Existing building laterals may be used in connection with new
buildings only when they are found to meet all requirements of this
chapter. NYCDEP shall approve the reuse of any existing laterals.
In all buildings in which any building drain is too low to permit
gravity flow to the public sewer, wastewater carried by such drain
shall be lifted by mechanical means and discharged to the building
lateral, on approval of NYCDEP.
All excavations required for the installation of a building
or street lateral shall be open trench work unless otherwise approved
by NYCDEP; provided, however, that NYDEP approval shall not be required
in cases where open trench work is not permitted by the New York State
Department of Transportation or Sullivan County Department of Public
Works as to state and county roads. Pipe laying and backfilling, regardless
of pipe material used, shall be performed in general accordance with
paragraphs 3 through 6 of ASTM Specification C-12, except that trench
width, measured at the top of the installed pipe, shall not exceed
the outside pipe diameter plus 14 inches and, except that no backfill
shall be placed until the work has been inspected. The depth of cover
over the pipe shall be sufficient to afford protection from frost,
but not in any case shall such depth be less than four feet. Where
it is physically impossible to provide cover of four feet, the depth
may be reduced to a minimum of two feet, and the pipe shall be insulated,
as approved by NYCDEP.
Laterals shall be tested for infiltration/exfiltration by:
A. Any full-pipe method described in §
36-405; or
B. By a suitable joint method, with the prior written approval of the
Inspector in consultation with NYCDEP.
All excavations for constructing building laterals shall be
adequately protected with barricades and lights so as to protect the
public from hazard. Streets, sidewalks, parkways, and other public
property disturbed, in the course of the work, shall be restored in
a manner satisfactory to the Town Engineer. When installation requires
disturbance of paved public roads and shoulders, restoration shall
involve backfilling to road grade. Shortly thereafter the Town or
County Department of Public Works (DPW), or New York State Department
of Transportation (DOT), as applicable, shall complete road and shoulder
restoration to the applicable standards.
For extension service area laterals, all costs associated with
the construction of the lateral from the sewer main to the property
owner's structure shall be borne by the City, and all maintenance
costs associated with that lateral following construction shall be
borne by the property owner. With respect to post-extension-project
laterals, all costs associated with the provisions of this article,
including construction and maintenance, shall be borne by the property
owner. The property owner shall indemnify NYCDEP or the Town as appropriate
from any loss or damage that may be directly or indirectly occasioned
by the installation of the building and street laterals, and connections
and appurtenances.
It shall be the responsibility of the property owner to cap the service connection of any structure either demolished or destroyed by fire or act of God unless the property owner can verify that he/she has plans to construct another structure with plumbing within six months of the demolition. Such capping must be completed within 60 days of the demolition of any structure. The capping should be done as close to the sewer main as possible, preferably within 20 feet. Notice of intent to cap a service connection shall be provided by the property owner (or its representative) to NYCDEP at least five business days prior to its commencement and shall be subject to inspection by NYCDEP. Costs for capping shall be borne by the property owner unless specified otherwise in any other agreement(s) between the Town and NYCDEP. Failure to comply with this requirement shall constitute a violation of this chapter and shall be subject to appropriate enforcement actions pursuant to Article
XII of this chapter.