All development proposals shall be served by a public wastewater disposal system, including both collection and treatment facilities as follows:
A.
For the issuance of a building permit, preliminary plat approval, or other land use approval the disposal system for the project site has been approved by the Department as being consistent with adopted rules and regulations of the applicable government, agency, or district;
B.
For the issuance of a certificate of occupancy for a building or change of use permit, the approved wastewater disposal system is installed to serve each building or lot;
C.
For recording a final plat, final short plat or binding site plan the approved wastewater disposal system is installed or bonded to serve each lot respectively; and
D.
For a zone reclassification the timing of installation of required wastewater system improvements is contained in the approving ordinance.
(Ord. 238 Ch. VI § 2(A), 2000; Ord. 299 § 1, 2002)