[Added 6-8-2022 by Ord.
No. 2022-7]
As used in this chapter:
30-DAY PERIOD
The period of time prescribed by N.J.S.A. 40:49-5 in which
a property owner is afforded the opportunity to correct zoning and
solid waste disposal after a notice of violation pertaining to this
chapter has been issued.
100-YEAR FLOOD ELEVATION
Elevation of flooding having a 1% annual chance of being
equaled or exceeded in a given year which is also referred to as the
Base Flood Elevation.
500-YEAR FLOOD ELEVATION
Elevation of flooding having a 0.2% annual chance of being
equaled or exceeded in a given year.
A ZONES
Areas of Special Flood Hazard in which the elevation of the
surface water resulting from a flood that has a 1% annual chance of
equaling or exceeding the Base Flood Elevation (BFE) in any given
year shown on the Flood Insurance Rate Map (FIRM) zones A, AE, AH,
A1-A30, AR, AR/A, AR/AE, AR/A1-A30, AR/AH, and AR/AO. When used in
reference to the development of a structure in this chapter, A Zones
are not inclusive of Coastal A Zones because of the higher building
code requirements for Coastal A Zones.
ACCESSORY STRUCTURE
Accessory structures are also referred to as appurtenant
structures. An accessory structure is a structure which is on the
same parcel of property as a principal structure and the use of which
is incidental to the use of the principal structure. For example,
a residential structure may have a detached garage or storage shed
for garden tools as accessory structures. Other examples of accessory
structures include gazebos, picnic pavilions, boathouses, small pole
barns, storage sheds, and similar buildings.
AGRICULTURAL STRUCTURE
A structure used solely for agricultural purposes in which
the use is exclusively in connection with the production, harvesting,
storage, drying, or raising of agricultural commodities, including
the raising of livestock. Communities must require that new construction
or substantial improvements of agricultural structures be elevated
or floodproofed to or above the Base Flood Elevation (BFE) as any
other nonresidential building. Under some circumstances it may be
appropriate to wet-floodproof certain types of agricultural structures
when located in wide, expansive floodplains through issuance of a
variance. This should only be done for structures used for temporary
storage of equipment or crops or temporary shelter for livestock and
only in circumstances where it can be demonstrated that agricultural
structures can be designed in such a manner that results in minimal
damage to the structure and its contents and will create no additional
threats to public safety. New construction or substantial improvement
of livestock confinement buildings, poultry houses, dairy operations,
similar livestock operations and any structure that represents more
than a minimal investment must meet the elevation or dry-floodproofing
requirements of 44 CFR 60.3(c)(3).
AH ZONES
Areas subject to inundation by one-percent-annual-chance
shallow flooding (usually areas of ponding) where average depths are
between one and three feet. Base Flood Elevations (BFEs) derived from
detailed hydraulic analyses are shown in this zone.
ALTERATION OF A WATERCOURSE
A dam, impoundment, channel relocation, change in channel
alignment, channelization, or change in cross-sectional area of the
channel or the channel capacity, or any other form of modification
which may alter, impede, retard or change the direction and/or velocity
of the riverine flow of water during conditions of the base flood.
AO ZONES
Areas subject to inundation by one-percent-annual-chance
shallow flooding (usually sheet flow on sloping terrain) where average
depths are between one and three feet.
AREA OF SHALLOW FLOODING
A designated Zone AO, AH, AR/AO or AR/AH (or VO) on a community's
Flood Insurance Rate Map (FIRM) with a 1% or greater annual chance
of flooding to an average depth of one to three feet where a clearly
defined channel does not exist, where the path of flooding is unpredictable,
and where velocity flow may be evident. Such flooding is characterized
by ponding or sheet flow.
ASCE 24
The standard for Flood Resistant Design and Construction,
referenced by the building code and developed and published by the
American Society of Civil Engineers, Reston, VA. References to ASCE
24 shall mean ASCE 24-14 or the most recent version of ASCE 24 adopted
in the UCC Code [N.J.A.C. 5:23].
