A. 
Submission of site development stormwater plan.
(1) 
Whenever an applicant seeks municipal approval of a development subject to this Part 4, the applicant shall submit all of the required components of the Checklist for the Site Development Stormwater Plan at § 225-190C below as part of the submission of the application for approval.
(2) 
The applicant shall demonstrate that the project meets the standards set forth in this Part 4.
(3) 
The applicant shall submit four copies of the materials listed in the checklist for site development stormwater plans in accordance with § 225-190C of this Part 4.
B. 
Site development stormwater plan approval. The applicant's site development project shall be reviewed as a part of the review process by the municipal board or official from which municipal approval is sought. That municipal board or official shall consult the municipality's review engineer to determine if all of the checklist requirements have been satisfied and to determine if the project meets the standards set forth in this Part 4.
C. 
Submission of site development stormwater plan. The following information shall be required:
(1) 
Topographic base map. The reviewing engineer may require upstream tributary drainage system information as necessary. It is recommended that the topographic base map of the site be submitted which extends a minimum of 200 feet beyond the limits of the proposed development, at a scale of one inch equals 200 feet or greater, showing two-foot contour intervals. The map as appropriate may indicate the following: existing surface water drainage, shorelines, steep slopes, soils, erodible soils, perennial or intermittent streams that drain into or upstream of the Category One waters, wetlands and floodplains along with their appropriate buffer strips, marshlands and other wetlands, pervious or vegetative surfaces, existing man-made structures, roads, bearing and distances of property lines, and significant natural and man-made features not otherwise shown.
(2) 
Environmental site analysis. A written and graphic description of the natural and man-made features of the site and its surroundings should be submitted. This description should include a discussion of soil conditions, slopes, wetlands, waterways and vegetation on the site. Particular attention should be given to unique, unusual, or environmentally sensitive features and to those that provide particular opportunities or constraints for development.
(3) 
Project description and site plans. A map (or maps) at the scale of the topographical base map indicating the location of existing and proposed buildings roads, parking areas, utilities, structural facilities for stormwater management and sediment control, and other permanent structures. The map(s) shall also clearly show areas where alterations will occur in the natural terrain and cover, including lawns and other landscaping, and seasonal high groundwater elevations. A written description of the site plan and justification for proposed changes in natural conditions shall also be provided.
(4) 
Land use planning and source control plan. This plan shall provide a demonstration of how the goals and standards of §§ 225-183, 225-184, and 225-186 are being met. The focus of this plan shall be to describe how the site is being developed to meet the objective of controlling groundwater recharge, stormwater quality and stormwater quantity problems at the source by land management and source controls whenever possible.
(5) 
Stormwater management facilities map. The following information, illustrated on a map of the same scale as the topographic base map, shall be included:
(a) 
Total area to be disturbed, paved or built upon, proposed surface contours, land area to be occupied by the stormwater management facilities and the type of vegetation thereon, and details of the proposed plan to control and dispose of stormwater.
(b) 
Details of all stormwater management facility designs, during and after construction, including discharge provisions, discharge capacity for each outlet at different levels of detention and emergency spillway provisions with maximum discharge capacity of each spillway.
(6) 
Calculations.
(a) 
Comprehensive hydrologic and hydraulic design calculations for the predevelopment and post-development conditions for the design storms specified in § 225-184 of this Part 4.
(b) 
When the proposed stormwater management control measures depend on the hydrologic properties of soils or require certain separation from the seasonal high-water table, then a soils report shall be submitted. The soils report shall be based on on-site boring logs or soil pit profiles. The number and location of required soil borings or soil pits shall be determined based on what is needed to determine the suitability and distribution of soils present at the location of the control measure.
(7) 
Maintenance and repair plan. The design and planning of the stormwater management facility shall meet the maintenance requirements of § 225-191.
(8) 
Waiver from submission requirements. The municipal official or board reviewing an application under this Part 4 may, in consultation with the municipality's review engineer, waive submission of any of the requirements in § 225-190C(1) through (6) of this Part 4 when it can be demonstrated that the information requested is impossible to obtain or it would create a hardship on the applicant to obtain and its absence will not materially affect the review process.
