All terms in this section shall be defined in the NJDEP Stormwater
Rule (N.J.A.C. 7:8, et seq.). The following additional terms are defined
for this chapter only.
EXEMPT DEVELOPMENT
Any development that creates an increase of less than 500
square feet of impervious area and disturbs less than 2,500 square
feet of land. Further, an exempt development shall not meet the definition
of "minor development."
MAJOR DEVELOPMENT
A.
Any individual development, as well as multiple developments
that individually or collectively result in:
(1)
The disturbance of one or more acres of land since February
2, 2004;
(2)
The creation of one-quarter acre or more of regulated impervious
surface since February 2, 2004;
(3)
The creation of 1/4 acre or more of regulated motor vehicle
surface since March 2,2021; or
(4)
A combination of the items in Subsection
A(2) and
(3) above that totals an area of 1/4 acre or more. The same surface shall not be counted twice when determining if the combination area equals 1/4 acre or more.
B.
Major development includes all developments that are part of a common plan of development or sale (for example, phased residential development) that collectively or individually meet any one or more of conditions in Subsection
A(1),
(2),
(3), or
(4) above. Projects undertaken by any government agency that otherwise meet the definition of “major development” but which do not require approval under the Municipal Land Use Law, N.J.S.A. 40:55D-1 et seq., are also considered “major development.”
MINOR DEVELOPMENT
Any development that results in the creation of an increase
of 500 square feet or more of impervious area or one that disturbs
more than 2,500 square feet of land area. Further, a minor development
shall not meet the definition of "major development."
There shall be no additional fees for stormwater review for
applications to the Land Use Board. Minor development applications
to the Township Engineer shall be accompanied by a review fee in the
amount of $250. Major development applications shall be accompanied
by a review fee in the amount of $1,000. If a project is approved,
an inspection escrow deposit shall be made in an amount to be determined
by the Township Engineer.
Any person who erects, constructs, alters, repairs, converts,
maintains, or uses any building, structure or land in violation of
this chapter shall be subject to one or more of the following penalties:
imprisonment for a term not exceeding 90 days; a fine not exceeding
$2,000; and a period of community service not to exceed 90 days.
This chapter shall take effect March 2, 2021.