The identified floodplain area shall consist of the following
specific areas:
A. The AE Area/District shall be those areas identified as an AE Zone
on the FIRM included in the FIS prepared by FEMA for which base flood
elevations have been provided.
(1) The AE Area without floodway shall be those areas identified as an
AE Zone on the FIRM included in the FIS prepared by FEMA for which
base flood elevations have been provided but no floodway has been
determined.
(a)
No permit shall be granted for any construction, development,
use, or activity within any AE Area/District without floodway unless
it is demonstrated that the cumulative effect of the proposed development
would not, together with all other existing and anticipated development,
increase the BFE more than one foot at any point.
(b)
No new construction or development shall be located within the
area measured 50 feet landward from the top-of-bank of any watercourse,
unless the appropriate permit is obtained from the Department of Environmental
Protection regional office.
B. The A Area/District shall be those areas identified as an A Zone
on the FIRM included in the FIS prepared by FEMA and for which no
base flood elevations have been provided. For these areas, elevation
and floodway information from other federal, state, or other acceptable
sources shall be used when available. Where other acceptable information
is not available, the base flood elevation shall be determined by
using the elevation of a point on the boundary of the identified floodplain
area which is nearest the construction site.
C. In lieu of the above, the municipality may require the applicant
to determine the elevation with hydrologic and hydraulic engineering
techniques. Hydrologic and hydraulic analyses shall be undertaken
only by professional engineers or others of demonstrated qualifications,
who shall certify that the technical methods used correctly reflect
currently accepted technical concepts. Studies, analyses, computations,
etc., shall be submitted in sufficient detail to allow a thorough
technical review by the municipality.
D. Community-identified flood hazard areas shall be those areas where
Borough of East Pittsburgh has identified local flood hazard or ponding
areas, as delineated and adopted on a "Local Flood Hazard Map" using
best available topographic data and locally derived information such
as flood of record, historic high-water marks, soils or approximate
study methodologies.
The identified floodplain area may be revised or modified by the Council where studies or information provided by a qualified agency or person documents the need for such revision. However, prior to any such change to the special flood hazard area, approval must be obtained from FEMA. Additionally, as soon as practicable, but not later than six months after the date such information becomes available, a community shall notify FEMA of the changes to the special flood hazard area by submitting technical or scientific data. See §
227-21B for situations where FEMA notification is required.
Should a dispute concerning any identified floodplain boundary
arise, an initial determination shall be made by the Borough of East
Pittsburgh, and any party aggrieved by this decision or determination
may appeal to the Council. The burden of proof shall be on the appellant.
Prior to development occurring in areas where annexation or
other corporate boundary changes are proposed or have occurred, the
community shall review flood hazard data affecting the lands subject
to boundary changes. The community shall adopt and enforce floodplain
regulations in areas subject to annexation or corporate boundary changes
which meet or exceed those in 44 CFR 60.3.