Piling shall be used under the footings of any habitable building. Such piling are required, and must be installed for supporting any structure, including chimneys, and shall be not less than eight inch butts and six inch tips, and sufficient time shall be allowed for the piling to set before pouring footing and pilings are to extend into footings from two to four inches; and pilings not to be more than six feet on centers. All piling shall be capped with a concrete beam at least twelve (12) inches by sixteen (16) inches reinforced with three 3/8 inch rods in the top and bottom. The bottom of the beam shall be twelve (12) inches below the existing grade and a masonry wall built from the top of beam to the bottom of the sill.
Applications for permits to construct or reconstruct a bulkhead shall be accompanied with plans showing size, shape, configuration and location of such bulkhead, and specifications of material to be used in such construction and the manner in which such material shall be incorporated into the bulkhead.
The location of the construction of any bulkheads shall be along the established line thereof as shown on the Official Tax Map of the Borough of Avalon and the finished elevation thereof shall be a minimum of seven (7.0) feet above mean sea level based on NAVD 88 datum provided, however, that in case of a dispute as to location, height or construction requirements, the same shall be determined by the Construction Official. Prior to the issuance of a Certificate of Compliance by the Borough confirming compliance by the owner with provisions of this chapter, the owner shall submit to the Construction Official an elevation certificate from a licensed professional Surveyor certifying that the finished elevation of the bulkhead is at least seven (7.0) feet above mean sea level (NAVD 88) as required herein. Where drainage related issues are in dispute, the Borough Engineer shall review same with the Construction Official. Owners shall eliminate storm water drainage impact to adjacent properties through installation of necessary drainage devices.
The minimum specifications covering the construction and reconstruction of bulkheads shall be as follows:
a. 
All piles shall have a butt diameter of not less than 10 inches and a tip diameter of not less than five inches and shall have a length at least four feet greater than the sheet piles. All piles shall be fir, oak or pine and shall be a net retention of twelve (12) pounds of creosote oil per cubic foot treatment by the full cell process with creosote oil meeting the latest A.W.P.A. specifications. As an alternative, sheathing, wales and main piles shall be preservative treated to a net retention of two and one-half (2.5) pounds per cubic foot of chromated copper arsenate (CCA). Anchor piles shall be treated to a net retention of one (1.0) pound per cubic foot of CCA. This shall be in accordance with A.W.P.A. specifications C2, C3, and C18, as applicable.
b. 
All timber sheet piles and wales shall be creosote No. 1 common fir or North Carolina pine and shall have a net retention of twelve (12) pounds of creosote oil per cubic foot treatment by the full cell process with creosote oil meeting the latest A.W.P.A. specifications. Sheet piles shall be two inches x eight inches or two inches x 10 inches and shall have a penetration of at least forty (40%) percent of the actual length of sheathing. Wales shall be four inches x six inches. At least two wales will be required. A third wale shall be used where the finished top of bulkhead extends more than seven feet six inches above the existing bottom. All wale joints shall be staggered at pilings. It shall be permissible to use CCA treated materials in accordance with the specifications set forth in Subsection a above.
c. 
All bolts, tie rods and spikes shall be genuine galvanized steel of first quality. Each bolt and the rod shall be fitted with two galvanized steel washers. Bolts and tie rods to be galvanized after threading and shall have sufficient length of thread so that no blocking will be required. No re-threading or thread extension will be permitted. Bolts shall be 3/4 inches in diameter and of sufficient length to comply with the above requirements. Wales to be bolted to all piles. Tie rods shall be at least 3/4 inches in diameter and shall have a minimum length of fourteen (14) feet. One tie rod will be required for each main pile. Galvanized nails or spikes shall be as specified and each sheet pile shall receive not less than two nails or spikes per wale. Hardware shall meet the following requirements:
1. 
Tie rods: ASTM A-36 steel
2. 
Bolts: ASTM A-307 steel
3. 
Nuts: ASTM A-307 steel
4. 
Washers: ASTM A-47 for class 30-A cast iron
5. 
