All conditions imposed by the City at the time of approval of the preliminary plat and all required improvements shall be completed prior to the approval of the final plat. However, the City Council may allow a subdivider, at the subdivider's option, to defer completion of certain required improvements in which case the following procedures and requirements shall apply:
A.
The subdivider shall enter into a subdivision improvements agreement with the City, found in Appendix F of these regulations, which guarantees the outstanding conditions will be completed.
B.
The subdivider shall certify that at least 2/3 (based on value of completed work) of all required improvements are designed and completed.
C.
The subdivider shall not be allowed to bond for:
D.
All conditions of approval shall be completed within the time schedule provided in the subdivision improvements agreement. The initial term of an agreement shall not exceed 12 months from date of City Council approval however, the City Manager, upon request by the subdivider may extend the agreement in increments not to exceed 12 months if:
1.
The subdivider demonstrates a reasonable hardship exists which is not solely financial;
2.
The conditions do not place a health or safety burden on existing lots; and
3.
The improvements are not necessary for the convenient enjoyment or use of lots which are in the process of developing or being utilized.
E.
The subdivider shall submit plans, specifications and cost estimates, prepared by a registered professional engineer, for the completion of all remaining improvements.
F.
The projected improvements cost shall be 125% of the current costs for completing the improvements.
G.
Upon completion of required improvements, the subdivider shall file with the City a statement certifying that:
1.
All required improvements are complete;
2.
The improvements are in compliance with the minimum standards specified by the City Council;
3.
The subdivider knows of no defects in these improvements;
4.
The improvements are free and clear of any encumbrance or liens;
5.
All applicable fees and surcharges have been paid.
H.
The subdivider shall also file with the City:
I.
The subdivider will provide for inspection of all required public improvements by a registered professional engineer before the City releases the subdivider from the subdivision improvements agreement.
J.
Upon completion of the inspection, the inspecting engineer shall file with the City a statement certifying that the improvements have been completed in the required manner.
K.
Only after the inspecting engineer certifies that improvements are complete and free from defect, and after receipt of other statements detailed above, the City shall release the subdivider from the subdivision improvements agreement.
(Ord. 1951, 5/4/2026)