A.
There are two stages in the procedure for approval of subdivision and land development plans. These stages are required to enable the Township Planning Commission and the Board of Supervisors and their professional consultants to have an adequate opportunity to review the subdivision and/or land development plan submission and to ensure that their formal recommendations are reflected in the approved plans.
B.
The separate stages of approval require the submission of preliminary and final plans. These plans differ in their purpose and required level of detail. The table below indicates the required plans for the different types of submission and the section in which those plans are defined:
Table 12. Plan Requirements | ||
|---|---|---|
Type of Subdivision | Type of Plan Requirements (and section number) | |
Preliminary | Final | |
Feasibility sketch plan | Not required but highly recommended | Not required |
Minor | Not required | Required (§ 305-504) |
Major | Required (§ 305-505) | Required (§ 305-506) |
Land development | Required (§ 305-505) | Required (§ 305-506) |
C.
The review process required by the Township Planning Commission and Board of Supervisors shall include no more than 90 days each for any preliminary and final plans, following the date of the regular meeting of the governing body or the Planning Commission (whichever first reviews the application) next following the date the complete application is filed or after a final order of court remanding an application, provided that should the said next regular meeting occur more than 30 days following the filing of the complete application or the final order of the court, the said ninety-day period shall be measured from the 30th day following the day the complete application has been filed. The Township shall make a determination as to whether the application and plans are complete, as required by this chapter. The developer shall be notified as to the completeness of the application. The ninety-day period shall begin only after the determination of completeness has been made. Said ninety-day period may be extended where the developer agrees in writing to an extension of time. The presentation of a revised preliminary or final plan shall each be considered a separate submission. A complete application shall include the required plans as set forth herein, the traffic impact study, as required herein, and other studies as required by this chapter.
D.
The Township Zoning Officer shall stamp each plan submission and resubmission "date received" and shall date and initial the plan above the title block. Plans should be distributed to the Township Planning Commission as soon as practicable.
E.
The Township Engineer shall review preliminary and final plan applications and provide recommendations to the Planning Commission and Board of Supervisors as required by the provisions in this chapter. The Township Engineer shall make recommendations indicating approval or disapproval of the proposed subdivision or land development based upon the various engineering considerations identified as they are reflected in the submitted plans. For the purpose of clearly identifying the extent of the Township Engineer's responsibilities in the review of subdivision and land developments, the following engineering considerations are provided:
(1)
Relative layout and design of lots and parcels.
(2)
Dimensions and areas of lots and parcels.
(3)
Soil conditions.
(4)
Surface and subsurface drainage conditions and plans.
(5)
Lighting plans.
(6)
Utility plans.
(7)
Landscape and buffer plans.
(8)
Location and design of entrance and exit accessways.
(9)
Road specifications, cross sections and profiles.
(10)
Traffic impact.
(11)
Water service.
(12)
Stormwater management.
(13)
Land profiles.
(14)
Sewage disposal.
(16)
Improvements required; materials, construction methods and workmanship.