Spikes and Nails: Common wire type per AISI 1010/1020 steel
d. 
All timbers shall be set by the water jet method. Piles shall be set on not more than five feet on center and shall be tied to anchor piles with the tie rods previously specified. Anchor piles may be local oak or pine and shall have a butt diameter of not less than eight inches and a tip diameter of not less than four and one-half (4 1/2) inches and shall not be less than twelve (12) feet in length and the top of same shall be set at least two feet six inches below the elevation of the bulkhead cap. Two (2) rows of two inch sheet piles shall be used throughout the joints staggered. All timber which has been cut off at the top during construction shall be field treated with hot creosote treatment.
e. 
All pipe penetrations from storm water drainage shall extend a minimum of one pipe diameter from bulkhead face. Penetrations shall be constructed with a tight fit around pipe extension and shall include the installation of soil fabric on interior of bulkhead. Additional wales shall be installed at tip and bottom of stormwater pipe between adjacent piles.
f. 
All bulkhead construction shall incorporate bulkhead returns at adjacent property limits. Bulkhead returns shall extend a minimum of five feet landward of bulkhead line. Construction of bulkhead returns shall tie into adjacent bulkhead construction.
g. 
Alternate bulkhead material or construction methods must be submitted to the Construction Official for technical review and approval. The Construction Official shall consult with the Borough Engineer prior to granting any such approval. Acceptable alternate material shall conform to the following specifications:
1. 
Aluminum Construction:
Sheeting material
aluminum alloy 6061-TS ASTM B221
Allowable moment
5067 ft.-lbs.
Thickness
0.150 inches
2. 
Vinyl Construction:
Sheeting material
PVC Class 1-4013-13-0101 ASTM D4216
Allowable moment
3750 ft.-lbs.
Thickness
0.250 inches
h. 
Whenever a bulkhead design does not meet the specifications of this section, then such design shall be prepared by a New Jersey Licensed Professional Engineer and shall be in accordance with generally accepted engineering principles and standards. It shall be the obligation of the property owner and the owner's engineer to provide any supplemental information which may reasonably be required by the Construction Official and/or the Borough Engineer in order to evaluate and approve the proposed bulkhead design. A permit shall only be issued by the Construction Official after consultation with and review of the alternate design by the Borough Engineer. Designs which strictly comply with this section do not require preparation by a Professional Engineer and the same shall come under the review responsibilities of the Construction Official.
i. 
The decision of the Borough Construction Official and Engineer shall be final as to all issues related to construction material and bulkhead design. A property owner may be entitled to a relaxation of the requirements of this section based upon a showing of exceptional circumstances, hardship or other good cause. The decision of the Construction Official in such matters shall be binding unless the property owner appeals that decision to the Borough Council. Nothing contained herein shall be construed as limiting or attempting to limit the right of any property owner to seek judicial review from a court of competent jurisdiction under appropriate circumstances.
All private bulkheads within the Borough of Avalon shall be maintained in such a manner so as to pose no danger to the health, safety or welfare of the citizens of Avalon and so as not to pose any threat or danger to person or property. Said bulkhead shall be kept in such a state of repair as to prevent erosion or danger to abutting, adjacent or adjoining properties. Whenever a bulkhead has deteriorated to such a degree that it poses a danger, the Construction Official shall notify the property owner, in writing, of the nature of the deterioration and require the property owner to make necessary repairs. The property owner shall submit a plan of corrective action to the Construction Official not later than thirty (30) days from receipt of the notice. Upon approval of the corrective action by the Construction Official, the property owner shall complete all necessary repairs forthwith. If permits are required from the State of New Jersey or the Federal government or any agency or instrumentality thereof and such permits are required before any work can commence, then the property owner shall forthwith make application for all required penults upon approval by the Borough of the property owner's corrective action plan. In the event that a property owner fails to submit a corrective action plan or fails to implement that plan, then, in either of such events, the Borough may, at its option, make the necessary repairs and charge the cost thereof to the property owner in such manner as authorized by law.