The purpose of this chapter is to establish requirements for
construction, operation, and decommissioning of solar facilities;
to provide standards for the placement, design, construction, monitoring,
modification, and removal of solar facilities; address public safety,
minimize impacts on scenic, natural, and historic resources; and provide
adequate financial assurance for decommissioning.
This chapter shall apply to all solar facilities constructed
after the effective date of this chapter, including any physical modifications
to any existing solar energy facilities that materially alter the
type, configuration, or size of such facilities or other equipment.
When used in this chapter, the following words shall have the
following meanings:
ACREAGE COVERAGE
The total acres covered by arrays of photovoltaic panels,
including spaces between panels, buildings, inverters, substation,
switchyard, battery storage, ancillary equipment, and fencing around
these items, but excluding wildlife corridors, mandated setbacks,
wetlands, and other avoided natural or cultural features outside of
the security fencing on the project site.
AGGREGATE CAP
The aggregate cap is the maximum total acreage coverage of
utility/industrial solar facilities allowed, not a goal to be achieved.
All projects shall undergo careful consideration in the special use
permit process.
APPLICANT
The person or entity who submits an application to the locality
for a permit under this chapter.
BATTERY ENERGY STORAGE SYSTEM
Equipment or devices capable of absorbing electrical energy,
storing it for a period of time and redelivering that energy after
it has been stored.
DECOMMISSIONING
The procedure to disconnect, remove and properly dispose
of all above and underground infrastructure, equipment, facilities,
electrical components or devices, and to restore the property to prior
use or future use consistent with the Comprehensive Plan and future
zoning.
INTEGRATED PV
Photovoltaics incorporated into building materials, such
as shingles.
KARST
A landscape/feature/topography with sinkholes, springs and
streams that sink into subsurface caverns and conduits.
NET METERING
An electricity billing mechanism that credits solar energy
system owners for the electricity they add to the grid.
OPERATOR
The person responsible for the overall operation and management
of a facility.
OWNER
The person or entity who owns all or a portion of a facility.
PHOTOVOLTAIC or PV
Relating to materials and devices that absorb sunlight and
convert it directly into electricity.
RATED CAPACITY
The maximum capacity of a solar facility based on the sum
total of each photovoltaic system's nameplate capacity.
SITE PLAN
A plan showing all proposed improvements to the site. The
site plan shall include the location of all easements and rights-of-way
and other conditions relating to use, location, and bulk of buildings,
density of development, open space, public facilities, and such other
information as is required in applicable sections of this chapter
such as with conditional use, rezoning, or variance applications.
SOLAR FACILITY
The entire area, including acreage coverage, setbacks, buffers,
access roads, wildlife corridors, wetlands, and other natural features
of a facility that generates electricity from sunlight.
SOLAR FACILITY, INDUSTRIAL-/UTILITY-SCALE
A facility that generates electricity from sunlight primarily
for sale to a utility provider. An energy conversion system consisting
of photovoltaic panels, their support structures, and associated infrastructure,
such as but not limited to control, conversion, and transmission hardware,
and energy storage systems, occupying more than two acres of total
land area.
SOLAR FACILITY, MEDIUM-SCALE
A facility that generates electricity from sunlight primarily
to reduce on-site consumption of utility power for agricultural, commercial
and industrial applications. Ground-mounted sites occupy less than
two acres.
SOLAR FACILITY, SMALL-SCALE
A solar facility that generates electricity from sunlight
primarily to reduce on-site consumption of utility power for residential
applications that:
A.
Either generates less than 25 kilowatts (kW) of electricity
from sunlight, consisting of one or more photovoltaic (PV) systems
and other appurtenant structures and facilities within the boundaries
of the site; or
B.
Utilizes sunlight as an energy source to heat or cool buildings,
heat or cool water, or produce electrical or mechanical power by means
of any combination of collecting, transferring, or converting solar-generated
energy; and
C.
Meets at least one of the following criteria:
(1)
Has a disturbance zone equal to or less than one acre if ground
mounted;
(2)
Is mounted on or over a building, parking lot, or other previously
disturbed area; or
(3)
Utilizes integrated PV only (excluding passive solar homes).