ASCE 7
The standard for the Minimum Design Loads for Buildings and
Other Structures, referenced by the building code and developed and
published by the American Society of Civil Engineers, Reston, VA,
which includes but is not limited to methodology and equations necessary
for determining structural and flood-related design requirements and
determining the design requirements for structures that may experience
a combination of loads including those from natural hazards. Flood
related equations include those for determining erosion, scour, lateral,
vertical, hydrostatic, hydrodynamic, buoyancy, breaking wave, and
debris impact.
BASE FLOOD ELEVATION (BFE)
The water surface elevation resulting from a flood that has
a one-percent or greater chance of being equaled or exceeded in any
given year, as shown on a published Flood Insurance Study (FIS), or
preliminary flood elevation guidance from FEMA. May also be referred
to as the "100-year flood elevation".
BASEMENT
Any area of the building having its floor subgrade (below
ground level) on all sides.
BEST AVAILABLE FLOOD HAZARD DATA
The most recent available preliminary flood risk guidance
FEMA has provided. The Best Available Flood Hazard Data may be depicted
on but not limited to Advisory Flood Hazard Area Maps, Work Maps,
or Preliminary FIS and FIRM.
BEST AVAILABLE FLOOD HAZARD DATA AREA
The areal mapped extent associated with the most recent available
preliminary flood risk guidance FEMA has provided. The Best Available
Flood Hazard Data may be depicted on but not limited to Advisory Flood
Hazard Area Maps, Work Maps, or Preliminary FIS and FIRM.
BEST AVAILABLE FLOOD HAZARD DATA ELEVATION
The most recent available preliminary flood elevation guidance
FEMA has provided. The Best Available Flood Hazard Data may be depicted
on but not limited to Advisory Flood Hazard Area Maps, Work Maps,
or Preliminary FIS and FIRM.
BREAKAWAY WALLS
Any type of wall subject to flooding that is not required
to provide structural support to a building or other structure and
that is designed and constructed such that, below the Local Design
Flood Elevation, it will collapse under specific lateral loads such
that (1) it allows the free passage of floodwaters, and (2) it does
not damage the structure or supporting foundation system. Certification
in the V Zone Certificate of the design, plans, and specifications
by a licensed design professional that these walls are in accordance
with accepted standards of practice is required as part of the permit
application for new and substantially improved V Zone and Coastal
A Zone structures. A completed certification must be submitted at
permit application.
BUILDING
Per the FHACA, "Building" shall mean a structure enclosed
with exterior walls or fire walls, erected and framed of component
structural parts, designed for the housing, shelter, enclosure, and
support of individuals, animals, or property of any kind. A building
may have a temporary or permanent foundation. A building that is intended
for regular human occupation and/or residence is considered a habitable
building.
COASTAL A ZONE
An Area of Special Flood Hazard starting from a Velocity
(V) Zone and extending up to the landward Limit of the Moderate Wave
Action delineation. Where no V Zone is mapped the Coastal A Zone is
the portion between the open coast and the landward Limit of the Moderate
Wave Action delineation. Coastal A Zones may be subject to wave effects,
velocity flows, erosion, scour, or a combination of these forces.
Construction and development in Coastal A Zones is to be regulated
similarly to V Zones/Coastal High Hazard Areas except as allowed by
ASCE 24.
COASTAL HIGH HAZARD AREA
An Area of Special Flood Hazard inclusive of the V Zone extending
from offshore to the inland limit of a primary frontal dune along
an open coast and any other area subject to high velocity wave action
from storms or seismic sources.
CONDITIONAL LETTER OF MAP REVISION
A Conditional Letter of Map Revision (CLOMR) is FEMA's
comment on a proposed project that would, upon construction, affect
the hydrologic or hydraulic characteristics of a flooding source and
thus result in the modification of the existing regulatory floodway,
the effective Base Flood Elevations (BFEs), or the Special Flood Hazard
Area (SFHA). The letter does not revise an effective NFIP map, it
indicates whether the project, if built as proposed, would be recognized
by FEMA. FEMA charges a fee for processing a CLOMR to recover the
costs associated with the review that is described in the Letter of
Map Change (LOMC) process. Building permits cannot be issued based
on a CLOMR, because a CLOMR does not change the NFIP map.
