[Amended 2-10-1977 by Ord. No. 2-77]
As used in this chapter and the Building Code,
the following terms shall have the meanings indicated:
ENFORCING AGENCY
The Building Official and his agents and any and all subcode
officials and their agents.
OWNER
Any person, corporation, partnership or association who holds
the legal or beneficial interest to any parcel of land within the
Borough limits of the Borough of Rockaway.
[Amended 2-10-1977 by Ord. No. 2-77; 5-24-1984 by Ord. No. 17-84; 11-14-1991 by Ord. No.
22-91]
A. Except as otherwise provided by law or in the code, before construction or alteration of any building or structure, the owner or his agent, engineer or architect should submit an application, in writing, including signed and sealed drawings and specifications, to the enforcing agency. The application shall be in accordance with the regulations established by the Commissioner of Community Affairs, on a form prescribed by the Commissioner and shall be accompanied by payment of the fee established in Subsection
D of this section. The application for a construction permit shall be filed with the enforcing agency and shall be of public record; and no application for construction permit shall be removed from the custody of the enforcing agency after a construction permit has been issued. If the Commissioner has not promulgated said forms, the application may be made on such forms as the municipality may provide.
B. The enforcing agency shall examine each application
for a construction permit. If the application conforms with the code
and the requirements of other applicable laws, regulations and ordinances,
the enforcing agency shall approve the application and shall issue
a construction permit to the applicant. Every application for a construction
permit shall be granted, in whole or in part, or denied within 20
business days. If the application is denied, in whole or in part,
the enforcing agency shall set forth the reasons therefor in writing.
If an enforcing agency fails to grant, in whole or in part, or deny
an application for a construction permit within the period of time
prescribed herein, such failure shall be deemed a denial of the application
for the purposes of an appeal to the Construction Board of Appeals,
unless such period of time has been extended with the consent of the
applicant. Except as otherwise provided by law or the code, the construction
or alteration of a building or structure shall not be commenced until
a construction permit has been issued.
C. A construction permit issued in accordance with the
foregoing provisions, pursuant to which no construction has been undertaken
above the foundation walls within one year from the time of issuance,
shall expire. The enforcing agency may suspend, revoke or cancel a
construction permit in case of neglect or failure to comply with the
provisions of the law, of this code or upon a finding by it that a
false statement or representation has been made in the application
for the construction permit.
D. Fees.
(1) The fee for a construction permit shall be the sum
of the subcode fees listed plus all applicable special fees, such
as elevator or sign fees. This fee shall be paid before a permit is
issued. The fee to be charged for a certificate of occupancy or certificate
of approval shall be paid before a certificate is issued. This fee
shall be in addition to the construction permit fee.
(a)
The building subcode fees shall be as follows:
[1]
Fees for new construction shall be based upon the volume of the structure. Volume shall be computed in accordance with N.J.A.C. 5:23-2.28, as from time to time amended. The new construction fee shall be as provided in Chapter
A263, Fees, for buildings and structures, provided that the minimum fee shall be as provided in Chapter
A263, Fees; and the fee shall be as provided in Chapter
A263, Fees, for structures on farms, including commercial farm buildings, provided that the minimum fee shall be as provided in Chapter
A263, Fees, with the maximum fee for such structures on farms to be as provided in Chapter
A263, Fees.
[2]
Fees for renovations, alterations and repairs shall be based upon the estimated cost of the work. The fee shall be as provided in Chapter
A263, Fees, provided that the minimum fee shall be as provided in Chapter
A263, Fees. For the purpose of determining estimated cost, the applicant shall submit to the Construction Department such cost data as may be available produced by the architect of record or by a recognized estimating firm or by the contractor. A bona fide contractor's bid, if available, shall be submitted. The Construction Official shall make the final decision regarding estimated cost.
[3]
Fees for additions shall be computed on the
same basis as for new construction for the added portion.
[4]
Fees for combination renovations and additions shall be computed as the sum of the fees computed separately in accordance with Subsection
D(1)(a)[2] and
[3] above.
[5]
The minimum fee for any building subcode permit shall be as provided in Chapter
A263, Fees.
(b)
The plumbing subcode fees shall be as follows:
[1]
The plumbing subcode fees shall be as provided in Chapter
A263, Fees, per plumbing fixture or stack and shall include but not be limited to sinks, urinals, water closets, bathtubs, shower stalls, laundry tubs, floor drains, drinking fountains, dishwashers, garbage disposals, clothes washers, hot-water heaters or similar devices.
[2]
The fee shall be as provided in Chapter
A263, Fees, per special device for the following: grease traps, oil separators, water-cooled air-conditioning units, refrigeration units, utility service connections, backflow preventers, steam boilers, hot-water boilers, gas piping, gas service entrances, active solar systems, sewer pumps, interceptors and fuel oil piping.
