Where specific manufacturers are mentioned in this chapter, it is for the purpose of indicating a type only. Other alternates may be submitted and used if approved by the Engineer.
A. 
Materials.
(1) 
Sand blanket. Sand blanket material shall consist of clean, free draining sand and gravel conforming to New Jersey State Department of Transportation Standard Specifications for Soil Aggregates Type 3, Class A.
(2) 
Aggregate base course. Base course material shall consist of quarry processed stone or blast furnace slag conforming to New Jersey Department of Transportation Standard Specifications of Soil Aggregates Type 5, Class A.
(3) 
Bituminous stabilized base course. Materials shall conform to the requirements specified therefor in Section 2A of the Standard Specifications of the New Jersey State Highway Department for bituminous stabilized base course stone mix, except that the minimum bitumen content shall be 5%.
(4) 
Surface course. The paving materials shall be FABC Mix 4 as specified in the New Jersey State Highway Department Standard Specifications, except that the minimum percentage of bitumen shall be 6%.
B. 
Methods of construction.
(1) 
Subgrade. Before construction of the pavement, the subgrade shall be in a properly finished condition conforming to the proper line and grade and free of any soft spots or other deficiencies. Not more than 24 hours prior to commencing of operations on any subgrade, the subgrade shall be tested by running a roller of a weight at least equal to that to be used in the paving operation over the entire subgrade area. When permitted by the Engineer, testing may be performed by other equipment such as loaded trucks. When, in the opinion of the Engineer or his representative, the deformation of the subgrade under such test is excessive, the subdivider will be required to stabilize the subgrade in a manner satisfactory to the Engineer. The subgrade shall not be prepared during freezing weather or when frozen or when it is unstable due to excessive moisture.
(2) 
Sand blanket. The subbase shall be shaped and compacted, and when finished it shall conform to the required grade and contour. The subbase shall be compacted by a three-wheel power roller weighing not less than 330 pounds per linear inch of tread of the rear wheels. The Engineer shall determine whether the subbase has been adequately prepared and satisfactory compaction has been outlined.
(3) 
Aggregate base course. Upon the properly prepared subbase the contractor shall construct a pavement base course. Base course material shall not be placed when the subbase is wet or frozen. The gravel shall be spread in quantity and shaped with road scrapers so that when compacted it will be of the required thickness and at the required grade and crown shown on the plans. Frozen material will not be used. The base course shall be compacted using a three-wheel roller weighing not less than 10 tons and having a load on the rear wheels or not less than 330 pounds per inch of width of the rolls. The base course shall be rolled until the surface is thoroughly bound, free from defects, hard and even and at the proper grade and contour.
(4) 
Bituminous stabilized base course. The method of construction shall conform to the same specification indicated for materials above. The base course shall be laid on a properly prepared subgrade and shall consist of two two-and-one-half-inch courses. Upon completion of base course construction, the contractor shall cut samples from the pavement with a jackhammer, coring machine, or other means suitable to the Engineer. The sample shall be intact for the full thickness of the base course and shall be a size suitable to the Engineer. At least one sample shall be cut for every 1,000 s.y. of base course. Where deficiencies in the required minimum thickness are noted, at least two additional cores will be required to determine the extent of such deficiency. The average thickness of the base course as determined by any five or more samples, representing contiguous areas of pavement, shall be not less than five inches, and the minimum thickness permitted at any location will be 4 1/2 inches. In the event that the average thickness is less than five inches or the minimum thickness 4 1/2 inches, the deficiency shall be made up by increasing the thickness of the surface course.
(5) 
Surface course.
(a) 
Prior to placing of the surface course, the contractor shall repair any defects in the base course. Where cracking or any other type of failure has occurred in the base course, the contractor shall completely remove the base course, stabilize the subgrade if necessary and construct new base course. Where the deficiency involves depressions or raveling in the surface of the base course, the repair may be made by skin patching with a suitable bituminous material. For checking or gutter drainage, the subdivider shall supply sufficient water at the high points of the streets and shall run said water into the gutters in order to determine whether or not gutter grades are satisfactory. Wherever puddles occur, he shall skin patch the base course to achieve proper grades in the gutters. After repair of the base course, a tack coat shall be applied as specified in § 3.10 of the New Jersey State Highway Department Standard Specifications.
(b) 
Upon completion of the surface course, the contractor shall cut samples therefrom in accordance with the requirements for base course. The minimum thickness of the surface course shall be not less than one inch for minor local, and collector streets, and 1 1/2 inches for other streets. Where the surface course is found to be deficient, the Township may require that an additional surface course be laid of a thickness to be established by the Engineer.