D.
Should the use change from residential to any other use, the
definition and requirements of that use shall apply.
In addition to other requirements of the Page County Zoning
Ordinance and special use permit requirements, applications for
a utility-scale solar facility shall include the following information:
A. Preapplication meeting. In addition to the written notice requirements
set forth in § 15.2-2316.7 of the Code of Virginia, the
applicant shall schedule a preapplication meeting with Page County
to discuss the location, scale, and nature of the proposed use and
what will be expected during the process.
B. Comprehensive plan review. A 2232 review as required by the Code
of Virginia (§ 15.2-2232) for utility-scale solar facilities
shall be completed. This Code provision provides for a review by the
Planning Commission of public utility facility proposals to determine
if their general or approximate location, character and extent are
substantially in accord with the Comprehensive Plan or part thereof.
This requirement may be waived by the Board of Supervisors pursuant
to the authority set forth in § 15.2-2232(H).
C. Special use permit (SUP) application. A complete SUP application,
including:
(1) Documents demonstrating the ownership of the subject parcel(s) and,
if applicable, proof that a valid land lease agreement otherwise exists.
(2) Proof that the applicant has authorization to act upon the owner's
behalf.
(3) A letter of commitment from the utility company who will interconnect
to the facility and a statement of line capacity before and after
interconnection.
(4) List of all adjacent property owners, their tax map numbers, and
addresses.
(5) A description of the current use and physical characteristics of
the subject parcels.
(6) A description of the existing uses of nearby properties.
(7) A narrative identifying the applicant, owner of the proposed project,
a substantive history of the owner's solar project developments,
including all previous and current solar projects, any legal challenges
or claims in which they were named or identified, and the name of
any proposed entity under which they intend to operate, if different.
The narrative shall further describe the proposed solar facility project,
including an overview of the project and its location, maximum rated
capacity of the solar facility project, the approximate number of
panels, representative types, expected footprint of solar equipment
to be constructed, and type and location of interconnection to electrical
grid.
(8) Aerial imagery which shows the proposed location of the solar facility,
fenced area, driveways, and interconnection to the electrical grid
with the closest distance to all adjacent property lines and dwellings
along with main points of ingress/egress.
(9) Payment of the application fee and any additional review costs, advertising,
or other required staff time.
(10)
The applicant shall consult with the Department of Wildlife
Resources and provide a written recommendation regarding wildlife
corridors.
(11)
A preliminary site plan prepared by a Virginia licensed engineer,
which shall include the following:
(a)
A description of the subject parcels.
(b)
Property lines and setback lines. A land survey by a Virginia
licensed surveyor is required.
(c)
Existing and proposed buildings and structures, including preliminary
locations of the proposed solar panels and related equipment; the
location of proposed fencing, driveways, internal roads, and structures;
and the location of points of ingress/egress.
(d)
The location and nature of proposed buffers and screening elements,
including vegetative and constructed buffers.
(e)
Existing and proposed access roads, drives, turnout locations,
and parking.
(f)
Location of substations, electrical cabling from the solar facility
systems to the substations, ancillary equipment, buildings, and structures,
including those within any applicable setback.
(g)
Twenty sets (11 inches by 17 inches or larger), one reduced
copy (8 1/2 inches by 11 inches) and one electronic copy of the
site plan, including elevations and landscape plans as required.
D. A proposed grading plan shall be submitted with the special use permit
application, with a final grading plan to be approved prior to any
construction activity commencing on the project site.
E. A proposed landscaping maintenance plan shall be submitted with the special use permit application which takes into account the requirements set forth in §
134-7. A final landscaping maintenance plan shall be submitted and must be approved prior to any construction activity commencing on the project site.
F. A proposed decommissioning plan shall be submitted with the special
use permit application. A completed decommissioning plan, certified
by an engineer, shall be submitted and approved prior to, or along
with, the special use permit, detailing how the applicant proposes
to decommission the facility. The proposal shall include the following
information:
(1) The anticipated life of the project;
(2) A cost estimate for the decommissioning of the facility that shall
be prepared by a Virginia licensed professional engineer or contractor
who has expertise in the removal of large-scale solar facilities.
