[1969 Code § 88-77; Ord. No. 1978-6; Ord. No. 80-2; Ord. No. 85-10; Ord. No. 87-1; Ord. No. 93-16; Ord. No. 93-4]
Every application for the review of a site plan, minor subdivision and major subdivision by the Planning Board or the Board of Adjustment shall be accompanied by check for deposit on fees, payable to the Borough of Elmwood Park for the amount computed under the guidelines below:
a.
Any application involving commercial/industrial site plan, minor subdivision at the commercial/industrial zoned property and construction involving Chapter 28, "Flood Damage Prevention."
1.
Application fee = $150 (separate check).
2.
Board's Attorney fees (separate check):
(a)
$500 in the escrow account for professional fees in preparation of related work and resolutions.
(b)
$150 for the first acre of land or part thereof included within the site development plan.
(c)
An additional sum computed at the rate of $25 per acre of land, or part thereof, in excess of one acre.
3.
Engineering fees (separate check):
(a)
$600 for the first acre of land or part thereof included within the site development plan, plus:
$150 if Soil Conservation District approval is needed;
$250 if County approval is needed;
$250 if DEP approval is needed;
$250 if EPA approval is needed;
$250 if DOT approval is needed.
(b)
An additional sum computed at the rate of $60 per acre for each acre of land, or part thereof, in excess of one acre.
(c)
An additional sum computed at the rate of $0.05 per square foot for the first 5,000 square feet of building's gross floor area, or part thereof, included within the site development plan.
(d)
An additional sum computed at the rate of $0.03 per square foot for each square foot of building's gross floor area in excess of 5,000 square feet.
(e)
Under no circumstances shall the maximum amount of fees to be paid on any application with regard to engineering fees exceed the maximum fee of $2,000 for initial site plan review.
4.
Special/extended hearing fees. For any special hearing required or requested on any application or any extended hearing, extended hearing is defined to be any hearing in excess of two regular public meetings, the applicant shall, in addition to the above provided fees, deposit in an escrow account for professional fees:
$475 for the Board's Attorney (separate check).
$475 for the Borough Engineer (separate check);
$200 for the Board's Recorder (separate check).
b.
Any application not involving site plan approval:
1.
For a variance from the provisions of the Zoning Ordinance as provided by N.J.S.A. 40:55D-70, to include all variances other than use variances as defined herein, an application fee of $100 shall be paid.
2.
For a use variance from the provisions of this Zoning Ordinance as provided by N.J.S.A. 40:55D-70, an application fee of $100 shall be paid.
3.
Where the application for a variance pertains to property containing more than one building lot of a size of fifty-foot width and 100 feet in depth, the application fee, in addition to the foregoing fees, shall be $25 for each additional lot.
4.
Under any of the above conditions, the application fee will be accompanied by a deposit of $200 in an escrow account for professional fees in preparation of related resolutions, except for residential dimensional variances for which the deposit in an escrow account will be $50.
5.
For initial processing fees in connection with minor subdivision review other than involving commercial/industrial zoned properties and properties regulated by Chapter 28, "Flood Damage Prevention," the foregoing fees shall be posted:
Application fee = $100 (separate check)
Board's Attorney fee = $250 (separate check)
Engineering fee = $400 (separate check)
6.
For initial processing fees in connection with major subdivision review, the following fees shall be paid:
(a)
Up to five Lots, 5,000 square feet or Less, Each.
(1)
Sketch Plat.
Application fee = $100 (separate check)
Board's Attorney fee = $150 (separate check)
Engineering fee = $300 (separate check)
(2)
Preliminary Plat.
Application fee = $100 (separate check)
Board's Attorney fee = $300 (separate check)
Engineering fee (separate check) = $600 plus $100 if Soil Conservation District approval is needed;
$250 if County approval is needed;
$250 if DEP approval is needed;
$250 if EPA approval is needed;
$250 if DOT approval is needed.
(3)
Final Plat.
Application fee = $100 (separate check)
Board's Attorney fees = $200 (separate check)
Engineering fee = $400 (separate fee)
(b)
Six to 10 Lots, 5,000 square feet or Less Each.
(1)
Sketch Plat.
Application fee = $100 (separate check)
Board's Attorney fee = $150 (separate check)
Engineering fee = $300 (separate check)
(2)
Preliminary Plat.
Application fee = $100 (separate check)
Board's Attorney fee = $350 (separate check)
Engineering fee (separate check) = $700 plus $150 if Soil Conservation District approval is needed;
$250 if County approval is needed;
$250 if DEP approval is needed;
$250 if EPA approval is needed;
$250 if DOT approval is needed.
(3)
Final Plat.
Application fee = $100 (separate check)
Board's Attorney fee = $250 (separate check)
Engineering fee = $450 (separate check)
(c)
11 Lots or More and Any Number of Lots Having a Lot Area Over 5,000 Square Feet Each.
(1)
Sketch Plat.
Application fee = $100 (separate check)
Board's Attorney fee = $100 (separate check)
Engineering fee = $325 (separate check)
(2)
Preliminary Plat.
Application fee = $100 (separate check)
Board's Attorney fee = $400 (separate check)
Engineering fee (separate check) = $900, plus $150 if Soil Conservation District approval is needed;
$250 if County approval is needed;
$250 if DEP approval is needed;
$250 if EPA approval is needed;
$250 if DOT approval is needed.
(3)
Final Plat.
Application fee = $100 (separate check)
Board's Attorney fees = $300 (separate check)
Engineering fee = $500 (separate check)
(d)
Certificate of Occupancy (C.O.) or Certificate of Continued Occupancy (C.C.O.):
Nonresidential zones where the building floor area exceeds 5,000 square feet:
Application fee = $100 (separate check)
Board's Attorney fee = $150 (separate check)
Engineering fee = $200 (separate check)
(e)
Minor Site Plan.
Application fee = $100 (separate check)
Board's Attorney fee = $300 (separate check)
Engineering fee = $400 (separate check)
(f)
Special Hearing.
For any special hearing required or requested on any application or any extended hearing, extended hearing is defined to be any hearing in excess of two regular public meetings in connection with the major subdivision review, the applicant shall, in addition to the above provided fees, deposit in the escrow account for professional fees:
$475 for the Board's Attorney (separate check)
$475 for the Borough Engineer (separate check)
$200 for the Board's Recorder (separate check).
c.
In every application for the review of a site plan, minor subdivision or major subdivision involving either residential or commercial/industrial zoned property, the applicant shall deposit in the escrow account, for each work session after the first work session review, at which said application is being considered, the following fees:
Separate Checks | |
|---|---|
$400 | Borough Attorney |
$400 | Borough Engineer |
$150 | Board Recorder |
All checks are to be made to the order of the Borough of Elmwood Park.