A. 
Applicants proposing regulated activities in the Township which are not exempt under § 178-6 shall submit a stormwater management site plan (SWM site plan) to the Township for review and approval in accordance with Articles III and IV. SWM site plans approved by the Township shall be on site throughout the duration of the regulated activity.
B. 
The stormwater management and runoff control criteria and standards in this chapter shall apply to the total proposed regulated activity, even if it is to take place in stages. The measurement of impervious surfaces shall include all of the impervious surfaces in the total proposed regulated activity even if the development is to take place in stages.
C. 
No regulated activity within the Township shall commence until:
(1) 
The Township issues approval of a SWM site plan, which demonstrates compliance with the requirements of this chapter; and
(2) 
The applicant has received a letter of adequacy or approval for the erosion and sediment control plan review by the Township and the Conservation District (if required), and has received all other local, state and federal permit approvals required for the project involving the regulated activity.
D. 
Neither submission of a SWM site plan under the provisions herein nor compliance with the provisions of this chapter shall relieve any person from responsibility for damage to any person or property otherwise imposed by law.
E. 
The applicant shall design the site to minimize disturbances to land, site hydrology, and natural resources, and to maintain the natural hydrologic regime, drainage patterns and flow conditions. The applicant shall apply the procedures set forth in § 178-18 for the overall site design and for selection, location and design of features and BMPs to be used to comply with the requirements of this chapter.
F. 
To the maximum extent practicable, postconstruction stormwater shall be discharged within the drainage area of the same stream or water body receiving the runoff prior to construction of the proposed regulated activity.
G. 
Existing drainage peak rate discharges up to and including the 100-year storm and the volume of runoff up to and including the two-year storm onto or through adjacent property(ies) or downgradient property(ies), including diffuse drainage discharge, shall not be altered in any manner by regulated activities under this chapter without written permission from, and, where applicable as determined by the Township an easement and agreement with, the affected landowner(s) for conveyance of discharges onto or through their property(ies). Altered stormwater discharges shall be subject to any applicable discharge criteria specified in this chapter.
H. 
Areas located outside of the site (i.e., areas outside of the regulated activity) that drain through a proposed site are not subject to water quality and volume control, infiltration, stream channel protection, or peak flow rate control requirements (as presented in §§ 178-19, 178-20, 178-21, and 178-22). Drainage facilities located on the site shall be designed to safely convey flows from outside of the site through the site.
I. 
If site conditions preclude capture of runoff from limited portions of the disturbed area for achieving water quality volume control standards, stream channel protection standards, and the two-year, five-year and ten-year storm event peak runoff rate reduction standards for new development required by this chapter, the applicant shall propose alternate methods to mitigate the bypass of the BMPs, subject to the approval of the Township Engineer. In no case shall resulting peak rate be greater than the predevelopment peak rate for the equivalent design storm.
J. 
For all regulated activities, erosion and sediment control BMPs shall be designed, implemented, operated, and maintained during the regulated activities (i.e., during construction) as required to meet the purposes and requirements of this chapter, to meet the erosion and sediment control requirements of the Township, if applicable, and to meet all requirements under Title 25 of the Pa. Code and the Clean Streams Law.[1]
[1]
Editor's Note: See 35 P.S. § 691.1 et seq.
K. 
For all regulated activities, permanent BMPs and conveyances shall be designed, implemented, operated, and maintained to meet the purposes and requirements of this chapter and to meet all requirements under Title 25 of the Pennsylvania Code, the Clean Streams Law,[2] and the Stormwater Management Act.[3]
[2]
Editor's Note: See 35 P.S. § 691.1 et seq.
[3]
Editor's Note: See 32 P.S. § 680.1 et seq.
L. 
The design of all BMPs and conveyances shall incorporate sound engineering principles and practices in a manner that does not aggravate existing stormwater problems as identified by the Township. The Township reserves the right to disapprove any design that would result in construction in an area affected by existing stormwater problem(s) or continuation of an existing stormwater problem(s).
M. 
Existing wetlands, either on the site or on an adjacent property, shall not be used to meet the minimum design requirements for stormwater management or stormwater runoff quality treatment. Stormwater discharges to existing wetlands shall not degrade the quality or hydrologic integrity of the wetland.
N. 
Hotspots runoff controls. Specific structural or pollution prevention practices may be required, as determined to be necessary by the Township Engineer, to pretreat runoff from hotspots prior to infiltration. Following is a list of examples of hotspots:
(1) 
Vehicle salvage yards and recycling facilities;
(2) 
Vehicle fueling stations;
(3) 
Vehicle service and maintenance facilities;
(4) 
Vehicle and equipment cleaning facilities;
(5) 
Fleet storage areas (bus, truck, etc.);
(6) 
Industrial sites based on Standard Industrial Classification Codes;
(7) 
Marinas (service and maintenance areas);
(8) 
Outdoor liquid container storage;
(9) 
Outdoor loading/unloading facilities;
(10) 
Public works storage areas;
(11) 
Facilities that generate or store hazardous materials;
(12) 
Commercial container nursery;
(13) 
Contaminated sites/brownfields;
(14) 
Other land uses and activities as designated by the Township.
O. 
Contaminated and brownfield sites. Where BMPs may contribute to the migration of contaminants in groundwater, the water quality and runoff volume, stream channel protection, and peak rate control standards shall be met; however, at the Township Engineer's discretion, the minimum infiltration requirement may be reduced or eliminated commensurate with the contaminated area and the required water quality and runoff control measures may be increased to mitigate the reduced infiltration requirement for the contaminated area.
P. 
Additional water quality requirements. The Township may require additional stormwater control measures for stormwater discharges to special management areas including, but not limited to:
(1) 
Water bodies listed as "impaired" by PADEP.
(2) 
Any water body or watershed with an approved total maximum daily load (TMDL).
(3) 
Areas of known existing flooding problems.
(4) 
Critical areas with sensitive resources (e.g., state-designated special protection waters, cold water fisheries, carbonate geology or other groundwater recharge areas that may be highly vulnerable to contamination, drainage areas to water supply reservoirs, etc.).
Q. 
Applicants shall utilize the Pennsylvania Stormwater Best Management Practices Manual (PA BMP Manual), as amended, or other sources acceptable to the Township Engineer, for testing and design standards for BMPs, and where there is a conflict with the provisions of this chapter, the most restrictive applies.
R. 
For areas underlain by karst or carbonate geology that may be susceptible to the formation of sinkholes and other karst features, the location, type, and design of infiltration BMPs shall be based on a site evaluation conducted by a qualified licensed professional and based on the PA BMP Manual (as amended) or other design guidance acceptable to the Township Engineer.
S. 
All regulated activities located within a special flood hazard area designated by the Federal Emergency Management Agency (FEMA) shall comply with Article VI of the Zoning Ordinance[4] of Pocopson Township and shall be designed to maintain the flood-carrying capacity of the floodway such that the base flood elevations are not increased, either upstream or downstream. The natural conveyance characteristics of the site and the receiving floodplain shall be incorporated into the stormwater management practices proposed for the site.