[3]
The minimum fee for any plumbing subcode permit shall be as provided in Chapter
A263, Fees.
(c)
The electrical subcode fees shall be as follows:
[1]
For from one to 50 receptacles or fixtures, the fee shall be as provided in Chapter
A263, Fees; for each 25 receptacles or fixtures in addition to this, the fee shall be as provided in Chapter
A263, Fees; for the purpose of computing this fee, receptacles or fixtures shall include lighting outlets, wall switches, fluorescent fixtures, a convenience receptacle or similar fixture and motors or devices of less than one horsepower or one kilowatt.
[2]
For each motor or electrical device greater than one horsepower and less than or equal to 10 horsepower and for transformers and generators greater than one kilowatt and less than or equal to 10 kilowatts, the fees shall be as provided in Chapter
A263, Fees.
[3]
For each motor or electrical device greater than 10 horsepower and less than or equal to 50 horsepower; for each service panel, service entrance or subpanel less than or equal to 200 amperes; and for all transformers and generators greater than 10 kilowatts and less than or equal to 45 kilowatts, the fee shall be as provided in Chapter
A263, Fees.
[4]
For each motor or electrical device greater than 50 horsepower and less than or equal to 100 horsepower; for each service panel, service entrance or subpanel greater than 200 amperes and less than or equal to 1,000 amperes; and for transformers and generators greater than 45 kilowatts and less than or equal to 112.5 kilowatts, the fee shall be as provided in Chapter
A263, Fees.
[5]
For each motor or electrical device greater than 100 horsepower; for each service panel, service entrance or subpanel greater than 1,000 amperes; and for each transformer or generator greater than 112.5 kilowatts, the fee shall be as provided in Chapter
A263, Fees.
[6]
For the purpose of computing these fees, all
motors except those in plug-in appliances shall be counted, including
control equipment, generators, transformers and all heating, cooking
or other devices consuming or generating electrical current.
[7]
The minimum fee for any electrical subcode permit shall be as provided in Chapter
A263, Fees.
(d)
The fire subcode fees shall be as follows:
[1]
New construction, including additions: an amount
equal to 10% of the fee charged for the building subcode.
[2]
Renovations and alterations: an amount equal
to 10% of the fee charged for the building subcode.
[3]
Mechanical systems.
[a]
The fee for new or replacement heating, ventilating or air-conditioning unit installations in all use groups except use group R-3 (one- and two-family dwellings) shall be as provided in Chapter
A263, Fees.
[b]
The fee for new or replacement heating, ventilating or air-conditioning unit installations in use group R-3 shall be as provided in Chapter
A263, Fees, provided that the total fee for plumbing, building and/or fire codes shall not exceed the fee as provided in Chapter
A263, Fees.
[c]
The fee for installations of metal or masonry chimneys, wood stoves, coal stoves, fireplaces and other unit heaters shall be as provided in Chapter
A263, Fees, per chimney or unit heater.
[d]
The fee for the installation of commercial kitchen cooking equipment exhaust systems shall be as provided in Chapter
A263, Fees.
[e]
The fee for any other mechanical system requested by the fire protection subcode and not specifically listed herein shall be as provided in Chapter
A263, Fees.
[4]
Fire protection systems.
[a]
The fee for automatic sprinkler systems shall be based on the number of heads being installed as provided in Chapter
A263, Fees.
[b]
The fee for automatic detection systems, manual fire alarm systems and other similar fire protection systems shall be based on the number of detection, control and alarm signaling devices being installed as provided in Chapter
A263, Fees.
[c]
The fee for automatic dry chemical, wet chemical, carbon dioxide, halon or other similar extinguishing systems shall be as provided in Chapter
A263, Fees.
[d]
The fee for the installation of a standpipe shall be as provided in Chapter
A263, Fees.
[e]
The fee for each independent pre-engineered system shall be as provided in Chapter
A263, Fees.
[f]
The fee for each inspection and issuance of
a certificate of compliance with the Smoke Detector Law, N.J.S.A.
52:27D-198.1, shall be as provided in Chapter 263A, Fees.
[Added 9-10-1998 by Ord. No. 11-98]
(e)
The mechanical subcode fees shall be as follows:
[Added 8-8-2019 by Ord.
No. 13-19]
[1]
The mechanical subcode fees shall be as provided in Chapter
A263, Fees, per device and shall include but not be limited to water heaters, steam boilers, hot water boilers, hot air furnaces, oil tanks, LPG (liquid propane gas) tanks, fireplace, or generator.
[2]
The minimum fee for any mechanical subcode permit shall be as provided in Chapter
A263, Fees.
