Certificate of compliance. No land shall be occupied or used and
no building which is hereafter constructed, altered, added to, modified,
repaired, rebuilt or replaced shall be occupied until a certificate
of compliance is issued by the Planning and Zoning Administrator,
except where no permit is required, subject to the following provisions:
(1) The certificate of compliance shall show that the building or premises
or part thereof, and the proposed use, conform to the provisions of
this chapter.
(2) Application for such certificate shall be concurrent with the application
for a permit.
(3) If all ordinance provisions are met, the certificate of compliance
shall be issued within 10 days after written notification that the
permitted work is completed.
(4) The applicant shall submit a certification signed by a registered professional engineer, architect or land surveyor that the fill, lowest floor and floodproofing elevations are in compliance with the permit issued. Floodproofing measures also require certification by a registered professional engineer or architect that the requirements of §
370-30 are met.