CONDITIONAL LETTER OF MAP REVISION - FILL
Fill (CLOMR-F) is FEMA's comment on a proposed project
involving the placement of fill outside of the regulatory floodway
that would, upon construction, affect the hydrologic or hydraulic
characteristics of a flooding source and thus result in the modification
of the existing regulatory floodway, the effective Base Flood Elevations
(BFEs), or the Special Flood Hazard Area (SFHA). The letter does not
revise an effective NFIP map, it indicates whether the project, if
built as proposed, would be recognized by FEMA. FEMA charges a fee
for processing a CLOMR to recover the costs associated with the review
that is described in the Letter of Map Change (LOMC) process. Building
permits cannot be issued based on a CLOMR, because a CLOMR does not
change the NFIP map.
CRITICAL BUILDING
Per the FHACA, shall mean that:
a.
It is essential to maintaining continuity of vital government
operations and/or supporting emergency response, sheltering, and medical
care functions before, during, and after a flood, such as a hospital,
medical clinic, police station, fire station, emergency response center,
or public shelter; or
b.
It serves large numbers of people who may be unable to leave
the facility through their own efforts, thereby hindering or preventing
safe evacuation of the building during a flood event, such as a school,
college, dormitory, jail or detention facility, day care center, assisted
living facility, or nursing home.
DEEP FOUNDATIONS
Per ASCE 24, shall mean deep foundations refer to those foundations
constructed on erodible soils in Coastal High Hazard and Coastal A
Zones which are founded on piles, drilled shafts, caissons, or other
types of deep foundations and are designed to resist erosion and scour
and support lateral and vertical loads as described in ASCE 7. Foundations
shall extend to 10 feet below Mean Water Level (MWL) unless the design
demonstrates that pile penetration will provide sufficient depth and
stability as determined by ASCE 24, ASCE 7, and additional geotechnical
investigations if any unexpected conditions are encountered during
construction.
DEVELOPMENT
Any manmade change to improved or unimproved real estate,
including but not limited to, buildings or other structures, tanks,
temporary structures, temporary or permanent storage of materials,
mining, dredging, filling, grading, paving, excavations, drilling
operations and other land-disturbing activities.
DRY FLOODPROOFING
A combination of measures that results in a non-residential
structure, including the attendant utilities and equipment as described
in the latest version of ASCE 24, being watertight with all elements
substantially impermeable and with structural components having the
capacity to resist flood loads.
ELEVATED BUILDING
A building that has no basement and that has its lowest elevated
floor raised above ground level by foundation walls, shear walls,
posts, piers, pilings, or columns. Solid perimeter foundations walls
are not an acceptable means of elevating buildings in V and VE Zones.
ELEVATION CERTIFICATE
An administrative tool of the National Flood Insurance Program
(NFIP) that can be used to provide elevation information, to determine
the proper insurance premium rate, and to support an application for
a Letter of Map Amendment (LOMA) or Letter of Map Revision based on
fill (LOMR-F).
ENCROACHMENT
The placement of fill, excavation, buildings, permanent structures
or other development into a flood hazard area which may impede or
alter the flow capacity of riverine flood hazard areas.
FEMA PUBLICATIONS
Any publication authored or referenced by FEMA related to
building science, building safety, or floodplain management related
to the National Flood Insurance Program. Publications shall include
but are not limited to technical bulletins, desk references, and American
Society of Civil Engineers Standards documents including ASCE 24.
FLOOD HAZARD AREA DESIGN FLOOD ELEVATION
Per the FHACA, shall mean the peak water surface elevation
that will occur in a water during the flood hazard area design flood.
This elevation is determined via available flood mapping adopted by
the State, flood mapping published by FEMA (including effective flood
mapping dated on or after January 31, 1980, or any more recent advisory,
preliminary, or pending flood mapping; whichever results in higher
flood elevations, wider floodway limits, greater flow rates, or indicates
a change from an A zone to a V zone or coastal A zone), approximation,
or calculation pursuant to the Flood Hazard Area Control Act Rules
at N.J.A.C. 7:13-3.1 - 3.6 and is typically higher than FEMA’s
base flood elevation. A water that has a drainage area measuring less
than 50 acres does not possess, and is not assigned, a flood hazard
area design flood elevation.