The decommissioning cost estimate shall detail the current cost in
dollars and projected costs over the life of the project without any
reduction for salvage value;
(3) How the estimate was determined;
(4) The manner and method of ensuring that funds will be available for
decommissioning;
(5) The proposed methods and steps required for removal of structures,
materials, buildings, roads, cabling, electrical components, operational
equipment, and any other associated facilities at the end of the anticipated
life of the project;
(6) Steps to restore the site to conditions prior to the commencement
of the project, including soil stabilization and revegetation (if
applicable);
(7) Impacts, if any, on the surrounding properties when decommissioned;
and
(8) The name and physical address of the person or entity responsible
for the decommissioning plan.
G. The following shall also be submitted with the application for a
special use permit:
(1) Traffic study modeling the construction and decommissioning processes.
The Virginia Department of Transportation will be responsible for
reviewing the study.
(2) An estimated construction schedule.
(3) An environmental inventory and impact study regarding any waterways,
wetlands, floodplains, and karst landscapes and topographies that
are adjacent to the project site, site and viewshed impacts, including
direct and indirect impacts to national and state forests, national
or state parks, wildlife management areas, conservation easements,
recreational areas, or any known historic or cultural resources within
five miles of the proposed project.
(4) An environmental site assessment and impact study prepared by a Virginia
certified engineer experienced in karst landscapes, including, but
not limited to, site investigations and an erosion and sediment control
plan confirming that the project will not adversely affect groundwater.
(5) A visual impact analysis demonstrating project siting and proposed
mitigation, if necessary, so that the solar facility minimizes impact
on the visual character of the County. The impact analysis shall include,
but not necessarily be limited to:
(a)
Accurate, to scale, photographic simulations showing the relationship
of the solar facility and its associated amenities and development
to its surroundings, including projected vegetative growth. The photographic
simulations shall show such views of solar structures from locations
such as property lines and roadways, as deemed necessary by the County
in order to assess the visual impact of the solar facility.
(b)
The total number of simulations and the perspectives from which
they are prepared shall be established by Page County after the preapplication
meeting.
(6) A written safety response plan prepared in coordination with the
Director of Emergency Services of Page County, Virginia.
H. Additional information may be required to be submitted with the application,
as determined by the Zoning Administrator, such as a scaled elevation
view of the property and other supporting drawings, photographs of
the proposed site, photo or other realistic simulations or modeling
of the proposed project from potentially sensitive locations as deemed
necessary by Page County to assess the visual impact of the project,
landscaping and screening plan, coverage map, and additional information
that may be necessary for a technical review of the proposal.
The applicant, owner, or operator of a utility-scale solar facility
shall coordinate with the County's emergency services staff to
provide annual materials, education and/or training to the departments
serving the property with emergency services in how to safely respond
to on site emergencies. In the event specialized equipment is necessary
to safely respond to on site emergencies, the applicant, owner, or
operator shall be responsible for furnishing the County with such
equipment.
The Board of Supervisors shall consider conditions when considering
a proposed utility-scale solar facility, including, but not limited
to, the following:
A. Maximum generating capacity of the solar facility.
B. More restrictive criteria pertaining to location and proximity of
facility to other uses, including but not limited to, residential
uses, highways, entry corridors, scenic highways.
C. More restrictive criteria pertaining to buffer zones and wildlife
corridors.
D. More restrictive criteria pertaining to prime soils, soil analysis,
water analysis, and deforestation.
E. Job fairs, hours of construction, public safety and EMS training.
F. In addition to the minimum setbacks set forth herein, the Board shall
determine minimum setbacks required of all panels, equipment, substations,
switchyards, and other ancillary structures, any karst features, wetlands,
waterways, rivers, creeks, and streams, floodplains, property lines
of parcels with existing dwellings, and property lines of all other
property without existing dwellings. These setbacks established by
the Board do not apply to internal lot lines that are included in
the project.
If any portion of this chapter shall be declared invalid by
a competent court of law, such invalidity shall not affect the validity
of any of the remaining provisions of this chapter.