[4]
Editor's Note: See Ch. 250, Zoning.
T. 
Disturbance of existing ground cover during construction of the proposed regulated activity is prohibited within riparian buffer areas, as defined in § 250-6 of the Zoning Ordinance, except for activities otherwise approved by state or local agencies (e.g., stream restoration projects, road crossings, subsurface utility projects, etc.). At the Township Engineer's discretion, and with Conservation District and PADEP approval where necessary, the nondisturbance buffer may be reduced because of setback or other site constraints, but never be less than 10 feet.
The following permit or other regulatory requirements may apply to certain regulated activities and shall be met prior to (or as a condition of) final approval by Pocopson Township of the SWM site plan and prior to commencement of any regulated activities, as applicable:
A. 
All regulated activities subject to permit or regulatory requirements by PADEP under regulations at Title 25 Pennsylvania Code, Chapter 102, or erosion and sediment control requirements of the Township.
B. 
Work within natural drainageways subject to permit by PADEP under Title 25 Pennsylvania Code, Chapter 105.
C. 
Any BMP or conveyance that would be located in or adjacent to surface waters of the commonwealth, including wetlands, subject to permit by PADEP under Title 25 Pennsylvania Code, Chapter 105.
D. 
Any BMP or conveyance that would be located on or discharge to a state highway right-of-way, or require access to or from a state highway and be subject to approval by PennDOT.
E. 
Culverts, bridges, storm sewers, or any other facilities which must pass or convey flows from the tributary area and any facility which may constitute a dam subject to permit by PADEP under Title 25 Pennsylvania Code, Chapter 105.
A. 
No regulated activity within the Township shall commence until:
(1) 
The Township receives documentation that the applicant has received:
(a) 
A "letter of adequacy" from the Conservation District or other approval from PADEP in compliance with Title 25, Chapter 102, of the Pennsylvania Code of an erosion and sediment control plan for construction activities for projects where the area of disturbance exceeds one acre, where pond dredging is involved, or when the disturbance is associated with activities described under Title 25, Chapter 105, of the Pennsylvania Code permits;
(b) 
A PADEP NPDES Permit for Stormwater Discharges Associated with Construction Activities as required under Title 25 Pennsylvania Code, Chapter 92a, if applicable;
(c) 
Evidence of any other permit(s) or approvals required for the regulated activities; and
(2) 
An erosion and sediment control plan, meeting the requirements of Chapter 85, has been approved by the Township, if required.
B. 
A copy of the erosion and sediment control plan and any required permit(s), as required by PADEP regulations, shall be available on the site at all times.
C. 
Additional erosion and sediment control measures shall be applied where infiltration BMPs are proposed, at a minimum including those required in § 178-20L.
The applicant shall design the site to minimize the disturbances to land, site hydrology, and natural resources, and to maintain the natural hydrologic regime, drainage patterns and flow conditions. The applicant shall demonstrate in its SWM site plan (as required in § 178-27C) that the design sequence, objectives and techniques described below were applied to the maximum extent practicable in the site design of the regulated activity while complying with all other requirements of this chapter. The site design shall:
A. 
First, identify and delineate all existing natural resources and natural and man-made hydrologic features listed in § 178-27B(8), and in § 250-87B(8) that are located within the site, or receive discharge from, or may be impacted by the proposed regulated activity.
B. 
Second, provide a prioritized listing of these resources and features to identify:
(1) 
Those to be incorporated into the site design in a manner that provides protection from any disturbance or impact from the proposed regulated activity;
(2) 
Those to be protected from further disturbance or impact but for which the proposed regulated activity will provide improvement to existing conditions;
(3) 
Those that can be incorporated into and utilized as components of the overall site design in a manner that protects or improves their existing conditions while utilizing their hydrologic function within the limits of their available capacity (e.g., for infiltration, evapotranspiration, or reducing pollutant loads, runoff volume or peak discharge rates, etc.) to reduce the need for or size of constructed BMPs; and
(4) 
Those that may be considered for alteration, disturbance or removal.
C. 
Third, develop the site design to achieve the following:
(1) 
Recognize and incorporate the priorities identified in § 178-18B as the basis for the proposed site layout, grading, construction, and permanent ground cover design;
(2) 
Minimize earth disturbance (both surface and subsurface);
(3) 
Maximize protection of or improvement to natural resources and special management areas;
(4) 
Minimize the disturbance of natural site hydrology, in particular natural drainage features and patterns, discharge points and flow characteristics, natural infiltration patterns and characteristics, and natural channel and floodplain conveyance capacity;
(5) 
Incorporate natural hydrologic features and functions identified in § 178-18B into the site design to protect and utilize those features and their hydrologic functions to reduce the need for or size of constructed BMPs;
(6) 
Maximize infiltration and the use of natural site infiltration features, patterns and conditions, and evapotranspiration features;
(7) 
Apply selective grading design methods to provide final grading patterns or preserve existing topography in order to evenly distribute runoff and minimize concentrated flows;
(8) 
Minimize the cumulative area to be covered by impervious surfaces, and:
(a) 
Minimize the size of individual impervious surfaces;
(b) 
Separate large impervious surfaces into smaller components;
(c) 
Disconnect runoff from one impervious surface to another; and
(d) 
Utilize porous materials in place of impervious wherever practicable;
(9) 
Minimize the volume and peak discharge rates of stormwater generated;
(10) 
Avoid or minimize stormwater runoff pollutant loads and receiving stream channel erosion;
(11) 
Locate infiltration and other BMPs:
(a) 
At or as near to the source of generation as possible; and
(b) 
At depths that are as shallow as possible;
(12) 
Prioritize the selection and design of BMPs as follows:
(a) 
Nonstructural and vegetation BMPs; then
(b) 
Structural (surface and subsurface) BMPs;
(13) 
For flow volumes requiring conveyance from the source of generation to a BMP for management, give preference to open channel conveyance techniques that provide infiltration and water quality benefits, and landscaped-based management in common open space areas, where practicable; and
(14) 
Consider additional guidance for incorporating natural hydrology into the site and BMP designs, methods and techniques that support the objectives of § 178-18B and C. Appendix B[1] presents additional discussion of conservation design and low-impact development.
[1]
Editor's Note: Appendix B is included as an attachment to this chapter.
D. 
The procedures set forth above shall be utilized to the maximum extent practicable for the overall site design and selection, location and design of features and BMPs to be used to comply with the requirements of §§ 178-19, 178-20, 178-21 and 178-22.
To control postconstruction stormwater impacts from regulated activities and meet state water quality requirements, BMPs shall be provided in the site design that replicate predevelopment stormwater infiltration and runoff conditions, such that postconstruction stormwater discharges do not degrade the physical, chemical, or biological characteristics of the receiving waters. The green infrastructure and low-impact development (LID) practices provided in the PA BMP Manual, as well as the guidance on green infrastructure, LID and conservation design (CD) provided in Appendix B,[1] shall be utilized for all regulated activities wherever possible. The applicant shall comply with the following water quality and runoff volume requirements for all regulated activities, including all new development and redevelopment activities:
A. 