(c) 
In the event of any deficiency in the surface course such as raveling, depressions, cracking, etc., such deficiencies shall be repaired by removing the surface course and replacing with new material.
(d) 
All equipment and methods of construction shall conform to the New Jersey State Highway Department Standard Specifications of 1961, except that only one roller may be used where the area to be paved is sufficiently small, in the opinion of the Engineer, to make the second roller unnecessary.
A. 
Materials.
(1) 
Concrete for curbs, gutters, sidewalks and driveway aprons shall be constructed with air-entrained concrete with a minimum 28 days compressive strength of 4,000 psi.
(2) 
Joint filler shall be a cellular compression material conforming to the requirements therefor of the Standard Specifications of the New Jersey State Highway Department as amended and revised to date.
B. 
Methods of construction.
(1) 
Excavation. The contractor shall make all necessary excavations or embankments for the construction, disposing of surplus materials. No filling shall be done below the proposed curb or gutter except when absolutely necessary, in which case such fill shall be made with clean sand or approved gravel and thoroughly tamped before concrete is laid thereon. All soft spots shall be thoroughly tamped, or if necessary, soft or spongy material shall be removed and clean sand or approved gravel refilled in its place.
(2) 
Backfill for curb. After curbing is completed and forms removed, the contractor shall backfill to the top of the curb in back and to the established gutter grade in front. Backfill shall be made with the materials excavated, except that any large or frozen lumps, wood, boulders or other foreign matter shall be removed before placing. Backfill shall be thoroughly compacted.
(3) 
Forms. Forms for concrete may be of lumber or steel. They shall be straight and of sufficient strength to prevent warping or bulging and to retain the concrete accurately in position. All mortar and dirt shall be removed from forms which have been previously used. Forms shall be well staked to the proposed lines and grades, and their upper edges shall conform to the finished surface of the curb. All forms shall be thoroughly wetted immediately before concrete is deposited against them.
(4) 
Concrete. Concrete construction, including curing, shall conform to the applicable requirements of the section on concrete structures contained elsewhere herein. The concrete shall be tamped and spaded or vibrated so that the forms are completely filled, the concrete thoroughly compacted and mortar is flushed to the face and top.
(5) 
Joints: concrete curb and gutters. Expansion joints shall be provided at intervals of 20 feet or when new construction abuts existing construction. The expansion joints shall be filled with one-half-inch thick cellular compression material to within 1/2 inch of the top and face of the curb and to within 1/4 inch of the top of the gutter. Dummy joints shall be provided at alternate twenty-foot intervals.
(6) 
Joints: Concrete sidewalks and aprons. Expansion joints, 1/2 inch wide, shall be provided at intervals of 20 feet and where the new paving abuts curb or old work. The expansion joints shall be filled with one-half-inch thick cellular compression material to within 1/4 inch of the top of the paving. For sidewalks, surface grooves shall be cut with an approved tool at least 1/4 inch thick at right angles to the line of the sidewalk and at intervals equal to the width of the sidewalk. Where new work abuts existing sidewalk, the surface grooves shall be spaced to conform to the lines of the abutting walk. All surface edges shall be rounded to a radius of 1/2 inch.
(7) 
Curb finish. Before initial set, the top of the curb and the gutter shall be finished with a wood float to an even, smooth and dense surface. As soon as the forms can be removed the face of the curb shall be given the same finish. Exposed edges shall be neatly rounded to a radius of 1/2 inch. The finished curb shall be true to the required grades, lines, dimensions and curvatures. Completed work shall be protected from traffic and the elements and shall be thoroughly wetted and kept moist for at least one day. Damaged, broken or cracked work shall be renewed by the contractor at his own sole cost and expense.
(8) 
Finish: concrete sidewalks and aprons. The finish shall be with a wood float, followed by brooming to a new and workmanlike surface. Exposed edges shall be neatly rounded to a radius of 1/2 inch. The concrete shall be cured as provided elsewhere herein.
A. 
Materials.
(1) 
Cement used shall conform to the following requirements of the ASTM, as amended to date:
(a) 
Standard portland cement.
(b) 
ASTM Designation C-150, Type 1.
(c) 
High early strength portland cement.
(d) 
ASTM Designation C-150, Type 3.
(e) 
Air-entraining portland cement.
(f) 
ASTM Designation C-175, Type 1-A.
(g) 
Air-entraining agent shall be Vinsol resin or Darex AEA.