FLOOD INSURANCE RATE MAP (FIRM)
The official map on which the Federal Emergency Management
Agency has delineated both the areas of special flood hazards and
the risk premium zones applicable to the community.
FLOOD INSURANCE STUDY (FIS)
The official report in which the Federal Emergency Management
Agency has provided flood profiles, as well as the Flood Insurance
Rate Map(s) and the water surface elevation of the base flood.
FLOOD or FLOODING
Shall mean:
a.
A general and temporary condition of partial or complete inundation
of normally dry land areas from:
1.
The overflow of inland or tidal waters.
2.
The unusual and rapid accumulation or runoff of surface waters
from any source.
3.
Mudslides (i.e. mudflows) which are proximately caused by flooding
as defined in a2 of this definition and are akin to a river or liquid
and flowing mud on the surfaces of normally dry land areas, as when
earth is carried by a current of water and deposited along the path
of the current.
4.
The collapse or subsidence of land along the shore of a lake
or other body of water as a result of erosion or undermining caused
by waves or currents of water exceeding anticipated cyclical levels
or suddenly caused by an unusually high water level in a natural body
of water, accompanied by a severe storm, or by an unanticipated force
of nature, such as flash flood or an abnormal tidal surge, or by some
similarly unusual and unforeseeable event which results in flooding
as defined in paragraph a1 of this definition.
FLOODPLAIN MANAGEMENT REGULATIONS
Zoning ordinances, subdivision regulations, building codes,
health regulations, special purpose ordinances (such as a floodplain
ordinance, grading ordinance, and erosion control ordinance) and other
applications of police power. The term describes such State or local
regulations, in any combination thereof, which provide standards for
the purpose of flood damage prevention and reduction.
FLOODPROOFING
Any combination of structural and nonstructural additions,
changes, or adjustments to structures which reduce or eliminate flood
damage to real estate or improved real property, water and sanitary
facilities, structures, and their contents.
FLOODPROOFING CERTIFICATE
Certification by a licensed design professional that the
design and methods of construction for floodproofing a non-residential
structure are in accordance with accepted standards of practice to
a proposed height above the structure's lowest adjacent grade
that meets or exceeds the Local Design Flood Elevation. A completed
floodproofing certificate is required at permit application.
FLOODWAY
The channel of a river or other watercourse and the adjacent
land areas that must be reserved in order to discharge the base flood
without cumulatively increasing the water surface elevation more than
0.2 foot.
FREEBOARD
A factor of safety usually expressed in feet above a flood
level for purposes of floodplain management. "Freeboard" tends to
compensate for the many unknown factors that could contribute to flood
heights greater than the height calculated for a selected size flood
and floodway conditions, such as wave action, bridge openings, and
the hydrological effect of urbanization of the watershed.
FUNCTIONALLY DEPENDENT USE
A use that cannot perform its intended purpose unless it
is located or carried out in close proximity to water, including only
docking facilities, port facilities necessary for the loading or unloading
of cargo or passengers, and shipbuilding and ship repair facilities.
The term does not include long-term storage or related manufacturing
facilities.
HABITABLE BUILDING
Pursuant to the FHACA Rules (N.J.A.C. 7:13), shall mean a
building that is intended for regular human occupation and/or residence.
Examples of a habitable building include a single-family home, duplex,
multi-residence building, or critical building; a commercial building
such as a retail store, restaurant, office building, or gymnasium;
an accessory structure that is regularly occupied, such as a garage,
barn, or workshop; mobile and manufactured homes, and trailers intended
for human residence, which are set on a foundation and/or connected
to utilities, such as in a mobile home park (not including campers
and recreational vehicles); and any other building that is regularly
occupied, such as a house of worship, community center, or meeting
hall, or animal shelter that includes regular human access and occupation.
Examples of a non-habitable building include a bus stop shelter, utility
building, storage shed, self-storage unit, construction trailer, or
an individual shelter for animals such as a doghouse or outdoor kennel.
HARDSHIP
As related to Article
VII of this chapter, shall mean the exceptional hardship that would result from a failure to grant the requested variance. The City Council requires that the variance be exceptional, unusual, and peculiar to the property involved. Mere economic or financial hardship alone is not exceptional. Inconvenience, aesthetic considerations, physical handicaps, personal preferences, or the disapproval of one's neighbors likewise cannot, as a rule, qualify as an exceptional hardship. All of these problems can be resolved through other means without granting a variance, even if the alternative is more expensive, or requires the property owner to build elsewhere or put the parcel to a different use than originally intended.