The postconstruction total runoff volume shall not exceed the predevelopment total runoff volume for all storms equal to or less than the two-year, twenty-four-hour duration precipitation (design storm). The water quality and runoff volume to be managed shall consist of any runoff volume generated by the proposed regulated activity over and above the predevelopment total runoff volume and shall be captured and permanently retained or infiltrated on the site. Permanent retention options may include, but are not limited to, reuse, evaporation, transpiration, and infiltration.
B. 
For modeling purposes, the predevelopment ground cover conditions shall be determined using the corresponding ground cover assumptions presented in § 178-23D of this chapter.
C. 
The design of the stormwater management facility outlet shall provide for protection from clogging and unwanted sedimentation.
D. 
BMPs that moderate the temperature of stormwater shall be used to protect the temperature of receiving waters. The applicant shall fulfill the requirements of the PADEP "Thermal Impact Analysis" for the "PAG-02 Stormwater Discharges Associated with Construction Activities, NOI for Coverage under General or Individual Permit" if they cannot meet the volume control requirements.
E. 
Water quality improvement shall be achieved in conjunction with achieving the infiltration requirements of § 178-20. The infiltration volume required under § 178-20 may be included as a component of the water quality volume. If the calculated water quality and runoff volume is greater than the volume infiltrated, then the difference between the two volumes shall be managed for water quality and runoff volume control through other techniques or practices but shall not be discharged from the site.
F. 
Runoff from the disturbed area shall be treated for water quality prior to entering existing waterways or water bodies. If a stormwater management practice does not provide water quality treatment, then water quality BMPs shall be utilized to provide pretreatment prior to the runoff entering the stormwater management practice.
G. 
The Township may require additional water quality and runoff control measures for stormwater discharging to special management areas such as those listed in § 178-15P.
H. 
When the regulated activity contains or is divided by multiple drainage areas, the water quality and runoff volume shall be separately addressed for each drainage area.
I. 
Weighted averaging of runoff coefficients shall not be used for manual computations or input data for water quality and runoff volume calculations.
J. 
Areas located outside of the site (i.e., areas outside of the regulated activity) may be excluded from the calculation of the water quality and runoff volume requirements.
K. 
Water quality and volume control practices shall be selected and designed to meet the criteria of § 178-18C that apply to water quality and volume control.
L. 
Evapotranspiration may be quantified and credited towards meeting volume requirements according to the PADEP Post Construction Stormwater Management (PCSM) Spreadsheet and Instructions (December 2020) or the most recent guidance from PADEP.
[1]
Editor's Note: Appendix B is included as an attachment to this chapter.
Providing for infiltration consistent with the natural hydrologic regime is required to compensate for the reduction in the recharge that occurs when the ground surface is disturbed or impervious surface is created or expanded. The applicant shall achieve the following infiltration requirements:
A. 
For regulated activities involving both new development and redevelopment, infiltration should be designed to accommodate the entire water quality and runoff volume required in § 178-19. Infiltration BMPs should be consistent with the design and infiltration period guidelines included in the PA BMP Manual or other PA DEP design guidance. If the runoff volume required by § 178-19 cannot be infiltrated, then alternative methods consistent with the PA BMP Manual (as amended) or other PA DEP guidance, such as the Managed Release Concept, may be used to manage this volume with approval from the Township Engineer.
B. 
For regulated activities involving both new development and redevelopment, the volume of a minimum of one inch of runoff from all regulated impervious surfaces shall be infiltrated.
C. 
If the requirements of § 178-20A or B cannot be physically accomplished, then the applicant shall be responsible for demonstrating with data or calculations to the satisfaction of the Township Engineer why this infiltration volume cannot be physically accomplished on the site (e.g., shallow depth to bedrock or limiting zone, open voids, steep slopes, etc.) and what alternative volume can be infiltrated;
D. 
Only if a minimum infiltration of the first 1/2 inch of runoff volume cannot be physically accomplished on the site, shall a waiver from § 178-20 be considered by the Township, in accordance with § 178-11.
E. 
If site conditions preclude capture of runoff from portions of the impervious surfaces, the infiltration volume for the remaining area shall be increased an equivalent amount to offset the loss.
F. 
When a project contains or is divided by multiple watersheds, the infiltration volume shall be separately addressed for each watershed.
G. 
Existing impervious surfaces located in areas outside of the site (i.e., outside of the regulated activity) may be excluded from the calculation of the required infiltration volume.
H. 
A detailed soils evaluation of the site shall be conducted by a qualified professional and at a minimum shall address soil permeability, depth to bedrock, and subgrade stability. The general process for designing the infiltration BMP shall be conducted by a qualified licensed professional and shall be consistent with the PA BMP Manual (as amended) (or other guidance acceptable to the Township Engineer) and in general shall:
(1) 
Analyze hydrologic soil groups as well as natural and man-made features within the site to determine general areas of suitability for infiltration practices. In areas where development on fill material is under consideration, conduct geotechnical investigations of subgrade stability; infiltration may not be ruled out without conducting these tests.
(2) 
Provide field tests such as double ring infiltrometer or other hydraulic conductivity tests (at the elevation of the proposed infiltration surface) to determine the appropriate hydraulic conductivity rate. Standard septic/sewage percolation tests are not acceptable for design purposes.
(3) 
Design the infiltration facility for the required retention (infiltration) volume based on field-determined infiltration capacity (and apply safety factor as per applicable design guidelines) at the elevation of the proposed infiltration surface.
(4) 
On-lot infiltration features are encouraged; however, it shall be demonstrated to the Township Engineer that the soils are conducive to infiltration on the identified lots.
I. 
Infiltration BMPs shall be selected based on suitability of soils and site conditions and shall be constructed on soils that have the following characteristics:
(1) 
A minimum depth of 24 inches between the bottom of the BMP and the top of the limiting zone. Additional depth may be required in areas underlain by karst or carbonate geology (see § 178-20M).
(2) 
An infiltration rate sufficient to accept the additional stormwater volume and drain completely as determined by field tests conducted by the applicant.
(3) 
The infiltration facility shall completely drain the retention (infiltration) volume within three days (72 hours) from the end of the design storm.
J. 
All infiltration practices shall:
(1) 
Be selected and designed to meet the criteria of § 178-18C that are applicable to infiltration;
(2) 
Be set back at least 15 feet from all buildings and features with subgrade elements (e.g., basements, foundation walls, etc.), and 10 feet from property or right-of-way lines, unless otherwise approved by the Township Engineer;
(3) 
For any infiltration practice that collects runoff from shared or multiple features and that is located within 25 feet of a building or feature with subgrade elements (e.g., basements, foundation walls, etc.), the bottom elevation shall be set below the elevation of the subgrade element.
K. 
