A building or compliance permit is required for any change in
the use of land, type of use or occupancy of any structure or for
a change to the amount of parking required by this chapter. For changes
in use, additional improvements may be required to bring the site
into compliance with current standards.
The following information is required:
A. Plans shall indicate the location, nature and extent of the proposed
work.
B. Plans shall provide sufficient detail to demonstrate compliance with
the building code and other relevant ordinances and regulations.
The holder of a building or compliance permit shall request
an inspection upon completion of the work. Any damages occurring during
construction shall be restored to their original condition. Upon successful
completion, a certificate of occupancy or other applicable approval
will be granted.
Structures, or parts thereof, shall not be occupied or used
until a certificate of occupancy is issued.
A. Accessory structures and uses may be included in the certificate
of occupancy for the principal use, provided they are included with
the permit, shown on the construction documents and completed at the
same time as the principal use.
B. A temporary certificate of occupancy may be issued in advance of
a final certificate of occupancy in situations where certain building
or site improvements are not complete, provided the portion of the
building or site complies with the provisions of this chapter and
the building code and does not pose a threat to public health, safety
or welfare. The Building Official may establish a time limit for the
temporary certificate of occupancy. Failure to obtain a final certificate
of occupancy within the specified time shall constitute a violation.
C. A final certificate of occupancy shall be issued upon compliance
with the provisions of this chapter and other applicable regulations.
If a final certificate of occupancy is denied, written notification
will be provided to the applicant within five days.
D. A certificate of occupancy shall remain in effect until the use of
the structure or land changes.