A.
Upon receipt of an application, the Secretary of the Planning Board shall submit the application to the Technical Coordinating Committee (TCC). The TCC shall review the application in order to determine whether or not it is complete and shall submit its findings to the Planning Board for action. If the application is declared complete by the Planning Board, copies of the same shall be forwarded by the Secretary of the Planning Board to such persons and agencies as directed by the Board, with a request for a written report from such persons or agencies within 20 days of receipt of the request.
B.
The persons and agencies from whom reports may be required may include but shall not be limited to the following: the County Planning Board, the Township Engineer, the Planning Consultant, the Ad Hoc Environmental Committee, the Board of Health, the Police Department, the Fire Department and such other Township officials as may be directed, and one copy is to be placed on file with the Township Clerk for public inspection.