[Amended 2-22-1984 by Ord. No. 3-1984]
A. Except as hereinafter provided, no building permit
shall be issued for a building or change of use or enlargement of
any building or use unless a site plan is first submitted and approved
in accordance with the Land Development Ordinance and no certificate
of occupancy shall be given unless all construction conforms to the
approved plan.
B. Temporary certificates of occupancy.
(1) The Planning Board may authorize the issuance of temporary
certificates of occupancy for good cause shown, and, furthermore,
the Chief Construction Official shall be authorized to issue a temporary
certificate of occupancy for any nonresidential development for a
period of time not to exceed 180 days. Temporary certificates of occupancy
shall be issued only for the following exterior site improvements:
(2) The time period of a temporary certificate of occupancy
issued by the Chief Construction Official shall be extended only by
an action of the Planning Board of Egg Harbor Township.
C. All volunteer fire companies and ambulance and rescue
squads of the Township of Egg Harbor shall not have to satisfy site
plan requirements.
[Added 10-8-1986 by Ord. No. 39-1986]
[Added 2-22-1984 by Ord. No. 3-1984]
After Planning Board approval, a detailed site
development plan shall not be subject to change. Any change in site
design subsequent to such approval shall be regarded as a separate
plan, and site development plans showing the proposed new design shall
be submitted under the requirements of the Township and shall be separately
approved under the provisions set forth in the Land Development Ordinance
of Egg Harbor Township.