plan previously approved and if the annual report required by §
158-8, Documentation and inspection, of this bylaw has been filed. Any expansion or extension of a permitted excavation will also be subject to a public hearing.
The Board of Selectmen shall set all application and renewal
fees. The applicant is responsible for peer review fees for new applications,
annual renewal of applications, inspections, plan review and site
visits for the Town's Engineer as deemed necessary.
Each day of fill or excavation without the permit required,
or otherwise, in violation of this bylaw shall constitute a separate
offense and shall be individually punishable by the fine provided
in MGL c. 40, § 21, Clause 17, or MGL c. 40, § 21D,
whichever is applicable.