(2) 
Aggregate, both fine and coarse, shall conform to the requirements therefor of the New Jersey State Highway Department Standard Specifications as amended and revised to date. Water shall be clean, fresh, and free of oils, acids, salts, organic matter or other injurious substances. Unless otherwise provided, all concrete shall be air entrained having 4% to 7% of entrained air, and shall be produced by using standard portland cement with additive of air-entraining portland cement with or without additional additive as may be required. Reinforcing steel shall be intermediate grade deformed bars conforming to ASTM Designation A-15 and ASTM Designation A-432, as amended and revised to date.
B. 
Methods of construction.
(1) 
Only enough water shall be added to make concrete workable for its intended use. The Engineer will determine the slump ranges within which the contractor must work. Ready-mix or transit-mix concrete may be used if obtained from sources approved by the Engineer. Equipment used to proportion and mix concrete on the job is subject to the approval of the Engineer.
(2) 
Forms shall conform to the shape, lines, dimensions, and grades shown on the plans. They shall be firmly braced, tight, and substantial so as to prevent movement, bulging, and mortar leakage. Wherever concrete will be exposed to view, forms shall be smooth and clean.
(3) 
Forms for footings may be omitted wherever soil and workmanship permit accurate excavation to size. All forms shall be completely removed.
(4) 
Reinforcement shall be accurately cut, bent and placed in accordance with the plans. It shall be free of excessive scale or any foreign material that would tend to reduce bond. It shall be securely supported, tied and fastened to prevent movement while concrete is being placed.
(5) 
Subgrades, and excavations and soil bases for foundations and slabs shall be properly finished to the prescribed lines, grades and dimensions, and shall be approved by the Engineer before concrete is placed. All areas to receive concrete shall be free of frost, foreign matter and excessive water; provided, however, that forms and soil surfaces shall be uniformly damp when the concrete is placed.
(6) 
Concrete shall be handled and placed so as to avoid any segregation. Concrete which has begun to set or which has been contaminated with foreign materials or to which too much water has been added shall not be used. Pouring of concrete shall generally be a continuous operation until the placing of an individual section has been completed. Concrete shall be thoroughly compacted with vibrators or by other suitable means.
(7) 
All concrete shall be finished by screening and floating to the required lines and grades. Unless otherwise specified, all work shall have a wood float finish; provided, however, that the contractor shall provide other finishes when so required by the plans or specifications or so directed by the Engineer.
(8) 
After the concrete has been poured, it shall be kept continuously wet for a period of one day or longer, as directed by the Engineer. Curing compound may be substituted for water, but in all cases, curing shall be done in a manner approved by the Engineer.
(9) 
Expansion joints, dummy joints, construction joints, and other appurtenances shall be provided as shown on the plans. Expansion joints shall have joint filler of the thickness indicated which shall extend the full depth of the concrete.
(10) 
After removal of forms all permanently exposed surfaces shall be cleaned of stains and dirt, and all surface defects which do not impair structural strength shall be repaired by cutting and patching in a manner satisfactory to the Engineer.
(11) 
Concrete shall not be poured when the atmospheric temperature is below 40º F. or when there is any precipitation, unless precautions satisfactory to the Engineer have been taken to prevent any damage to the work. Precautions necessary to avoid freezing of the concrete shall be in accordance with the current recommendations of the American Concrete Institute.
A. 
Materials.
(1) 
Cast-iron pipe and fittings.
(a) 
Cast-iron pipe shall conform to the requirements of the American Standards Association Specification A.21.6 or A.21.8, as amended and revised to date. Unless otherwise specified herein, cast iron shall be Thickness Class 22.
(b) 
Flanges shall conform to American Standards Association Specification A.S.A. B.16.1, Class 125, as amended and revised to date. Mechanical joints shall conform to the American Standards Association Specification A.21.11, as amended and revised to date. Gasket type joints shall be Tyton or approved equal. Either mechanical or gasket-type joints shall be used for normal water main construction.
(c) 
Fittings shall conform to the requirements of the American Standards Association A.21.10, as amended and revised to date.
(d) 
Unless otherwise specified, all cast-iron pipe and fittings shall be cement lined in accordance with American Standards Association A.21.4, as amended and revised to date.
(2) 
Valves.
(a) 
Valves shall conform to the current American Water Works Association Standard for Iron Body Double-Disc Gate Valves with parallel seats. Valves shall be of the type manufactured by either the Kennedy or Mueller Valve Company. Unless otherwise specified, valves shall be operated by a two-inch square operating nut of cast iron and shall open in the counterclockwise direction. The direction of opening shall be marked on the nut by an arrow and the word "OPEN."
(b) 
All cast-iron surfaces of valves and valve boxes shall be painted with three coats of asphaltum paint, inside and out.
