Temporary use permits for temporary mobile home parks may be issued by the Zoning Administrator, subject to the following conditions for the construction office and the housing of construction workers.
A. 
That the location of a temporary mobile home park is necessary for construction offices and the housing of construction workers employed on an industrial or highway construction project.
B. 
That the request is filed by or certified to by the industry or Virginia Department of Transportation as being essential to the construction.
C. 
That a minimum area of 2,000 square feet be provided for each space.
D. 
That sanitary facilities conform to the State Health Department's requirements.
E. 
That the period for operating such temporary park shall not exceed the anticipated period of the construction or one year, whichever is less. An application for renewal may be submitted if more time is required to complete the project. However, such renewal applications must be filed at least 30 days prior to the expiration of the original temporary use permit. Subsequent renewals shall be treated as an original application.
F. 
The Zoning Administrator, in granting such a temporary use permit, may require the posting of a bond to assure that the temporary mobile home park will be removed and the site restored to good order at the expiration of the permit.
G. 
The Zoning Administrator, in consultation with the governing body, may establish additional requirements, without a public hearing, as shall be in the best interest of the public.