HIGHEST ADJACENT GRADE
The highest natural elevation of the ground surface prior
to construction next to the proposed or existing walls of a structure.
HISTORIC STRUCTURE
Any structure that is:
a.
Listed individually in the National Register of Historic Places
(a listing maintained by the Department of Interior) or preliminarily
determined by the Secretary of the Interior as meeting the requirements
for individual listing on the National Register;
b.
Certified or preliminarily determined by the Secretary of the
Interior as contributing to the historical significance of a registered
historic district or a district preliminarily determined by the Secretary
to qualify as a registered historic district;
c.
Individually listed on a State inventory of historic places
in States with historic preservation programs which have been approved
by the Secretary of the Interior; or
d.
Individually listed on a local inventory of historic places
in communities with historic preservation programs that have been
certified either:
1.
By an approved State program as determined by the Secretary
of the Interior; or
2.
Directly by the Secretary of the Interior in States without
approved programs.
LAWFULLY EXISTING
Per the FHACA, shall mean an existing fill, structure and/or
use, which meets all Federal, State, and local laws, and which is
not in violation of the FHACA because it was established:
a.
Prior to January 31, 1980; or
b.
On or after January 31, 1980, in accordance with the requirements
of the FHACA as it existed at the time the fill, structure and/or
use was established.
Note: Substantially damaged properties and substantially improved
properties that have not been elevated are not considered "lawfully
existing" for the purposes of the NFIP. This definition is included
in this chapter to clarify the applicability of any more stringent
statewide floodplain management standards required under the FHACA.
|
LETTER OF MAP AMENDMENT
A Letter of Map Amendment (LOMA) is an official amendment,
by letter, to an effective National Flood Insurance Program (NFIP)
map that is requested through the Letter of Map Change (LOMC) process.
A LOMA establishes a property's location in relation to the Special
Flood Hazard Area (SFHA). LOMAs are usually issued because a property
has been inadvertently mapped as being in the floodplain but is actually
on natural high ground above the base flood elevation. Because a LOMA
officially amends the effective NFIP map, it is a public record that
the community must maintain. Any LOMA should be noted on the community's
master flood map and filed by panel number in an accessible location.
LETTER OF MAP CHANGE
The Letter of Map Change (LOMC) process is a service provided
by FEMA for a fee that allows the public to request a change in flood
zone designation in an Area of Special Flood Hazard on an Flood Insurance
Rate Map (FIRM). Conditional Letters of Map Revision, Conditional
Letters of Map Revision - Fill, Letters of Map Revision, Letters of
Map Revision-Fill, and Letters of Map Amendment are requested through
the Letter of Map Change (LOMC) process.
LETTER OF MAP REVISION
A Letter of Map Revision (LOMR) is FEMA's modification
to an effective Flood Insurance Rate Map (FIRM). Letter of Map Revisions
are generally based on the implementation of physical measures that
affect the hydrologic or hydraulic characteristics of a flooding source
and thus result in the modification of the existing regulatory floodway,
the effective Base Flood Elevations (BFEs), or the Special Flood Hazard
Area (SFHA). The LOMR officially revises the Flood Insurance Rate
Map (FIRM) and sometimes the Flood Insurance Study (FIS) report, and
when appropriate, includes a description of the modifications. The
LOMR is generally accompanied by an annotated copy of the affected
portions of the FIRM or FIS report. Because a LOMR officially revises
the effective NFIP map, it is a public record that the community must
maintain. Any LOMR should be noted on the community's master
flood map and filed by panel number in an accessible location.
LETTER OF MAP REVISION - FILL
A Letter of Map Revision Based on Fill (LOMR-F) is FEMA's
modification of the Special Flood Hazard Area (SFHA) shown on the
Flood Insurance Rate Map (FIRM) based on the placement of fill outside
the existing regulatory floodway may be initiated through the Letter
of Map Change (LOMC) Process. Because a LOMR-F officially revises
the effective Flood Insurance Rate Map (FIRM) map, it is a public
record that the community must maintain. Any LOMR-F should be noted
on the community's master flood map and filed by panel number
in an accessible location.