Infiltration facilities shall, to the maximum extent practicable, be located to avoid introducing contaminants to groundwater:
(1) 
When a hotspot is located in the area draining to a proposed infiltration facility, an evaluation of the potential of groundwater contamination from the proposed infiltration facility shall be performed, including a hydrogeologic investigation (if requested by the Township Engineer) by a qualified licensed professional to determine what, if any, pretreatment or additional design considerations are needed to protect groundwater quality.
(2) 
When located within a "wellhead protection area" of a public water supply well, infiltration practices shall be in conformance with the applicable approved source water protection assessment or source water protection plan.
(3) 
The applicant shall provide appropriate safeguards against groundwater contamination for land uses that may cause groundwater contamination should there be a mishap or spill.
L. 
During site construction, all infiltration practice components shall be protected from compaction due to heavy equipment operation or storage of fill or construction material. Infiltration areas shall also be protected from sedimentation. Areas that are accidentally compacted or graded shall be remediated to restore soil composition and porosity. Adequate documentation to this effect shall be submitted to the Township Engineer for review. All areas designated for infiltration shall not receive runoff until the contributory drainage area has achieved final stabilization.
M. 
Where sediment transport in the stormwater runoff is anticipated to reach the infiltration system, appropriate permanent measures to prevent or collect sediment shall be installed prior to discharge to the infiltration system.
N. 
Where roof drains are designed to discharge to infiltration practices, they shall have appropriate measures to prevent clogging by unwanted debris (for example, silt, leaves and vegetation). Such measures shall include but are not limited to leaf traps, gutter guards and cleanouts.
O. 
All infiltration practices shall have appropriate positive overflow controls.
P. 
No sand, salt or other particulate matter may be applied to a porous surface material for winter ice conditions.
Q. 
The following procedures and materials shall be required during the construction of all subsurface facilities:
(1) 
Excavation for the infiltration facility shall be performed with equipment that will not compact the bottom of the seepage bed/trench or like facility.
(2) 
The bottom of the bed and/or trench shall be scarified prior to the placement of aggregate.
(3) 
Only clean aggregate with documented porosity, free of fines, shall be allowed.
(4) 
The tops, and sides of all seepage beds, trenches, or like facilities shall be covered with drainage fabric. Where the seepage bed, trench or like facility will be subject to vehicular traffic, the bottom of the bed may be required to be covered with fabric as well. Fabric shall be nonwoven fabric acceptable to the Township Engineer.
(5) 
Stormwater shall be distributed throughout the entire seepage bed/trench or like facility and provisions for the collection of debris shall be provided in all facilities.
For regulated activities involving new development with one or more acres of earth disturbance, the applicant shall comply with the following stream channel protection requirements to minimize stream channel erosion and associated water quality impacts to the receiving waters:
A. 
The peak flow rate of the postconstruction two-year, twenty-four-hour design storm shall be reduced to the predevelopment peak flow rate of the one-year, twenty-four-hour duration precipitation, using the SCS Type II distribution.
B. 
To the maximum extent practicable, and unless otherwise approved by the Township Engineer, the postconstruction one-year, twenty-four-hour storm flow shall be detained for a minimum of 24 hours and a maximum not to exceed 72 hours from a point in time when the maximum volume of water from the one-year, twenty-four-hour storm is stored in a proposed BMP (i.e., when the maximum water surface elevation is achieved in the facility). Release of water can begin at the start of the storm (i.e., the invert of the orifice is at the invert of the proposed BMP).
C. 
For modeling purposes, the predevelopment ground cover conditions shall be determined using the corresponding ground cover assumptions presented in § 178-23D of this chapter.
D. 
The minimum orifice size in the outlet structure to the BMP shall be three inches in diameter unless otherwise approved by the Township Engineer, and a trash rack shall be installed to prevent clogging. For sites with small drainage areas contributing to the BMP that do not provide enough runoff volume to allow a twenty-four-hour attenuation with the three-inch orifice, the calculations shall be submitted showing this condition.
E. 
When the calculated orifice size is below three inches, gravel filters (or other methods) are recommended to discharge low-flow rates subject to the Township Engineer's satisfaction. When filters are utilized, maintenance provisions shall be provided to ensure filters meet the design function.
F. 
All proposed stormwater management facilities shall make use of measures to extend the flow path and increase the travel time of flows in the facility.
G. 
When a regulated activity contains or is divided by multiple drainage areas, the peak flow rate control shall be separately addressed for each drainage area.
The applicant shall comply with the following peak flow rate control requirements for all regulated activities including those that involve new development and redevelopment.
A. 
Postconstruction peak flow rates from any regulated activity shall not exceed the predevelopment peak flow rates as shown for each of the design storms specified in Table 178-22.1.
Table 178-22.1
Peak Rate Control Standards
(Peak Flow Rate of the Postconstruction Design Storm Shall Be Reduced to the Peak Flow Rate of the Corresponding Predevelopment Design Storm Shown in the Table)
Postconstruction Design Storm Frequency
(24-Hour Duration)
Predevelopment Design Storm
New Development Regulated Activities
Redevelopment Regulated Activities
2-year
1-year
2-year
5-year
2-year
5-year
10-year
2-year
10-year
25-year
25-year
25-year
50-year
50-year
50-year
100-year
100-year
100-year
B. 
For modeling purposes, the predevelopment ground cover conditions shall be determined using the corresponding ground cover assumptions presented in § 178-23D of this chapter.
C. 
For regulated activities involving only redevelopment, no peak flow rate controls are required when and only if the total regulated impervious surface area is at least 20% less than the total existing impervious surface area to be disturbed by the regulated activity. In all cases where this requirement is not met, the redevelopment regulated activity shall achieve the peak flow rate controls presented in Table 178-22.1, using the redevelopment ground cover assumptions presented in § 178-23D. This design criterion for redevelopment is only permitted with approval of Township Engineer. It shall result in no impact on downstream properties.
D. 
Only the area of the proposed regulated activity shall be subject to the peak flow rate control standards of this chapter. Undisturbed areas for which the discharge point has not changed are not subject to the peak flow rate control standards.
E. 
Areas located outside of the site (i.e., areas outside of the regulated activity) that drain through a proposed site are not subject to peak flow rate control requirements. Drainage facilities located on the site shall be designed to safely convey flows from outside of the site through the site.
F. 
When a regulated activity contains or is divided by multiple drainage areas, the peak flow rate controls shall be separately addressed for each drainage area.
G. 
The effect of structural and nonstructural stormwater management practices implemented as part of the overall site design may be taken into consideration when calculating total storage volume and peak flow rates.
A. 
Stormwater runoff from all regulated activity sites with a drainage area of greater than five acres shall be calculated using a generally accepted calculation technique(s) that is based on the NRCS Soil Cover Complex Method. Table 309.1 summarizes acceptable computation methods. The method selected for use shall be based on the individual limitations and suitability of each method for a particular site. The use of the Rational Method to estimate peak discharges for drainage areas greater than five acres shall be permitted only upon approval by the Township Engineer.
