[Ord. No. 4-2005, 8/9/2005]
1.
Submission of a final application for approval shall occur not more than three years following the date of approval of the preliminary application. Failure to submit the final application within this period of time shall make the approval of the preliminary application null and void unless an extension of time has been granted. In any case, the applicant shall demonstrate his ability to substantially complete the required improvements within the five-year period provided by Act 247, as amended by Act 170 of 1988, the Municipalities Planning Code,[1] by providing the Township with a proposed schedule of completion.
[1]
Editor's Note: See 53 P.S. § 10101 et seq.
2.
Except for any modifications or changes required, the final application shall conform basically to the approved preliminary application. Where significant modifications or changes, other than those required, are made to an approved preliminary application, the application shall be submitted again as a preliminary application.