LICENSED DESIGN PROFESSIONAL
Either a New Jersey Licensed Professional Engineer, licensed
by the New Jersey State Board of Professional Engineers and Land Surveyors
or a New Jersey Licensed Architect, licensed by the New Jersey State
Board of Architects.
LICENSED PROFESSIONAL ENGINEER
A licensed professional engineer shall refer to individuals
licensed by the New Jersey State Board of Professional Engineers and
Land Surveyors.
LIMIT OF MODERATE WAVE ACTION (LiMWA)
Inland limit of the area affected by waves greater than 1.5
feet during the Base Flood. Base Flood conditions between the VE Zone
and the LiMWA will be similar to, but less severe than those in the
VE Zone.
LOCAL DESIGN FLOOD ELEVATION (LDFE)
The elevation reflective of the most recent available preliminary
flood elevation guidance FEMA has provided as depicted on but not
limited to Advisory Flood Hazard Area Maps, Work Maps, or Preliminary
FIS and FIRM which is also inclusive of freeboard specified by the
New Jersey Flood Hazard Area Control Act and Uniform Construction
Codes and any additional freeboard specified in a community's
ordinance. In no circumstances shall a project's LDFE be lower
than a permit-specified Flood Hazard Area Design Flood Elevation or
a valid NJDEP Flood Hazard Area Verification Letter plus the freeboard
as required in ASCE 24 and the effective FEMA Base Flood Elevation.
LOWEST ADJACENT GRADE
The lowest point of ground, patio, or sidewalk slab immediately
next a structure, except in AO Zones where it is the natural grade
elevation.
LOWEST FLOOR
Shall mean:
a.
In A Zones, the lowest floor is the top surface of the lowest
floor of the lowest enclosed area (including basement).
b.
In V Zones and coastal A Zones, the bottom of the lowest horizontal
structural member of a building is the lowest floor.
An unfinished or flood resistant enclosure, usable solely for
the parking of vehicles, building access or storage in an area other
than a basement is not considered a building's lowest floor provided
that such enclosure is not built so as to render the structure in
violation of other applicable non-elevation design requirements of
these regulations.
|
LOWEST HORIZONTAL STRUCTURAL MEMBER
In an elevated building in a Coastal A or Coastal High Hazard
Zone, shall mean the lowest beam, joist, or other horizontal member
that supports the building is the lowest horizontal structural member.
Grade beams installed to support vertical foundation members where
they enter the ground are not considered lowest horizontal members.
MANUFACTURED HOME
A structure that is transportable in one or more sections,
eight feet or more in width and greater than 400 square feet, built
on a permanent chassis, designed for use with or without a permanent
foundation when attached to the required utilities, and constructed
to the Federal Manufactured Home Construction and Safety Standards
and rules and regulations promulgated by the U.S. Department of Housing
and Urban Development. The term also includes mobile homes, park trailers,
travel trailers and similar transportable structures that are placed
on a site for 180 consecutive days or longer.
MARKET VALUE
The price at which a property will change hands between a
willing buyer and a willing seller, neither party being under compulsion
to buy or sell and both having reasonable knowledge of relevant facts.
As used in these regulations, the term refers to the market value
of buildings and structures, excluding the land and other improvements
on the parcel. Market value shall be determined by one of the following
methods (1) Actual Cash Value (replacement cost depreciated for age
and quality of construction), (2) tax assessment value adjusted to
approximate market value by a factor provided by the Property Appraiser,
or (3) established by a qualified independent appraiser.
NEW CONSTRUCTION
Structures for which the start of construction commenced
on or after the effective date of the first floodplain regulation
adopted by a community; includes any subsequent improvements to such
structures. New construction includes work determined to be a substantial
improvement.
NON-RESIDENTIAL
Pursuant to ASCE 24, shall mean any building or structure
or portion thereof that is not classified as residential.