Table 178-23.1
Acceptable Computation Methodologies for SWM Site Plan
Method
Developed By
Applicability
TR-20 (or commercial computer package based on TR-20)
USDA NRCS
Applicable where use of full hydrology computer model is desirable or necessary
TR-55 (or commercial computer package based on TR-55)
USDA NRCS
Applicable for land development plans where limitations described in TR-55 are met
HEC-1/HEC-HMS
U.S. Army Corps of Engineers
Applicable where use of a full hydrologic computer model is desirable or necessary
Rational Method (or commercial computer package based on Rational Method)
Emil Kuichling (1889)
For sites up to 5 acres, or as approved by the Township
Other methods
Varies
Other computation methodologies approved by the Township
B. 
All calculations using the Soil Cover Complex Method shall use the appropriate design rainfall depths for the various return period storms consistent with this chapter. Rainfall depths used shall be obtained from the latest version of the Precipitation-Frequency Atlas of the United States, National Oceanic and Atmospheric Administration (NOAA), National Weather Service, Hydrometeorological Design Studies Center, Silver Spring, Maryland (NOAA Atlas 14), values consistent with a partial duration series. When stormwater calculations are performed for routing procedures or infiltration, water quality and runoff volume functions, the duration of rainfall shall be 24 hours.
C. 
All calculations using the Rational Method shall use rainfall intensities consistent with appropriate times-of-concentration (duration) and storm events with rainfall intensities obtained from NOAA Atlas 14 partial duration series estimates, or the latest version of the PennDOT Drainage Manual (PDM Publication 584). Times-of-concentration shall be calculated based on the methodology recommended in the respective model used. Times of concentration for channel and pipe flow shall be computed using Manning's equation.
D. 
The applicant shall utilize the following ground cover assumptions for all predevelopment water quality and runoff volume, infiltration volume and peak flow rate calculations:
(1) 
For regulated activities involving new development, the following ground cover assumptions shall be used:
(a) 
For areas that are woods (as defined in Article II of this chapter), predevelopment calculations shall assume ground cover of "woods in good condition."
(b) 
For all other areas (including all impervious surfaces), predevelopment calculations shall assume ground cover of "meadow."
(2) 
For regulated activities involving redevelopment, the following ground cover assumptions shall be used:
(a) 
For areas that are woods (as defined in Article II of this chapter), predevelopment calculations shall assume ground cover of "woods in good condition."
(b) 
For areas that are not woods or not impervious surfaces, predevelopment calculations shall assume ground cover of "meadow."
(c) 
For areas that are impervious surfaces, predevelopment calculations shall assume at least 20% of the existing impervious surface area to be disturbed as "meadow" ground cover.
(3) 
The applicant shall determine which stormwater standards apply to the proposed regulated activity as follows:
(a) 
Stormwater standards for new development shall apply to all proposed regulated activities that involve only new development activities as defined in this chapter.
(b) 
Stormwater standards for redevelopment shall apply to all proposed regulated activities that involve only redevelopment activities as defined in this chapter.
(c) 
At the discretion of the Township Engineer, regulated activities that involve a combination of both new development and redevelopment activities, as defined in this chapter, may either:
[1] 
Apply the stormwater standards (redevelopment or new development) that are associated with the activity that involves the greatest amount of land area; or
[2] 
Apply the redevelopment and new development stormwater standards to the corresponding redevelopment and new development portions of the proposed regulated activity.
E. 
Runoff curve numbers (CN) for both predevelopment and proposed (postconstruction) conditions to be used in the Soil Cover Complex Method shall be obtained from Table C-1 in Appendix C[1] of this chapter.
[1]
Editor's Note: Appendix C is included as an attachment to this chapter.
F. 
Runoff coefficients (C) for both predevelopment and proposed (postconstruction) conditions for use in the Rational Method shall be obtained from Table C-2 in Appendix C[2] of this chapter.
[2]
Editor's Note: Appendix C is included as an attachment to this chapter.
G. 
Weighted averaging of runoff coefficients shall not be used for manual computations or input data for water quality and runoff volume calculations.
H. 
Hydraulic computations to determine the capacity of pipes, culverts, and storm sewers shall be consistent with methods and computations contained in the Federal Highway Administration Hydraulic Design Series Number 5 (Publication No. FHWA-NHI-01-020 HDS No. 5, as amended). Hydraulic computations to determine the capacity of open channels shall be consistent with methods and computations contained in the Federal Highway Administration Hydraulic Engineering Circular Number 15 (Publication No. FHWA-NHI-05-114 HEC 15, as amended). Values for Manning's roughness coefficient (n) shall be consistent with Table C-3 in Appendix C[3] of the chapter.
[3]
Editor's Note: Appendix C is included as an attachment to this chapter.
I. 
Runoff calculations shall include the following assumptions:
(1) 
Average antecedent moisture conditions (for the Soil Cover Complex Method only for example, TR-55, TR-20).
(2) 
A Type II distribution storm (for the Soil Cover Complex Method only for example, TR-55, TR-20).
A. 
Any BMP intended to hold standing water for four days or longer shall be designed to incorporate biologic controls consistent with the West Nile Guidance found in Appendix D,[1] PADEP document 363-0300-001 "Design Criteria - Wetlands Replacement/Monitoring" (as amended) (or contact the Pennsylvania State Cooperative Wetland Center or the Penn State Cooperative Extension Office for design information).
[1]
Editor's Note: Appendix D is included as an attachment to this chapter.
B. 
Any stormwater basin required or regulated by this chapter designed to store runoff and requiring a berm or earthen embankment shall be designed to provide an emergency spillway to safely convey flow up to and including the 100-year proposed conditions. The height of embankment shall provide a minimum one foot of freeboard above the maximum pool elevation computed when the facility functions for the 100-year proposed conditions inflow. Should any BMP require a dam safety permit under Pa. Code Chapter 105 regulations, the facility shall be designed in accordance with and meet the regulations of Pa. Code Chapter 105 concerning dam safety. Pa. Code Chapter 105 may require the safe conveyance of storms larger than 100-year event.
C. 
Any drainage conveyance facility and/or channel not governed by Pa. Code Chapter 105 regulations shall be designed to convey, without damage to the drainage facility or roadway, runoff from the twenty-five-year storm event. Larger storm events (fifty-year and 100-year storms) shall also be safely conveyed in the direction of natural flow without creating additional damage to any drainage facilities, nearby structures, or roadways.
D. 
Conveyance facilities to or exiting from stormwater management facilities (i.e., detention basins) shall be designed to convey the 100-year design flow to or from the facility.
E. 
Roadway crossings or structures located within designated floodplain areas shall be able to convey runoff from a 100-year design storm consistent with Federal Emergency Management Agency National Flood Insurance Program floodplain management requirements.
F. 
Any stormwater management facility located within a PennDOT right-of-way shall comply with PennDOT minimum design standards and permit submission and approval requirements.