(c) 
Valves shall be provided with a means of jointing suitable for use with the adjoining pipe.
(3) 
Valve boxes.
(a) 
Valve boxes shall be complete with covers and both valve box and cover shall be of ample strength and dimension to fully sustain the shocks of heavy vehicular traffic and to maintain the upper section and cover at proper grade under heavy vehicular traffic.
(b) 
Covers shall be round, at least six inches in diameter and shall have the word "WATER," an arrow showing the opening direction and the word "OPEN" clearly cast thereon.
(4) 
Fire hydrants. Fire hydrants shall follow these specifications: Operating and cap nuts shall be one-and-one-half-inch pentagon. They shall be equipped with two hose nozzles and one steamer nozzle, size and threads to be in accordance with local fire company requirements. The steamer nozzle shall be equipped with a four-and-one-half-inch F NH by five-inch Storz permanent hydrant adaptor with cap and cable connector. The fire hydrants shall have a provision for six-inch connection to the main. Minimum valve opening for the hydrant shall be 4 1/4 inches.
[Amended 12-16-2013 by Ord. No. 43-2013]
(5) 
Concrete. Concrete for cradles and thrust blocks shall be constructed with a minimum 28 days compression strength of 3,500 psi conforming to requirements as specified elsewhere herein.
B. 
Methods of construction.
(1) 
Excavation and backfill shall conform to the requirements for subsurface structure excavation. The contractor shall provide adequate equipment and so operate it as to maintain an essentially dry excavation, stable trench bottoms, suitable working conditions and protection from water damage throughout and until the completion of the work.
(2) 
Water mains shall be laid in straight lines except when otherwise specifically provided or directed by the Engineer. When deviation from a straight line is permitted, the deflection of each joint shall not exceed the manufacturer's recommended maximum for the type of joint and size of pipe being installed. Pipe shall be laid with at least 3 1/2 feet of cover over the top of the pipe to the existing or proposed finished grade, or to the future finished grade when such is lower. Along extensions of roads which are unimproved, the pipe shall be laid with at least four feet of cover over the top of the pipe to the existing grade. The depth of pipe may be increased or slightly decreased locally to pass obstructions. Grade changes shall be accomplished by fittings and/or dividing the necessary deflection among several joints.
(3) 
Special care shall be exercised to remove all earth, stones and other materials from each pipe as it is laid, and to prevent any such materials from entering the pipe line. The contractor shall see that the entire line maintained is absolutely clean on the inside and that all valves and hydrants are clean and in good working order when installed. Open ends shall be at all times adequately protected and shall be securely sealed with approved plugs whenever work is stopped for any reason whatsoever. After removing a plug the interior of the pipe line shall be inspected and cleaned before resuming pipe-laying operations.
(4) 
Before placing each length of pipe, the contractor shall carefully examine it for breaks, cracks or other defects and shall discard any which may appear to be in any way defective. All pipe and fittings shall be handled and installed with care to avoid breakage.
(5) 
Each section of pipe shall be solidly bedded in the trench bottom and shall be supported for its full length except where excess excavation has been made for joints. Before making each joint, the ends of the pipes and all joint members shall be thoroughly cleaned. All jointing shall be done in strict accordance with the manufacturer's recommendations and the directions of the Engineer.
(6) 
The contractor shall do all necessary pipe cutting and shall locate valves, fittings and fire hydrants in the exact positions indicated. He shall provide and use cutting tools of an approved type and in good order, so as to endure clean, square cuts to exact measurements.
(7) 
All fittings and valves shall be set accurately true to and square with pipe lines. Valve stems shall be accurately plumb. Fittings and valves shall be supported by approved blocking so as to ensure their remaining accurately in position during joints and in such manner that their weight will not place undue strain on connecting pipe or points. Valve boxes shall be set plumb, accurately centered with respect to the valve stem, well supported by solidly tamped earth and with their tops flush with the finished surface grade of the roadway or surface of the ground where set. Pipe lines shall be rodded or thrust blocked at the discretion of the Engineer at all bends greater than 10º and at all tees, plugs, valves and fire hydrants so as to prevent movement of the lines under pressure.
(8) 
Before new water lines are put into service, the contractor shall provide the necessary equipment for and shall perform a two-hour pressure test during which time pressure will be maintained at 125 pounds per square inch and the amount of water that must be added to maintain this pressure will be measured. The maximum leakage which will be permitted for sections of the system up to and including 500 linear feet will be 0.01 gallon per inch of diameter per 24 hours per foot of pipe. Where the length of pipe to be tested exceeds 500 linear feet, the total amount of leakage allowed for any such section of pipe shall be the amount which would be allowed for 500 feet. In general, every square root of the length in feet of the section to be tested and divided by the square root of 500. In general, every section of pipe which can be isolated by existing or proposed valves shall be individually pressure tested except where such sections are less than 200 feet in length, in which case they may be tested as a part of another section.