A. 
Applicability. Projects subject to review as in § 225-180 of this Part 4 shall comply with the requirements of § 225-191B and C.
B. 
General maintenance.
(1) 
The design engineer shall prepare a maintenance plan for the stormwater management measures incorporated into the design of a major development.
(2) 
The maintenance plan shall contain specific preventative maintenance tasks and schedules; cost estimates, including estimated cost of sediment, debris, or trash removal; and the name, address, and telephone number of the person or persons responsible for preventative and corrective maintenance (including replacement). The plan shall contain information on BMP location, design, ownership, maintenance tasks and frequencies, and other details as specified in Chapter 8 of the NJ BMP Manual, as well as the tasks specific to the type of BMP, as described in the applicable chapter containing design specifics.
(3) 
If the maintenance plan identifies a person other than the property owner (for example, a developer, a public agency or homeowners' association) as having the responsibility for maintenance, the plan shall include documentation of such person's or entity's agreement to assume this responsibility, or of the owner's obligation to dedicate a stormwater management facility to such person under an applicable ordinance or regulation.
(4) 
Responsibility for maintenance shall not be assigned or transferred to the owner or tenant of an individual property in a residential development or project, unless such owner or tenant owns or leases the entire residential development or project. The individual property owner may be assigned incidental tasks, such as weeding of a green infrastructure BMP, provided the individual agrees to assume these tasks; however, the individual cannot be legally responsible for all of the maintenance required.
(5) 
If the party responsible for maintenance identified under § 225-191B(3) above is not a public agency, the maintenance plan and any future revisions based on § 225-191B(7) below shall be recorded upon the deed of record for each property on which the maintenance described in the maintenance plan must be undertaken.
(6) 
Preventative and corrective maintenance shall be performed to maintain the functional parameters (storage volume, infiltration rates, inflow/outflow capacity, etc.) of the stormwater management measure, including, but not limited to, repairs or replacement to the structure; removal of sediment, debris, or trash; restoration of eroded areas; snow and ice removal; fence repair or replacement; restoration of vegetation; and repair or replacement of nonvegetated linings.
(7) 
The party responsible for maintenance identified under § 225-191B(3) above shall perform all of the following requirements:
(a) 
Maintain a detailed log of all preventative and corrective maintenance for the structural stormwater management measures incorporated into the design of the development, including a record of all inspections and copies of all maintenance-related work orders;
(b) 
Evaluate the effectiveness of the maintenance plan at least once per year and adjust the plan and the deed as needed;
(c) 
File a report with the Municipal Engineer annually during the month of April stating or showing the condition of stormwater management facilities, maintenance work that has been performed, maintenance work that is necessary, and any safety hazards. The report shall include a schedule for performing needed maintenance, repairs, or safety improvements. The Municipal Engineer shall be notified when all such work has been completed; and
(d) 
Retain and make available, upon request by any public entity with administrative, health, environmental, or safety authority over the site, the maintenance plan and the documentation required by § 225-191B(6) and (7) above.
(8) 
The requirements of § 225-191B(3) and (4) do not apply to stormwater management facilities that are dedicated to and accepted by the municipality or another governmental agency, subject to all applicable municipal stormwater general permit conditions, as issued by the Department. Maintenance and inspection guidance can be found on the Department's website at https://www.njstormwater.org/maintenance_guidance.htm.
(9) 
In the event that the stormwater management facility becomes a danger to public safety or public health, or if it is in need of maintenance or repair, the municipality shall so notify the responsible person in writing. Upon receipt of that notice, the responsible person shall have 14 days to effect maintenance and repair of the facility in a manner that is approved by the Municipal Engineer or his designee. The municipality, in its discretion, may extend the time allowed for effecting maintenance and repair for good cause. If the responsible person fails or refuses to perform such maintenance and repair, the municipality or county may immediately proceed to do so and shall bill the cost thereof to the responsible person. Nonpayment of such bill may result in a lien on the property.
C. 
Nothing in this section shall preclude the municipality in which the major development is located from requiring the posting of a performance or maintenance guarantee in accordance with N.J.S.A. 40:55D-53.