A.
Installation of water main extensions will not be allowed when the ground is frozen unless the applicant agrees to pay for additional cost involved. The utility shall determine when frost conditions are encountered and will notify the owner or their authorized agent in advance when such condition is in effect.
B.
Any street or public right-of-way in which a main, valve or hydrant is to be placed should be graded to an established grade elevation as set and approved by the Director of Public Works. Any additional costs incurred by the Village in installing a main, valve or hydrant in a street or public right-of-way that is not to grade will be charged to, and made a lien upon, the property fronting on said extension. The contractor shall be responsible for maintenance and repair of any main extension for a period of one year after completion and approval unless specific written agreements specify otherwise.