In the event that a person fails to comply with the requirements
of this chapter, or fails to conform to the requirements of any permit
issued hereunder, the municipality will provide notification of the
violation. After notice is provided, failure to correct violations
in a timely manner may result in additional violations.
The Township of Maidencreek Board of Supervisors is hereby authorized
and directed to enforce all of the provisions of this chapter. All
inspections regarding compliance with the drainage plan shall be the
responsibility of the Municipal Engineer or other qualified persons
designated by the Township of Maidencreek.
A. No person shall modify, remove, fill, landscape or alter any stormwater
management BMPs, facilities, areas, or structures, without the written
approval of the Township of Maidencreek.
B. Upon presentation of proper credentials, the Township of Maidencreek
may enter at reasonable times upon any property within the Township
of Maidencreek to inspect the condition of the stormwater structures
and facilities in regard to any aspect regulated by this chapter.
C. It shall be unlawful for a person to undertake any regulated activity
except as provided in an approved stormwater management site plan,
unless specifically exempted from the requirement to submit a stormwater
management site plan by this chapter.
D. The developer shall be responsible for providing as-built plan of
all stormwater management BMPs included in the approved stormwater
management site plan. The as-built plans and an explanation of any
discrepancies with the construction plans shall be submitted by the
developer to the Township of Maidencreek.
E. The as-built submission shall include a certification of completion
signed by a qualified professional verifying that all permanent stormwater
management BMPs have been constructed according to the approved plans
and specifications. If any licensed qualified professionals contributed
to the construction plans, then a licensed qualified professional
must sign the completion certificate.
F. After receipt of the completion certificate by the Township of Maidencreek,
the Township of Maidencreek may conduct a final inspection.
G. Inspections regarding compliance with the stormwater management site
plan are a responsibility of the Township of Maidencreek.
H. The Township of Maidencreek may withhold an occupancy permit until
a certificate of completion has been provided by the developer.