[Amended by Ord. No. 5-96]
Upon receipt of an application, the Town Clerk shall forward same to the Secretary of the Planning Board who, in turn, shall forward same to the Subdivision and Site Plan Committee and in addition shall send a copy to each of the following for report and recommendation: Tax Assessor; County Planning Board, if required pursuant to the County Land Development Standards; and such other municipal, County, State and Federal Officials and agencies as directed by the Subdivision and Site Plan Committee.
A.
The Subdivision and Site Plan Committee shall review the application along with reports required from any officials or agencies and shall submit its findings and recommendations to the Planning Board.
B.
Action by Planning Board.
(1)
The Planning Board shall grant or deny the application within the times of submission of a complete application prescribed below, or within such further time as may be consented to by the applicant.
Type of Application | Period of Time For Action By Planning Board | |
|---|---|---|
Minor subdivision | 45 days | |
Preliminary plat: 10 lots or less | 45 days | |
Preliminary plat: more than 10 lots | 95 days | |
Minor site plan | 45 days | |
Preliminary site plan: 10 acres of land or less | 45 days | |
Preliminary site plan: more than 10 acres of land | 95 days | |
Final plat | 45 days | |
Final site plan | 45 days | |
(2)
Failure of the Planning Board to act within the period prescribed shall constitute approval and a certificate of the Town Clerk as to the failure of the Planning Board to act shall be issued on request of the applicant, and it shall be sufficient in lieu of the written endorsement (or the Town Clerk as to the failure of the Planning Board to act shall be issued on request of the applicant, and it shall be sufficient in lieu of the written endorsement) or other evidence of approval, herein required, and shall be so accepted by the County Recording Officer for purposes of filing subdivision plats. The applicant shall be notified in writing of the Planning Board's action within one week of its action.
C.
Whenever review or approval of an application by the County Planning Board is required by the County Land Development Standards, the Planning Board shall condition any approval that it grants upon timely receipt of a favorable report on the application by the County Planning Board or approval by the County Planning Board by its failure to report thereon within the required time period.
D.
Prior to returning the approved plat or site plan to the applicant, the applicant shall submit sufficient copies to the Secretary of the Planning Board in order to furnish a copy to each of the following: Construction Official; Tax Assessor; County Planning Board; Secretary of the Planning Board; and such other agency or official as may be directed by the Planning Board.
E.
No approved subdivision plat or site plan shall be signed until all municipal conditions in the resolution of approval have been met and verified. No permits shall be issued until the maps are signed by the Chairman and Secretary of the Board and the Town Engineer.