(2) General fees shall be as follows:
(a)
Processing fees. There shall be a ten-percent surcharge on any subcode fee processed by a third party agency licensed by the State of New Jersey, provided that the minimum fee for such processing shall be as provided in Chapter
A263, Fees.
(b)
Plan review fees. The fee for plan review shall
be 20% of the amount to be charged for the construction permit and
shall be paid before the plans are reviewed. The amount paid for this
fee shall be credited toward the total of the fees to be charged for
the construction permit.
(c)
Demolition fees.
[Amended 8-8-2019 by Ord.
No. 13-19]
[1]
The fees for the demolition of a building or structure exceeding 5,000 cubic feet shall be as provided in Chapter
A263, Fees.
[2]
The fees for the demolition of a building or structure of 5,000 cubic feet or less shall be as provided in Chapter
A263, Fees.
[3]
A cash bond of $500 shall be posted with the
Construction Official prior to the issuance of a demolition permit.
Said bond may be used by the Borough of Rockaway at its discretion
to mitigate all or part of any damages caused by the applicant to
any Borough facilities or otherwise.
(d)
Removal of building or structure fees. The fee for a permit for the removal of a building or structure from one lot to another or to a new location on the same lot shall be as provided in Chapter
A263, Fees, provided that the minimum fee shall be as provided in Chapter
A263, Fees.
(e)
Sign fees. The fee for the permit to construct or modify a sign shall be as provided in Chapter
A263, Fees, provided that the minimum fee shall be as provided in Chapter
A263, Fees.
(f)
Certificate fees.
[1]
The fee for a certificate of occupancy shall be in the amount of 10% of the new construction permit fee which would be charged by the Construction Department pursuant to these regulations. The minimum fee shall be as provided in Chapter
A263, Fees, except for one- or two-family (use group R-3 of the building subcode) structures of less than 5,000 square feet in area and less than 30 feet in height and structures on farms, including commercial farm buildings subject to N.J.A.C. 5:23-3.2(d), for which the minimum fee shall be as provided in Chapter
A263, Fees.
[2]
The fee for a certificate of occupancy granted pursuant to a change of use group shall be as provided in Chapter
A263, Fees.
[3]
The fee for a certificate of continued occupancy shall be as provided in Chapter
A263, Fees.
[4]
There shall be no fee for a temporary certificate
of occupancy.
[5]
There shall be no fee for a certificate of approval certifying
that work done under a construction permit has been satisfactorily
completed. All permits will require a certificate of approval.
[Amended 8-8-2019 by Ord.
No. 13-19]
(g)
Fees for ordinary maintenance. Ordinary maintenance as defined
in the State Uniform Construction Code can be verified by the Construction
Official of the Borough of Rockaway and shall require no fee or permit.
[Amended 8-8-2019 by Ord.
No. 13-19]
(h)
Fees for ordinary maintenance. Ordinary maintenance as defined
in the State Uniform Construction Code can be verified by the Construction
Official of the Borough of Rockaway and shall require no fee or permit.
[Amended 8-8-2019 by Ord.
No. 13-19]
(i)
Swimming pool fees.
[1]
The fee for a building permit of an aboveground pool shall be as provided in Chapter
A263, Fees.
[2]
The fee for a building permit of an in-ground pool shall be as provided in Chapter
A263, Fees, provided that the minimum fee shall be as provided in Chapter
A263, Fees.
(j)
The fee for an application for a variation in accordance with N.J.A.C. 5:23-210 shall be as provided in Chapter
A263, Fees, for Class I structures and as provided in Chapter
A263, Fees, for Class II and Class III structures. The fee for resubmission of an application for a variation shall be as provided in Chapter
A263, Fees, for Class I structures and as provided in Chapter
A263, Fees, for Class II and Class III structures.
(k)
Training and certification fees. In order to
provide for the training, certification and technical support programs
required by the Uniform Construction Code Act and the regulations, the enforcing agency shall collect, in addition to the fees specified above, a surcharge fee as provided in Chapter
A263, Fees. Said surcharge shall be remitted to the Department of Community Affairs.
(l)
The fee for each incinerator shall be as provided in Chapter
A263, Fees.
(m)
The fee for each crematorium shall be as provided in Chapter
A263, Fees.
(n)
The fee for the installation or replacement of fuel oil and motor fuel oil tanks shall be as provided in Chapter
A263, Fees, for inside tanks.
(o)
The fee for the installation of underground storage tanks shall be as provided in Chapter
A263, Fees.
(p)
The permit fee for taking a tank out of service, altering the piping or otherwise modifying any installation shall be as provided in Chapter
A263, Fees.
[1]
Notwithstanding the above Schedule of Fees,
all third party agency fees and any fees herein omitted from the above
Schedule of Fees shall be adjust to conform to the Fee Schedule of
the Department of Community Affairs as authorized by the Commissioner
of the Department of Community Affairs of the State of New Jersey.