(9) 
Before new water lines are put into service, they shall be completely sterilized with chlorine. The chlorine shall be introduced and distributed into the new pipe lines by suitable and approved means and in such manner that it shall reach all of the pipe and all fittings, valves and appurtenances. Sterilization may be done in connection with pipe testing or independently, as may appear more practical. The manner and method of introduction of chlorine shall be satisfactory to and must be approved by the governing water authority. Sterilizing dosage shall be sufficient to provide the equivalent of not less than 50 parts per million (ppm) of free chlorine to the entire contents of the pipe line or section thereof to be sterilized, and the chlorinated water shall be permitted to remain in the pipe line for a contact period of not less than 24 hours. After sterilization, the water main or section shall be thoroughly flushed and put into service. Any section of pipe line which is drained or emptied of water at any time or for any purpose in connection with this work, whether a newly laid pipe line or part of an existing water main system, shall be sterilized as above specified before being returned to service. Existing water service shall not be interrupted unless necessary for the completion of the work and then only in accordance with the requirements of the Authority.
A. 
Materials.
(1) 
Cast-iron pipe and fittings.
(a) 
Cast-iron pipe shall be centrifugally cast and shall conform to the requirements of the American Standards Association Specifications therefor, as amended and revised to date. In general, cast-iron pipe shall be Thickness Class 22 for nominal pipe diameters of 12 inches and less, and Thickness Class 21 for nominal pipe diameters of 14 inches and greater.
(b) 
Cast-iron pipe shall be provided with mechanical joints which conform to the American Standards Association Specifications therefor, or shall be "Tyton Joint" pipe as manufactured by United States Pipe and Foundry Company, or approved equal.
(c) 
All cast-iron fittings, including Y-branches, shall conform to the requirements of the current American Water Works Association Specifications therefor, except that fittings shall be provided with joints suitable for use with the adjoining pipe. In general, cast-iron fittings shall be Class D for sizes 12 inches and less, and Class B for sizes 14 inches and greater. Cast-iron saddles shall be subject to the approval of the Engineer.
(2) 
Asbestos-cement pipe and fittings.
(a) 
Asbestos cement pipe and fittings shall conform to the requirements of the American Society for Testing Materials Specifications therefor, as amended and revised to date. Except where required for special conditions such as excessive depth, asbestos-cement pipe and fitting shall be nonpressure, and in no case less than Class 2400.
(b) 
All asbestos-cement pipe and fittings shall be furnished complete with sleeve and gasket-type couplings designed for use with the size and class of pipe specified. Cast-iron fittings for use with asbestos-cement pipe shall conform to the requirements for cast-iron fittings hereinabove.
(3) 
Vitrified clay pipe and fittings.
(a) 
Vitrified clay pipe and fittings shall conform to the requirements of the American Society for Testing Materials Specifications therefor, as amended and revised to date. Except where required for special conditions such as excessive depth, vitrified clay pipe and fittings shall be "Extra Strength" or "Vitra-Chem."
(b) 
All vitrified clay pipe and fittings shall have factory-fabricated, gasket-type couplings which conform to the American Society for Testing Materials Specifications therefor, as amended and revised to date.
(4) 
Concrete. Any concrete required for cradles, pads, drop connections at manholes, and any other miscellaneous items shall be 4,000 psi conforming to the requirements set forth elsewhere herein.
B. 
Methods of construction.
(1) 
Excavation and backfill shall conform to the requirements set forth for subsurface structure excavation. The contractor shall provide adequate equipment and so operate it as to maintain an essentially dry excavation, stable trench bottoms, suitable working conditions and protection from water damage throughout and until the completion of the work.
(2) 
Pipe shall be laid in straight lines between manholes except when otherwise specifically provided or directed by the Engineer. When deviation from a straight line is permitted, the deflection of each joint shall not exceed the manufacturer's recommended maximum for the type of joint and size of pipe being installed. All pipe shall be laid to uniform grades between manholes.
(3) 
Before making each joint, the ends of the pipes and all joint members shall be thoroughly cleaned. All jointing shall be done in strict accordance with the manufacturer's recommendations and the directions of the Engineer.
(4) 
No defective or leaking pipe, fittings, joints, connections, manholes or other parts of the work will be acceptable. All visible leakage of any description, and no matter where located, shall be corrected by the contractor in a manner satisfactory to the Engineer, whether or not the total leakage into the sewer is within the allowable maximum as determined by infiltration tests.