ORDINARY MAINTENANCE AND MINOR WORK
Types of work excluded from construction permitting under
N.J.A.C. 5:23 in the March 5, 2018 New Jersey Register. Some of these
types of work must be considered in determinations of substantial
improvement and substantial damage in regulated floodplains under
44 CFR 59.1. These types of work include but are not limited to replacements
of roofing, siding, interior finishes, kitchen cabinets, plumbing
fixtures and piping, HVAC and air conditioning equipment, exhaust
fans, built in appliances, electrical wiring, etc. Improvements necessary
to correct existing violations of State or local health, sanitation,
or code enforcement officials which are the minimum necessary to assure
safe living conditions and improvements of historic structures as
discussed in 44 CFR 59.1 shall not be included in the determination
of ordinary maintenance and minor work.
RECREATIONAL VEHICLE
A vehicle that is built on a single chassis, 400 square feet
or less when measured at the largest horizontal projection, designed
to be self-propelled or permanently towable by a light-duty truck,
and designed primarily not for use as a permanent dwelling but as
temporary living quarters for recreational, camping, travel or seasonal
use. A recreational vehicle is ready for highway use if it is on its
wheels or jacking system, is attached to the site only by quick disconnect
type utilities and security devices and has no permanently attached
additions.
RESIDENTIAL
Pursuant to the ASCE 24 shall mean:
a.
Buildings and structures and portions thereof where people live
or that are used for sleeping purposes on a transient or non-transient
basis;
b.
Structures including but not limited to one- and two-family
dwellings, townhouses, condominiums, multi-family dwellings, apartments,
congregate residences, boarding houses, lodging houses, rooming houses,
hotels, motels, apartment buildings, convents, monasteries, dormitories,
fraternity houses, sorority houses, vacation time-share properties;
and
c.
Institutional facilities where people are cared for or live
on a twenty-four-hour basis in a supervised environment, including
but not limited to board and care facilities, assisted living facilities,
halfway houses, group homes, congregate care facilities, social rehabilitation
facilities, alcohol and drug centers, convalescent facilities, hospitals,
nursing homes, mental hospitals, detoxification facilities, prisons,
jails, reformatories, detention centers, correctional centers, and
prerelease centers.
SOLID WASTE DISPOSAL
The storage, treatment, utilization, processing or final
disposition of solid waste as described in N.J.A.C. 7:26-1.6 or the
storage of unsecured materials as described in N.J.A.C. 7:13-2.3 for
a period of greater than six months as specified in N.J.A.C. 7:26
which have been discharged, deposited, injected, dumped, spilled,
leaked, or placed into any land or water such that such solid waste
may enter the environment or be emitted into the air or discharged
into any waters, including groundwaters.
SPECIAL FLOOD HAZARD AREA
The greater of the following: (1) Land in the floodplain
within a community subject to a 1% or greater chance of flooding in
any given year, shown on the FIRM as Zone V, VE, V1-3-, A, AO, A1-30,
AE, A99, or AH; (2) Land and the space above that land, which lies
below the peak water surface elevation of the flood hazard area design
flood for a particular water, as determined using the methods set
forth in the New Jersey Flood Hazard Area Control Act in N.J.A.C.
7:13; (3) Riparian Buffers as determined in the New Jersey Flood Hazard
Area Control Act in N.J.A.C. 7:13. Also referred to as the AREA OF
SPECIAL FLOOD HAZARD.
START OF CONSTRUCTION
The Start of Construction shall mean as follows:
a.
For other than new construction or substantial improvements,
under the Coastal Barrier Resources Act (CBRA), this is the date the
building permit was issued, provided that the actual start of construction,
repair, rehabilitation, addition, placement or other improvement was
within 180 days of the permit date. The actual start means either
the first placement of permanent construction of a building on site,
such as the pouring of a slab or footing, the installation of piles,
the construction of columns or any work beyond the stage of excavation;
or the placement of a manufactured (mobile) home on a foundation.
For a substantial improvement, actual start of construction means
the first alteration of any wall, ceiling, floor, or other structural
part of a building, whether or not that alteration affects the external
dimensions of the building.
b.