[2]
The Construction Official shall, with the advice
of the subcode officials, prepare and submit to the Borough of Rockaway
Council, every two years following adoption of this chapter, a report
recommending a fee schedule based on the operating expenses of the
municipality fairly attributable to the enforcement of the State Uniform
Construction Code Act.
[Amended 2-10-1977 by Ord. No. 277]
A. The office of Building Official (also known as “Construction
Officer") is hereby created.
B. Pursuant to the standards created by Chapter
217 of the Public Laws of 1975, State of New Jersey, persons with the following qualifications shall be eligible
for appointment to the position of Building Officer:
(1) A licensed engineer or registered architect with at
least three years' experience in construction, design or supervision.
(2) An architect or engineer with a bachelor's degree
from an accredited institution of higher education with five years'
experience in construction, design or supervision.
(3) A journeyman in a trade or a contractor with 10 years'
experience in construction, design or supervision.
(4) The Building Official of the Borough appointed prior to the effective date of Chapter
217 of the Laws of 1975 (February 4, 1976) or within one year thereafter, and further provided that said person attain a certification from the Department of Community Affairs to serve in said position within four years of the date of the appointment. Persons meeting the qualifications set forth in Subsections
B(1),
(2) or
(3) must also be certified by the Department of Community Affairs.
C. The Building Official shall be appointed by the Mayor
with the advice and consent of the Council for a term of four years;
provided, however, that tenure shall continue for:
[Amended 11-14-1991 by Ord. No. 22-91]
(1) A Construction Officer who is serving under tenure as otherwise provided by law on the effective date of Chapter
217 of the Laws of 1975 (February 4, 1976) or within one year thereafter; or
(2) Any person certified pursuant to Subsection
B of this section and who subsequently gains such tenure.
D. The Mayor and Council shall have the authority to
appoint a Building Subcode Official, Plumbing Subcode Official, Electrical
Subcode Official, Fire Protection Official and other subcode officials
deemed necessary by the Mayor and Council or required by law or regulation.
Each official position created under this subsection shall be filled
by a person qualified for such position pursuant to P.L. 1975, C.
217, as amended, and N.J.A.C. 5:23, provided that, in lieu of any particular
subcode official, an on-site inspection agency may be retained by
contract pursuant to N.J.A.C. 5:23. More than one such official position
may be held by the same person, provided that such person is qualified
pursuant to P.L. 1975, C. 217 and N.J.A.C. 5:23 to hold each such
position.
[Amended 2-10-1977 by Ord. No. 2-77]
The enforcing agency or its agent shall periodically
inspect all construction undertaken pursuant to a construction permit
issued by it to ensure that the construction or alteration is performed
in accordance with the terms of the construction permit and consistent
with the requirements of the code and any ordinance implementing said
code.
[Amended 2-10-1977 by Ord. No. 2-77]
A. The owner of any premises upon which a building or
structure is being constructed shall be deemed to have consented to
the inspection by the enforcing agency or its agent of the entire
premises and of any and all construction being performed on it until
a certificate of occupancy has been issued. An inspector or a team
of inspectors, on presentation of proper credentials, shall have the
right to enter and inspect such premises and any and all construction
thereon for purposes of ensuring compliance with the provisions of
the applicable construction permit, the Building Code and other applicable
laws and regulations. All inspections pursuant to this section shall
be between the hours of 9:00 a.m. and 5:00 p.m. on business days or
when construction is actually being undertaken; provided, however,
that inspections may be conducted at other times if the Building Official
has reasonable cause to believe that an immediate danger to life,
limb or property exists or if permission is given by an owner or his
agent, architect, engineer or builder. No person except the owner
or his agent shall accompany an inspector or team of inspectors on
any inspection pursuant to this section unless his presence is necessary
for the enforcement of this section or the code or unless consent
is given by an owner or his agent, architect, engineer or builder.
B. If the construction of the structure or building is
being undertaken contrary to the provisions of a construction permit,
a building code or other applicable laws or ordinances, the Building
Official may issue a stop-construction order, in writing, which will
state the conditions upon which construction may be resumed and which
shall be given to the owner or the holder of the construction permit
or to the person performing the construction. If the person doing
the construction is not known or cannot be located with a reasonable
effort, the notice may be delivered to the person in charge of or
apparently in charge of the construction. No person shall continue
or cause or allow to be continued the construction of a building or
structure in violation of the stop-construction order except with
the permission of the Building Official to abate a dangerous condition
or to remove a violation or except by court order. If an order to
stop construction is not obeyed, the Building Official shall apply
to the appropriate court as otherwise established by law for an order
enjoining the violation of the stop-construction order. The remedy
for the violation of such an order provided in this subsection shall
be in addition to and not in limitation of any other remedies provided