(5) 
Infiltration tests shall be made when and as directed by the Engineer, and no connections to flowing lines shall be made until the testing is complete and satisfactory results have been obtained. The contractor shall furnish all labor, material and equipment necessary for the infiltration tests. No section of sanitary sewer between adjacent manholes will be considered satisfactory or acceptable when the rate of infiltration there into exceeds 100 gallons per inch of internal diameter, per mile of sewer, per day; and no section of sanitary sewer one mile or more in length will be considered satisfactory or acceptable when the rate of infiltration there into exceeds 1/2 of the above-specified rate. Leakage in excess of the above shall be located and corrected by the contractor.
(6) 
Y-branches and service laterals which are not to be immediately connected to flowing lines shall be securely plugged with an approved type of plug which will provide a permanently watertight seal.
(7) 
The contractor shall accurately record the station of each Y-branch placed and direction of the Y. He shall also show the location of each Y-branch on his copy of the plans and permanently mark each location with a cross-cut on the curb or a hub stake driven at the curbline.
(8) 
Drop connections or manholes and concrete pads at service risers shall be constructed as shown on the detail sheet of the plans, and at the locations shown on the plans or as directed by the Engineer. All concrete work shall conform to the requirements as set forth elsewhere herein.
(9) 
When so required by the Engineer, the contractor shall flush such newly completed sewers as may be designated by the Engineer, in order to remove any foreign matter which may have accumulated herein during construction. The contractor shall furnish all labor, material, equipment and water necessary for flushing and shall provide for the disposal of water used for flushing.
A. 
Materials.
(1) 
Reinforced concrete pipe: Reinforced concrete pipe shall conform to the requirements of the American Society for Testing Materials Specifications therefor, as amended and revised to date. Unless otherwise specified herein, reinforced concrete pipe shall be Class III, Wall B.
(2) 
Corrugated metal pipe:
(a) 
Corrugated metal pipe and pipe arch shall conform to the requirements of the American Association of State Highway Officials Specifications therefor, as amended and revised to date and conform to the following gauge requirements:
Diameter
(inches)
Gauge
(Alum)
Gauge
(Corr)
15
14
16
18
12
16
21
12
16
24
12
14
30
12
14
36
10
12
42
10
12
48
10
10
54
8
10
60
8
8
(b) 
For pipe diameters in excess of 60 inches the specific design shall be approved by the Engineer.
(c) 
Corrugated metal pipe and pipe arch shall be fully bituminous coated inside and outside in accordance with current American Railway Engineering Association Specifications and shall have bituminous paved inverts. The invert paving shall fill the valleys of the corrugations and cover the crests of the corrugations a minimum of 1/8 inch. For round pipe the invert paving shall cover not less than 25% of the inside perimeter of the pipe, and for pipe arch the invert paving shall cover not less than 40% of the inside perimeter of the pipe.
(3) 
Concrete. Concrete of 4,000 pounds per square inch conforming to the requirements set forth elsewhere herein shall be used for the construction of concrete cradles and in making the connections to existing drainage structures.
B. 
Methods of construction.
(1) 
Excavation and backfill shall conform to the requirements for subsurface structure excavation. The contractor shall provide adequate equipment and so operate it as to maintain an essentially dry excavation, stable trench bottoms, suitable working conditions and protection from water damage throughout and until the completion of the work.
(2) 
Pipe shall be laid in straight lines between drainage structures except when otherwise specifically provided. When deviation from a straight line is permitted, the deflection of each joint shall not exceed the manufacturer's recommended maximum for the type of joint and size of pipe being installed. All pipes shall be laid to uniform grades.
(3) 
Each section of pipe shall be solidly bedded in the trench bottom and shall be supported for its full length except where excess excavation has been made for the joints. Before making each joint, the ends of the pipes and all the joint members shall be thoroughly cleaned. All jointing shall be done strictly in accordance with the manufacturer's recommendations.
(4) 
No defective or leaking pipe, joints, connections, manholes, inlets, or other parts of the work will be acceptable. All visible leakage of any description, and no matter where located, shall be corrected by the contractor in a manner satisfactory to the Engineer.
(5) 
Except when necessary to maintain a flow, storm drains shall not be placed in embankment until the embankment has been constructed and consolidated to proposed finished grade or subgrade, or to an elevation not less than three feet above the proposed top of pipe, whichever is lower. After an embankment has been so constructed, trenches for storm drains shall be excavated as hereinabove specified.
