The Township has adopted the procedures set forth herein which
shall be observed for all subdivision and/or land development applications.
A. Authority for plan approval. Final authority for approval or denial
of all subdivision and land development plans shall be the responsibility
of the Board of Supervisors in accordance with the procedures set
forth herein. Prior to action by the Board, all plans shall be referred
for review and recommendation to the Township Planning Commission,
Township Engineer, and such other agencies as deemed pertinent by
the Board or as required by law.
B. Plan classification. All applications for subdivision or land development
shall be classified as either major or minor as defined below:
(1)
Minor subdivision or land development. Any subdivision or land
development where:
(a)
No public improvement intended to be dedicated to the Township
is to be constructed, with the exception of public water or sewer
lines.
(b)
No street, public or private, is to be constructed, improved
or widened.
(c)
No more than five lots are proposed.
(d)
No further subdivision can occur within the resulting lots.
(e)
Lot line adjustments are made where no development is proposed.
(2)
All applications not considered minor in accordance with §
115-300B(1) shall be considered major subdivision or land development applications.
C. MPC Requirements. Preliminary and final plans shall be reviewed in
accordance with the requirements of the Pennsylvania Municipalities
Planning Code and as set forth herein.
D. Two phases are included in the procedure for approval of subdivision
and/or land development plans: preliminary and final. These phases
are required to afford the Thornbury Township Planning Commission
and the Board of Supervisors an adequate opportunity to review the
submission and to ensure that all recommendations are reflected in
the final plan and that all ordinance requirements are addressed.