G. 
Adequate erosion protection and energy dissipation shall be provided along all open channels and at all points of discharge. Design methods shall be consistent with the Federal Highway Administration Hydraulic Engineering Circular Number 11 (Publication No. FHWA-IP-89-016, as amended) and the PADEP Erosion and Sediment Pollution Control Program Manual (Publication No. 363-2134-008, as amended), or other design guidance acceptable to the Township Engineer.
A. 
Open vegetated channels.
(1) 
Open vegetated channels are primarily applicable for land uses such as roads, highways, residential developments and pervious areas.
(2) 
Open vegetated channels shall be designed to meet the following minimum standards:
(a) 
The channel shall be designed to safely and nonerosively convey the ten-year frequency storm event, with a freeboard of at least 12 inches. "Freeboard" is the difference between the water surface elevation of the design flow in the channel and the top elevation of the side bank of the channel.
(b) 
The longitudinal slope shall be no greater than 6%, and no less than 1%, unless an underdrain is provided.
(c) 
Channels shall be trapezoidal in cross section. The minimum bottom width shall be two feet. The maximum bottom width shall be eight feet.
(d) 
Channels shall be designed with moderate side slopes of no greater than four horizontal to one vertical. Flatter side slopes may be necessary under certain circumstances.
(e) 
Landscape specifications shall address the grass species, wetland plantings (if applicable), soil amendment, and hydric conditions present along the channel.
(f) 
Accumulated sediment within the channel bottom shall be removed when it has reached three inches deep. This requirement shall be included in the O&M plan.
(g) 
The use of low ground pressure (less than four psi) equipment for construction is required where infiltration credit will be sought.
B. 
Retention and detention basins.
(1) 
Basins intended to hold water for more than four days shall be designed to create a healthy ecological community with sufficient circulation of water to prevent the growth of unwanted vegetation and mosquitoes. Care should be taken to landscape retention basins in accordance with § 178-25D. Detention basins, also known as dry basins, are generally discouraged as a stormwater management practice and should only be used where infiltration of stormwater is not possible, and then only for street runoff, or, as a last resort, where no other management facility is practical.
(2) 
See Appendix D[1] for guidance on design of wet basins to avoid creation of mosquito breeding areas.
[1]
Editor's Note: Appendix D is included as an attachment to this chapter.
(3) 
The outlet structure of any basin designed with a permanent pool shall include a gate valve designed to allow complete drainage of the pond for maintenance.
(4) 
The design of a retention basin shall include the determination of the proposed site's ability to support a viable permanent pool. The design shall take into account such factors as the available and required rate and quality of dry weather inflow, the stormwater inflow, seasonal and longer-term variations in groundwater table, freeboard, and impacts of potential pollutant loadings.
(5) 
A clay core, keyed into the in situ soil, shall be required in embankments.
(6) 
Sediment storage volume equal to at least 20% of the volume of the permanent pool shall be provided.
(7) 
"Freeboard" is the difference between the water surface elevation of the design flow in the emergency spillway and the top elevation of the settled basin embankment (that is, top of berm). The minimum freeboard shall be one foot.
(8) 
A sediment forebay with a hardened bottom shall be provided at each inlet into a basin. The forebay storage capacity shall, at minimum, be 10% of the two-year volume discharged from that inlet. The forebay shall be designed to allow for access by maintenance equipment for periodic cleaning.
(9) 
Emergency spillways shall be sized and located to permit the safe passage of stormwater flows from a 100-year storm. The maximum velocities in vegetated spillways, excavated in otherwise undisturbed soil, shall be analyzed based upon the velocity of peak flow in the emergency spillway during an assumed clogged primary outlet condition. Where maximum velocities exceed design standards contained in the Engineering Field Manual for Conservation Practices (USDA, SCS, July 1984), suitable lining shall be provided. All emergency spillways placed on fill materials shall be lined, regardless of flow velocities or depths. Suitable linings include grass pavers, riprap (comprised of native stone if possible) and permanent turf reinforcing mats.
(10) 
Existing ponds or basins can be used for stormwater management, provided that it can be demonstrated that the ponds are structurally sound and meet the design requirements herein.
(11) 
Inlet structures and outlet structures shall be separated to the greatest extent possible in order to maximize the flow path through the basin. Inlets shall discharge into areas of the basin that slope toward the outlet structure, but be adequately separated to ensure predischarge sediment deposition. Low-flow channels, constructed of concrete or asphalt, are not permitted. Where low-flow channels are necessary, they shall be composed of a natural or bioengineered material or riprap. Low-flow channels shall be designed to improve water quality and slow the rate of flow through the basin. Low-flow channels may also be designed to infiltrate, where practical.
(12) 
Basins shall be designed to provide a length-to-width ratio of no greater than 3L:1W as measured in plan view (for example, a ratio of 4L:1W is too narrow).
(13) 
For ponds with a permanent pool, the basin depth shall average three feet to six feet, with no area shallower than three feet, with the exception of side slopes or benches. In residential areas, ponds shall be equipped with management practices that reduce the potential for unauthorized entry and use of the pond by the general public. Special measures are particularly desirable where a deep pond is not very visible from a public road or residence.
(14) 
All areas of the basin that are deeper than four feet shall have two safety benches, totaling 15 feet in width. One bench shall start at the normal water surface (permanent pool) and extend up the pond's side slopes at a maximum slope of 10%. The other shall extend down from the normal water surface into the pond to a maximum depth of 18 inches, also at a slope no greater than 10%.
(15) 
Any side slopes below the permanent water surface level shall not exceed five horizontal to one vertical (5H:1V). Side slopes above the permanent water surface level shall not exceed three horizontal to one vertical (3H:1V). For detention basins, where used, the inside side slopes shall be no steeper than three horizontal to one vertical (3H:1V). The minimum slope for the basin bottom is 2%. A level bottom is acceptable, provided the designer demonstrates to the Township Engineer's satisfaction that the basin bottom will be landscaped with appropriate wetland vegetation. In addition, detention basins of sufficient size and slope may serve other functions as well, including recreational uses, which do not hinder or conflict with the function of the detention basin.
(16) 
Proper stabilization structures, including stilling basins, energy dissipaters, and channel lining, shall be constructed at the outlets of all basins and emergency spillways. The stabilization structures shall control water to avoid erosion, reduce velocities of released water, and direct water so that it does not interfere with downstream activities.
(17) 
An access ramp, with a slope no greater than 20% and an access easement 20 feet in width, shall be provided to each basin to facilitate cleanout.
(18) 
Energy dissipaters and/or level spreaders shall be installed to prevent erosion and/or initiate sheet flow at points where pipes or drainageways discharge to or from basins. Energy dissipaters shall comply with criteria in Hydraulic Engineering Circular No. 15, Design for Stable Channels with Flexible Linings (USDOT, FHWA, 1986), or the Engineering Field Manual for Conservation Practices (USDA, SCS, July 1984) or the latest revised versions thereof. Such facilities shall be both functional and harmonious with the surrounding environment. For example, native rock (not quarried riprap) from the site may be used in constructing dissipaters where practical.