For the purposes of determining whether proposed construction
must meet new requirements when National Flood Insurance Program (NFIP)
maps are issued or revised and Base Flood Elevation's (BFEs)
increase or zones change, the Start of Construction includes substantial
improvement, and means the date the building permit was issued, provided
the actual start of construction, repair, reconstruction, rehabilitation,
addition placement, or other improvement was within 180 days of the
permit date. The actual start means either the first placement of
permanent construction of a structure on a site, such as the pouring
of slab or footings, the installation of piles, the construction of
columns, or any work beyond the stage of excavation; or the placement
of a manufactured home on a foundation. Permanent construction does
not include land preparation, such as clearing, grading, and filling,
nor does it include the installation of streets and/or walkways; nor
does it include excavation for a basement, footings, piers, or foundations
or the erection of temporary forms; nor does it include the installation
on the property of accessory buildings, such as garages or sheds not
occupied as dwelling units or not part of the main structure. Such
development must also be permitted and must meet new requirements
when National Flood Insurance Program (NFIP) maps are issued or revised
and Base Flood Elevation's (BFEs) increase or zones change.
For a substantial improvement, the actual start of construction
means the first alteration of any wall, ceiling, floor, or other structural
part of a building, whether or not that alteration affects the external
dimensions of the building.
|
For determining if new construction and substantial improvements
within the Coastal Barrier Resources System (CBRS) can obtain flood
insurance, a different definition applies.
|
STRUCTURE
A walled and roofed building, a manufactured home, or a gas
or liquid storage tank that is principally above ground.
SUBSTANTIAL DAMAGE
Damage of any origin sustained by a structure whereby the
cost of restoring the structure to its before damaged condition would
equal or exceed 50% of the market value of the structure before the
damage occurred.
SUBSTANTIAL IMPROVEMENT
Any reconstruction, rehabilitation, addition, or other improvement
of a structure taking place over a period of time not greater than
two years, the cumulative cost of which equals or exceeds 50% of the
market value of the structure before the "start of construction" of
the improvement. The period of accumulation for determining whether
an improvement is a substantial improvement requires a review of all
improvements over a two-year period prior to the date of any proposed
improvement. This term includes structures which have incurred "substantial
damage", regardless of the actual repair work performed. The term
does not, however, include either:
a.
Any project for improvement of a structure to correct existing
violations of State or local health, sanitary or safety code specifications
which have been identified by the local code enforcement official
and which are the minimum necessary to assure safe living conditions;
or
b.
Any alteration of a "historic structure", provided that the
alteration will not preclude the structure's continued designation
as a "historic structure."
V ZONE CERTIFICATE
A certificate that contains a certification signed by a licensed
design professional certifying that the designs, plans, and specifications
and the methods of construction in V Zones and Coastal A Zones are
in accordance with accepted standards of practice. This certificate
also includes an optional Breakaway Wall Design Certification for
enclosures in these zones below the Best Available Flood Hazard Data
Elevation. A completed certification is required at permit application.
V ZONES
Areas of Special Flood Hazard in which the elevation of the
surface water resulting from a flood that has a 1% annual chance of
equaling or exceeding the Base Flood Elevation in any given year shown
on the Flood Insurance Rate Map (FIRM) zones V1-V30 and VE and is
referred to as the Coastal High Hazard Area.
VARIANCE
A grant of relief from the requirements of this section which
permits construction in a manner otherwise prohibited by this section
where specific enforcement would result in unnecessary hardship.
VIOLATION
A development that is not fully compliant with these regulations
or the flood provisions of the building code. A structure or other
development without the elevation certificate, other certifications,
or other evidence of compliance required in this chapter is presumed
to be in violation until such time as that documentation is provided.
WATER SURFACE ELEVATION
The height, in relation to the North American Vertical Datum
(NAVD) of 1988, (or other datum, where specified) of floods of various
magnitudes and frequencies in the flood plains of coastal or riverine
areas.
WATERCOURSE
A river, creek, stream, channel, or other topographic feature
in, on, through, or over which water flows at least periodically.
WET FLOODPROOFING
Floodproofing method that relies on the use of flood damage
resistant materials and construction techniques in areas of a structure
that are below the Local Design Flood Elevation by intentionally allowing
them to flood. The application of wet floodproofing as a flood protection
technique under the National Flood Insurance Program (NFIP) is limited
to enclosures below elevated residential and non-residential structures
and to accessory and agricultural structures that have been issued
variances by the community.