(6) 
When so required by the Engineer, the contractor shall flush such newly completed storm drains as may be designated by the Engineer, in order to remove any foreign matter which may have accumulated therein during construction. The contractor shall furnish all labor, material, equipment and water necessary for flushing and shall provide for the disposal of water used for flushing.
(7) 
The locations of existing pipes and structures shown on the plans are approximate, and before construction the contractor shall determine the exact locations of all existing pipes and structures in the vicinity of the proposed work. Connections to existing pipes and structures shall be made in a manner satisfactory to the Engineer.
A. 
Materials.
(1) 
Concrete. Concrete shall conform to the requirements specified elsewhere herein.
(2) 
Concrete block: Concrete block for the construction of manholes, inlets and catch basins shall conform to the requirements of the American Society for Testing Materials Specifications therefor, as amended and revised to date. Concrete blocks for manholes shall have the required radius and batter.
(3) 
Brick: Brick shall be Grade MA conforming to the American Society for Testing Materials Specifications therefor, as amended and revised to date.
(4) 
Mortar. Mortar shall be 1.2 cement-sand mortar.
(5) 
Iron castings: Iron castings shall conform to the requirements of the American Society for Testing Materials Specifications for gray iron casting, as amended and revised to date, supplemented as follows: Castings shall be boldly filleted, and arises shall be sharp and perfect. The castings shall be true to pattern in form and dimension, free of pouring faults, sponginess, cracks, blowholes and other defects which affect their strength and value for the service intended. The bearing surfaces of frames, covers and grates shall be fitted together so as to prevent rocking and the pieces match-marked.
(6) 
Ladder rungs: Ladder rungs shall be fabricated of rolled wrought iron or aluminum conforming to the current American Society for Testing Materials Specifications therefor and shall be subject to the approval of the Engineer.
B. 
Methods of construction.
(1) 
Excavation and backfill shall conform to the requirements for subsurface structure excavation. Manholes, inlets and catch basins shall be constructed in accordance with the standard details shown on the plans. Unless otherwise specified or directed, manholes, inlets and catch basins may be constructed of either brick, concrete block or concrete of 400 psi. The foundations for all manholes, inlets and catch basins shall be concrete of 4,000 psi.
(2) 
Concrete construction shall conform to applicable requirements elsewhere herein.
(3) 
Concrete blocks and bricks shall be laid with vertical joints staggered. Joints shall be not more than 1/2 inch thick and shall be completely filled with mortar. The masonry shall be carried to such a height that a mortar joint not more than 1/2 inch thick will be required for setting the head casting without using split blocks or bricks. Outside walls shall be plastered with a five-eighths-inch thick coat of mortar, troweled to a smooth finish.
(4) 
Outside walls of sanitary sewer manholes shall receive two coats of an approved coal tar pitch.
A. 
Materials.
(1) 
Materials for backfill, if acceptable to the Engineer or his representative, shall be the material excavated, except that any large and frozen lumps, wood, boulders or other foreign matter shall be removed before placing.
(2) 
If the excavated material is not acceptable as backfill material, all excavations shall be backfill with run-of-bank sand and gravel. All excess excavated will be disposed of by the contractor in a manner acceptable to the Engineer.
B. 
Methods of construction.
(1) 
The contractor shall do all excavations of whatever substances encountered to the depth shown on the plans.
(2) 
Excavation shall not be carried below the required level except where unstable soil is encountered. The Engineer shall determine the depth of removal of unstable soil and the contractor shall at the Engineer's direction remove and replace same with gravel, crushed stone or crushed slag thoroughly tamped. Whenever excavation has been made below the required level, it shall be replaced with gravel, crushed stone or crushed slag and shall be thoroughly tamped.
(3) 
The ground adjacent to the excavation shall be graded to prevent water from running in. The contractor shall remove any water accumulating in excavations by pumping or other suitable means.
(4) 
The contractor shall do all bracing, shoring and sheeting necessary to prevent failure of the banks of public, underground and aboveground utilities and structures, pavements, and public and private property. No bracing, shoring, or sheeting shall be placed below the bottom of the pipe or structure unless approved by the Engineer.
(5) 
The contractor shall provide, install and operate an adequate well-point system of dewatering when necessary to stabilize trench bottoms and banks or other excavations or when necessary to protect the work, workmen, public, underground and aboveground utilities and structures, pavements, and public and private property. The well-point system or portions thereof shall be removed by the contractor upon the completion of backfill, and the holes remaining from the points shall be backfilled and thoroughly tamped.