(19) 
The minimum distance between a proposed basin discharge point (including the energy dissipater, etc.) and a downstream property boundary shall in no case be less than 30 feet. Where there is discharge onto, or through, adjacent properties prior to release to a stream, designers shall demonstrate how downstream properties are to be protected. The Township Engineer may require that the setback distance be increased based upon factors such as topography, soil conditions, the size of structures, the location of structures, and discharge rates. A drainage easement may also be required.
(20) 
Outlet structures shall meet the following specifications:
(a) 
For storms up to, and including, the two-year storm, normal overflow, after development, shall be through a siphon structure, which draws cooler water from just above the bottom of the basin, and discharges at the intended level of the permanent water surface of the retention basin, to a concrete or rock apron or level spreader on the downstream slope and toe of the basin, possibly in conjunction with the discharge structure for larger storms.
(b) 
For storms greater than the two-year storm, a concrete principal outlet structure shall be built, using reinforced concrete with watertight construction joints.
(c) 
Discharges shall be to level spreaders or energy dissipaters. The point of discharge shall be a point where the discharge will spread out in shallow sheet flow to level ground or to slopes of less than 5%.
(d) 
To minimize clogging and to facilitate cleaning and inspecting, outlet pipes used to drain the pond and used for discharges to maintain pond levels after construction shall have an internal diameter of at least 18 inches and a minimum grade of 1%.
(e) 
Concrete antiseep collars shall be provided on all outlet pipes within a constructed berm.
(f) 
The use of architecturally treated concrete, stucco, or stone facade treatment shall be considered for enhancing the outlet structure. Such facilities shall be both functional and harmonious in design with the surrounding environment.
(g) 
Outlet pipes through a basin berm shall be constructed of reinforced concrete with rubber gaskets in conformance with AASHTO M170, M198 and M207. For siphon structures, pipe materials shall be reinforced concrete, Schedule 80 PVC or other material acceptable to the Township Engineer.
(h) 
Basin outlet structures shall have childproof, nonclogging, trash racks, fabricated from stainless steel. The bars in the trash rack shall be spaced such that a four-inch-diameter sphere cannot pass through any opening in the trash rack. Periodic cleaning of debris from trash racks shall be included in the operation and maintenance plan.
(i) 
Antivortex devices, consisting of a thin vertical plate, shall be provided at the top of all circular risers or standpipes.
C. 
Conveyance systems (open channels, drainageways, and storm sewers).
(1) 
Applicants are encouraged to design conveyance systems that encourage infiltration and improve water quality wherever practicable.
(2) 
Wherever conveyance channels are necessary, drainage shall be maintained by an open channel with landscaped banks designed to carry the fifty-year, twenty-four-hour stormwater runoff from upstream contributory areas without erosion. The Township Engineer may require a higher design storm, as conditions require. All open channels shall be designed with one foot of freeboard above the water surface elevation of the design runoff condition.
(3) 
Flood relief channels shall be provided and designed to convey the runoff from the 100-year, twenty-four-hour storm, such that a positive discharge of this runoff to an adequate receiving stream or conveyance system occurs without allowing this runoff to encroach upon other properties. The intent is to ensure that runoff can reach its designated management facility or receiving conveyance or stream, even if the site conveyance becomes blocked or otherwise nonfunctional.
(4) 
The Board of Supervisors may require that open channels along existing roadways be enclosed if PennDOT standards for safety and maintenance cannot be satisfied. All drainage structures shall conform to the latest edition of Form 408, PennDOT specifications.
(5) 
Manholes and/or inlets shall not be spaced more than 300 feet apart for pipe sizes up to 24 inches in diameter and not more than 450 feet apart for larger pipe sizes.
(6) 
Stormdrain pipes shall be reinforced concrete pipe with gasketed joints, or smooth lined corrugated polyethylene pipes with gasketed joints. No mortar joint concrete pipes are permitted.
(7) 
Inlet tops shall be sealed to boxes with a preformed concrete joint sealant material (such as RAM-NEK® or equivalent).
(8) 
Storm manhole covers and inlet grates shall have the phrase "No dumping, drains to waterway." cast into them, and shall meet all applicable PennDOT specifications.
(9) 
Where vegetated swales are used in lieu of, or in addition to, storm sewers, they shall be designed to carry the ten-year flow without erosion. Drainage swales shall be designed with a minimum grade of 1% and a maximum grade of 6%, unless underdrains or check dams are provided.
(10) 
Storm drainage systems collecting runoff from streets or parking areas and discharging to detention basins shall, to the maximum extent possible, allow runoff to flow through a series of one or more depressions containing wetland vegetation in order to reduce the level of pollutants.
(11) 
Utilizing street curbing for the purpose of stormwater conveyance is discouraged. On streets that must contain curbing, storm sewers shall be placed in front of the curbing. To the greatest extent possible, storm sewers shall not be placed directly under curbing. At curbed street intersections, storm inlets shall be placed in the tangent sections of the road.
(12) 
The use of open vegetated swales, in lieu of curbing, to convey, infiltrate, and/or treat stormwater runoff from roadways is encouraged in areas with slopes less than 6%. Inlets shall be placed at the center of the shoulder swale, draining the street, and shall be located no less than four feet from the edge of the cartway.
(13) 
The Township (and the party responsible for maintenance, if applicable) shall be granted a minimum twenty-foot-wide drainage easement over all storm sewers, drainage swales, channels, etc., that are a component of the stormwater management system, when located within undedicated land. All permanent retention or detention basins, and/or other stormwater management facilities providing stormwater control for other than a single residential lot, shall be located within a defined drainage easement that allows proper legal access and maintenance vehicle access by the Township personnel.
(14) 
No property owner shall obstruct or alter the flow, location, or carrying capacity of a stream, channel, or drainage swale to the detriment of any other property owner, whether upstream or downstream. All subdivision and/or land development plans containing streams, channels, drainage swales, storm sewers, or other conveyance systems that cross property boundaries, existing or proposed, or whose discharge crosses such boundaries, shall contain a note stating the above.
(15) 
Water quality inlets. Storm drainage systems that collect runoff from parking areas and/or loading areas exceeding 10,000 square feet of impervious coverage and that discharge to stormwater management systems, including surface or subsurface infiltration systems, shall have a minimum of one water quality inlet per each acre of drainage area. The purpose of water quality inlets is to remove oil, grease, and heavy particulates or total suspended solids, hydrocarbons, and other floating substances from stormwater runoff.
(16) 
Oil-separation devices; runoff from streets or parking lots; cleaning.
