General format. The stormwater management plan shall include
a narrative and a set of plan drawings. Refer to sample checklist
in Appendix D.
A. A narrative describing the overall stormwater management concept
for the project.
(1) A determination of site conditions in accordance with the PA DEP
Stormwater BMP Manual. A detailed site evaluation shall be completed
for projects proposed environmentally sensitive areas, such as brownfields.
(2) Runoff calculations. Stormwater runoff design calculations for determining pre- and post-development discharge rates, for designing proposed stormwater control facilities and to demonstrate that the maximum practicable measures have been taken to meet the requirements of this chapter, must be submitted with the stormwater management plan. All calculations shall be prepared using the methods and data prescribed by general requirements in §
220-15. Refer to the Acceptable Computation Methodologies Table in §
220-20 of this chapter.
(a)
Runoff volume and rate shall be calculated according to generally
accepted methods such as those listed under Stormwater Management
Performance Standards, General Standards.
(b)
Detention/retention requirements, including volume, routing,
etc., for BMPs shall be calculated using commonly acceptable standard
methods.
(c)
Water quality calculations shall be determined by using the
PA DEP Stormwater BMP Manual 2006 or current PA DEP NPDES/PCSM calculation
spreadsheets or acceptable alternative method as set forth by the
Borough or WCD.
(3) Expected project time schedule for the installation of all temporary
and permanent stormwater control measures and devices. If the development
is to be constructed in stages, the applicant must describe how stormwater
facilities and BMPs will be sequentially installed to manage stormwater
runoff safely during each stage of development.
(4) The effect of the project (in terms of runoff rate, volumes, and
water quality) on surrounding properties and aquatic features and
on any existing stormwater conveyance system that may be affected
by the project.
(5) If appropriate, the narrative should provide justification as to
why any preferred stormwater management techniques, such as LID and
green infrastructure, as listed in this chapter, are not proposed
for use. Refer to the PA DEP Stormwater BMP Manual 2006 or most recent
edition for list of acceptable management techniques.
(6) Operation and maintenance program and responsible party(s) for permanent stormwater facilities and BMPs. Refer to Article
VI of this chapter.
B. The stormwater management plan drawings shall be drawn to a scale
of not less than one inch equals 100 feet. All sheets shall contain
a title block with name and address of applicant and designer, scale,
North arrow, legend and date of preparation.
(1) Existing and proposed features. The plan shall show the following:
(a)
Watershed location. Provide a key map (using USGS topo maps)
showing the location of the development site within the watershed(s)
and watershed subarea(s). On all site drawings, show the boundaries
of the watershed(s) and subarea(s) as they are located on the development
site and identify watershed name(s) and subarea number(s). Refer to
Appendix A, Watershed Performance District Maps.
(b)
Floodplain boundaries. Identify 100-year floodplains on the
development site (as appropriate) based on the Borough's flood
insurance study maps.
(c)
Natural features. Show all bodies of water (natural or artificial),
watercourses (permanent and intermittent), swales, wetlands and other
natural drainage courses on the development site, or which will be
affected by runoff from the development.
(d)
Soils. Provide an overlay showing soil types and boundaries
within the development site (consult WCD, SCS and U.S. Geological
Survey for information).
(e)
Contours. Show existing and final contours at intervals of two
feet; in areas with slopes greater than 15%, five-foot contour intervals
may be used.
(f)
Land cover. Show existing and final land cover classifications,
including existing and proposed improvements, as necessary to support
and illustrate the runoff calculations performed.
(g)
Drainage area delineations. Show the boundaries of the drainage
areas and points of interest employed in the runoff calculations performed.
(h)
Time of concentration flow paths. Show flow paths used for all
time of concentration calculations. Identify the different segments
of flow path used for travel time calculations for sheet flow, shallow
concentrated flow and channel flow regimes.
(i)
Utilities and easements. Show any existing utilities, stormwater
management or drainage controls and/or structures, such as sanitary
sewers, water, gas, electric, telecommunications, storm sewers, swales,
culverts, and any easements, which are located on the development
site, or which are off site but may be affected by runoff from the
development.
(2) Proposed stormwater facilities and BMPs. All proposed stormwater
runoff control measures must be shown on the plan including methods
for collecting, conveying and storing stormwater runoff onsite, which
are to be used both during and after construction. Erosion and sedimentation
controls shall be shown in accordance with applicable Borough and
WCD requirements. The plan shall provide information on the exact
type, location, sizing, design and construction of all proposed facilities
and relationship to the existing watershed drainage system.
(a)
If the development is to be constructed in stages, the applicant
must demonstrate that stormwater facilities will be installed to manage
stormwater runoff safely during each stage of development.
(b)
A schedule for the installation of all temporary and permanent
stormwater control measures and devices shall be included in the narrative
and shown on the site plan. This schedule shall include all stages
of construction identified as critical for the proper short-term and
long-term operation and performance of these control measures that
will need to be inspected by the stormwater design engineer, the Borough
Engineer and/or the WCD.
(c)
Operation and maintenance program and responsible party(s) for
permanent stormwater BMPs. Refer to Section VI of this chapter.
(3) Easements, rights-of-way, deed restrictions. BMPS and stormwater
management facilities that provide control for more than one lot shall
be located on a separate dedicated lot or in an easement. All existing
and proposed easements for any BMPs and stormwater management facilities
and controls for access, inspections, maintenance, repair, preservation
and use shall be shown on the plan and, if required, dedicated to
the entity, association or person required. The easement and the purpose
for the same shall be set forth on the plan and in the agreement required
by this chapter.
A list of any approvals/permits relative to stormwater management that will be required from other governmental agencies (e.g., Chapter 102 Erosion and Sedimentation Control, PennDOT HOP, Chapter
105 Water Obstruction and Encroachment Permit from PA DEP) and anticipated dates of submission/receipt should be included with the stormwater plan submission. Copies of permit applications may be requested by the Borough where they may be helpful for the plan review.
The application shall contain a proposed operation and maintenance plan (O&M) for all stormwater control facilities in accordance with the following and as described in Article
VI of this chapter:
A. Identify the responsible party and their responsibilities as described in §
220-36 (e.g., the Borough, property owner, private corporation, homeowner's association or other entity).
B. Include an operation and maintenance plan for all stormwater facilities, outlining the routine maintenance actions and schedules necessary to ensure proper operation of the stormwater control facilities as described in §
220-37.
C. Submit any legal agreements required to implement the maintenance program and copies of the maintenance agreement as required by this chapter. Refer to §
220-38.
D. Identify method of financing continuing operation and maintenance if the facility is to be owned by other than the Borough or a governmental agency. Refer to §
220-39.
Submit financial guarantees for timely installation, proper construction and structural integrity (maintenance guarantee) of stormwater facilities and BMPs as specified in Article
VII of this chapter.