(6) 
Excavation for manholes and other structures shall have a twelve-inch minimum clearance and twenty-four-inch maximum clearance on all sides. The width of trenches for pipe shall be not less than 16 inches and not more than 22 inches in excess of the outside diameter of the pipe. Rocks and boulders present in excavation shall be removed within six inches of the pipe. Banks of excavation, unless otherwise indicated or allowed, shall be vertical.
(7) 
Preliminary excavation shall be made only to a depth of three inches above the final depth of any trench or other excavation. The remaining depth shall be carefully excavated, shaped, and formed with hand tools immediately preceding laying of pipe or placing concrete. Trench bottoms shall be accurately formed to receive and support the bottom of the barrel of the pipe. Additional excavation shall be made in pipe trenches at the pipe joints and to prevent any possibility of a pipe resting on the bell rather than the barrel.
(8) 
After the structure has been completed, inspected and approved or, in the case of pipe, after each joint has been made, inspected and approved, backfilling shall proceed immediately. Where pipe has been laid this shall be done in four-inch layers of suitable fine material, each layer thoroughly tamped, to a height of 12 inches above the top of the pipe. The remainder of the trench and the entire excavation for all structures other than pipe shall be backfilled in nine-inch layers, loose measure, each layer thoroughly tamped. Dampening of the material to be tamped may be required by the Engineer.
(9) 
Puddling or flushing in lieu of tamping may be used if approved by the Engineer or may be required by the Engineer. Shoring, sheeting, and bracing of any kind shall be withdrawn as the backfilling proceeds, except that the Engineer may require such bracing to be left in place if it has been placed below the bottom of any structure or pipe or if he deems it necessary in order to protect adjacent structures, utilities or property.
A. 
Tot-lots. Tot-lots shall as a minimum provide three kinds of play facilities for young children such as a sand box, climbing apparatus, swings. A seating area for adults will also be required.
B. 
Tennis courts. Tennis courts shall be regulation size, and shall contain, as a minimum, the following improvements:
(1) 
The courts shall be surrounded by a twelve-inch-high fence and buffer planting as approved by the Planning Board.
(2) 
One bench per court shall be provided.
(3) 
Night lighting shall be provided.
(4) 
The courts shall be paved in a manner acceptable to the Township Engineer.
C. 
Basketball courts. Basketball courts shall be a minimum size of 35 feet to 60 feet and shall contain as a minimum the following improvements:
(1) 
Two regulation backstops with nets.
(2) 
Paved in a manner acceptable to the Township Engineer.
(3) 
Night lighting.
D. 
Multipurpose fields: Multipurpose fields shall be a minimum size of 200 feet by 350 feet and shall be completely grassed.
E. 
Swimming pools shall be a minimum of 1,800 square feet.
F. 
Other facilities shall be constructed to standards approved by the Township Engineer.
[Added 12-20-1993 by Ord. No. 20-1993]
A. 
There shall be included in any new multifamily housing development that requires subdivision or site plan approval an indoor or outdoor recycling area for the collection and storage of residentially generated recyclable materials. The dimensions of the recycling area shall be sufficient to accommodate recycling bins or containers which are of adequate size and number, and which are consistent with anticipated usage and with current methods of collection in the area in which the project is located. The dimensions of the recycling area and the bins or containers shall be determined in consultation with the Municipal Recycling Coordinator and shall be consistent with the district recycling plan adopted pursuant to Section 3 of P.L. 1987, c. 102 (N.J.S.A. 13:1E-99.13) and any applicable requirements of the Municipal Master Plan, adopted pursuant to Section 26 of P.L. 1987, c. 102.
B. 
The recycling area shall be conveniently located for the residential disposition of source-separated recyclable materials, preferably near, but not separated from, a refuse dumpster.
C. 
The recycling area shall be well lit, and shall be safely and easily accessible by recycling personnel and vehicles. Collection vehicles shall be able to access the recycling area without interference from parked cars or other obstacles. Reasonable measures shall be taken to protect the recycling area, and the bins or containers placed therein, against theft of recyclable materials, bins or containers.
D. 
The recycling area or the bins or containers placed therein shall be designed so as to provide protection against adverse environmental conditions which might render the collected materials unmarketable. Any bins or containers which are used for the collection of recyclable paper or cardboard, and which are located in an outdoor recycling area, shall be equipped with a lid, or otherwise covered, so as to keep the paper or cardboard dry.
E. 
Signs clearly identifying the recycling area and the materials accepted therein shall be posted adjacent to all points of access to the recycling area. Individual bins or containers shall be equipped with signs indicating the materials to be placed therein.
F. 
Landscaping and/or fencing shall be provided around any outdoor recycling area and shall be developed in an aesthetically pleasing manner.