During any stage of the work, if the Township determines that the
permanent stormwater management facilities are not being installed
in accordance with the approved drainage plan, the Township shall
revoke the applicable permits until the facilities are correctly installed
or a revised drainage plan is submitted and approved, as specified
in this Part.
Provide a certificate from an engineer, architect, surveyor or other
qualified professional, as determined by the Township, certifying
that all required stormwater management facilities have been constructed
according to the approved drainage plan.
Provide a complete set of as-built drawings bearing the seal of the
same professional who provided the certificate referred to in § 26-142(1)(A)
above; provided, however, that neither as-built plans nor professional
certification shall be required for a minor subdivision.