(a) 
Any inlet or manhole in a storm drainage collection system which discharges runoff from a street with lot or building frontages of less than 100 feet or from a parking lot to a surface or subsurface infiltration system shall have an oil-separation device installed at the outlet of the manhole or inlet. The oil-separation device will be maintained by the Township if the contributing flow is from a Township-owned street, and the oil-separation device will be maintained by the property owner or homeowners' association if the contributing flow is from a parking lot or private street or driveway. The structure containing the oil separator will be constructed with a ring foundation with an open floor, consisting of a bed of clean three-quarter-inch stone with a minimum depth of eight inches. The floor of the inlet structure shall be a minimum of 18 inches below the outlet elevation. The Township Engineer may also require structures to capture suspended solids or permit other oil- and/or trash-separation devices, or methods, if the applicant can prove that such alternative devices will be effective and easily maintained.
(b) 
Storm drainage systems receiving runoff from street or parking lots and discharging to retention/detention basins or at points of interest shall, to the maximum extent possible, flow through a series of one or more depressions containing wetland vegetation in order to reduce the level of pollutants leaving the property. The variety of vegetation in wetlands created for this purpose shall be specified on the plan and provided in the construction sequence. Wetland area plantings shall be maintained and protected from invasive or inappropriate species.
(c) 
Periodic cleaning of these systems shall be addressed in the operation and maintenance plan submitted to the Township.
(17) 
All storm drainage pipes greater than 15 inches in diameter shall incorporate grill-or grate-type measures, at headwalls and end sections, to prevent children or small animals from entering the pipes. The bars in the grill or grate shall be spaced such that a four-inch-diameter sphere cannot pass through any opening. Periodic cleaning of debris from grills and/or grates shall be included in the operation and maintenance plan.
(18) 
Box or arch culverts under roadways shall be designed for a fifty-year storm and shall have a natural stream bottom, except when under a road providing the only means of access to a property, also known as a "single access street." For a single-access street, a 100-year storm shall be used. A culvert for a driveway shall be designed for a 100-year storm if the driveway provides the only means of access to the property.
(19) 
Structures, such as box culverts, arch culverts, or bridges, shall be provided with wing walls with deep footings and shall be constructed for the full width of the right-of-way. Where possible, a natural stream channel, using river cobbles, or similar treatment, shall be maintained under the structure to allow the passage of wildlife. Measures such as toe walls, or similar methods, shall be provided to prevent scouring. The cartway area over the bridge shall be as wide as the widest road connecting with the bridge, or if the character of the road is expected to change for future planning, the cartway of the bridge shall be made to anticipate this condition. On either side of the cartway, the bridge railing must be at least five feet back from the edge of the final cartway width so this five feet may be used to place sidewalks/bikeways, present or future. Where no increased vehicle traffic is possible, a six-foot-wide sidewalk/bikeway shall be provided on one side to connect to existing or planned sidewalks/bikeways.
(20) 
If necessary, due to the configuration of a crossing requiring the construction of headwalls, and/or wing walls or similar structures outside of the right-of-way, additional right-of-way, encompassing the structure, shall be provided.
(21) 
Any point where a stormdrain pipe discharges to grade shall be protected with rock outlet protection designed for the maximum pipe capacity, as determined by Manning's equation. Additional measures may be required where such pipes discharge to areas of greater than 5% slope.
(22) 
Inlets along streets shall be arranged so that 95% of gutter flow will be captured by each inlet.
D. 
Landscaping of stormwater management practices. Stormwater management practices shall be landscaped in accordance with the following standards. Landscape plans shall be prepared by a professional landscape architect, licensed in the Commonwealth of Pennsylvania.
(1) 
Landscaping shall be required in and around all constructed stormwater management practices, with a minimum surface area of 1,000 square feet, for the purposes of:
(a) 
Assisting in the management of stormwater;
(b) 
Stabilizing the soil within such facilities to minimize and control erosion;
(c) 
Enhancing the visual appearance of such facilities; and
(d) 
Mitigating maintenance problems commonly associated with the creation of such facilities.
(2) 
A planting plan and planting schedule shall be submitted in accordance with the following:
(a) 
Wet meadows, including floors of stormwater management practices.
[1] 
Wet meadows and floors of stormwater management practices shall be planted with native wildflowers and nonaggressive grasses, the intent being to create a mixed meadow of such plantings, where appropriate. Selection of plantings shall be based on whether the area in question is usually well drained or permanently wet and whether the area will be used for recreation purposes. No woody plants shall be planted within the saturated zone (phreatic line) of a stormwater management practice or on a berm constructed for impounded water.
[2] 
Seeding by drills, corrugated rollers, cyclone or drop seeders or hand seeding of such areas is preferred. However, subject to approval of the Township Engineer, hydroseeding, followed by hydromulching, can be used.
[3] 
Fertilizers, as a nutrient supplement, shall not be used unless it is documented that soil conditions warrant such use and nutrient applied does not exceed plant uptake. Soil for planting of wildflowers shall contain not less than 3% or more than 10% organic matter, as determined by an agricultural chemist, with certification of the test before planting.
[4] 
Seeding shall take place either between April 1 and May 15 or between September 1 and October 15. Planting areas shall be soaked to maintain a consistent level of moisture for at least four weeks to six weeks after planting.
[5] 
A maintenance plan shall be submitted for the stormwater management practice(s) proposed, listing mowing frequency, weeding, aerating, and any other required maintenance activities.
(b) 
Wet edges that remain wet all or most of the year shall be planted with native wildflowers, grasses, and shrubs. Plants to be located on rims or banks which remain dry most of the year shall be planted with species tolerant of dry soil conditions.
(c) 
Wooded areas.
[1] 
Where stormwater management practices adjoin wooded areas, native trees and shrubs shall be selected and planted outside the practice, so as to blend with existing surroundings.
[2] 
Plantings in such areas shall be of sufficient density to eliminate the need for mowing.
[3] 
After construction, clusters of trees and shrubs shall be planted in cleared areas around stormwater management facilities, but well away from outfalls and any constructed berms.
[4] 
Vegetation shall be planted during appropriate times of the year, predominantly between late March and mid-May or from early October until evidence of ground freezing, depending upon the species selected. Most deciduous trees and shrubs can be planted in either spring or fall. Evergreens are best planted in late summer or early fall.
(d) 
Slopes.
[1] 
On slopes of less than 20%, a mixture of native meadow grasses and wildflowers (for wet meadows) shall be planted.
[2] 
On slopes equal to or greater than 20% dense spreading shrubs, tolerant of dry soils, shall be planted. Heavy mat mulch shall be used during the period of establishment.
[3] 
No woody plant materials or trees shall be located on a constructed or natural berm acting as the impoundment structure of a stormwater management practice. Trees shall be located downstream of an impoundment berm a sufficient distance from the toe of the constructed slope to assure that the toe of the slope is outside the future projected mature dripline of the species planted, but in no case less than 15 feet.
[4] 
In cases where stormwater management practices are to be located in proximity to wetlands or waterways, the applicant's planting plan and schedule shall consider the sensitive conditions existing therein and be modified accordingly to reflect existing flora.
[5] 
Stormwater management practices shall be screened in a manner which complements the existing landscape and provides sufficient access for maintenance.