[Adopted 5-9-1969 as Ord. No. 106]
This Article shall be known and may be cited as the "Road Improvement Ordinance of the Township of Bethlehem."
[Amended 12-10-1971 by Ord. No. 132]
The purpose of this Article shall be to apply rules, regulations and standards regulating the improvements required prior to the acceptance of roads into the municipal road system of the Township of Bethlehem, be the same new roads hereafter created or be the same existing roads or rights-of-way presently used but not accepted into the municipal road system of the Township of Bethlehem and not heretofore accepted for full municipal maintenance. In addition, the purpose of this Article shall be to apply rules, regulations and standards regulating the improvement of roads not to be accepted into the municipal road system of the Township of Bethlehem but created by provision of the Zoning and Subdivision Ordinances of the Township of Bethlehem[1] and after completion thereof, constituting private roads.
[1]
Editor's Note: See Ch. 102, Land Use and Development.
Subsequent to the adoption of this Article, all roads shall comply with the following standards of construction before the same are accepted into the municipal road system of the Township of Bethlehem and accepted for full municipal maintenance.
As used in this Article, the following terms shall have the meanings indicated:
PLAN
The road improvement plan approved by the Planning Board of Bethlehem Township where a new road or an improvement of an existing road is required by virtue of a subdivision, or a road improvement plan approved by the Township Engineer in the case of an existing road being improved to township standards for the purpose of acceptance into the township road system for full municipal maintenance.
STANDARD SPECIFICATIONS
Those applicable specifications set forth in Standard Specifications for Road and Bridge Construction, 1961, New Jersey State Highway Department.
A. 
Clearing site. The ground surface beneath the new roadway shall be cleared of all trees, brush, weeds, roots, matted leaves, small structures, debris and other unsuitable material. Tree stumps shall be grubbed out unless they will be at least three feet below the proposed road grade.
B. 
Excavation.
(1) 
The vegetation and underlying topsoil within excavation and embankment areas shall be stripped off to a depth of one foot below the existing ground surface.
(2) 
Excavation shall be carried to the lines, grades and slopes shown on the plan.
(3) 
Unstable or unsuitable material encountered at the prescribed bottom limits of roadway excavation or during the formation of embankment shall be removed within the limits of the proposed pavement and shoulders. The excavated areas shall be backfilled with suitable, approved material obtained from other excavation or with subbase material, as directed by the Township Engineer. The backfill shall be placed and compacted as specified for embankment. The construction of embankment shall not proceed if the embankment material is excessively wet.
C. 
Embankment.
(1) 
The material used for embankment shall in all ways comply with the standards of the New Jersey State Highway Department and shall be free from stumps, brush, weeds, roots, sod, rubbish, garbage and other matter that may decay.
(2) 
Embankment shall not be constructed between December 1 and March 1 unless the soil moisture conditions are such that compaction can be performed as specified. Embankment shall not be constructed on frozen ground nor shall frozen material be used for embankment.
(3) 
All vegetation and topsoil shall be stripped off the existing ground surface, as outlined under Subsection B above, before embankment material is placed.
(4) 
Backfill in rock excavation areas shall be made with subbase material. Rocks larger than 12 inches in any dimension shall not be placed within a distance of three feet from proposed or existing pipes, culverts, utility poles or other subsurface structures above an elevation one foot below the bottom of such facilities.
(5) 
Compaction shall be to a density of not less than 95% at optimum moisture content.
(6) 
The embankment shall be compacted by the rolling or vibrating method as follows:
(a) 
Rolling or vibrating method. The embankment shall be placed in layers not more than six inches thick, loose measurement, and each layer shall be compacted by one of the following alternative types of equipment and number of passes of each:
[1] 
Smooth-faced power rollers, either solid-surface or pad-type, weighing not less than 10 tons and having a load of not less than 330 pounds per inch of width of roller surface when wheels are in contact with a level surface. The load requirements for solid-surface rollers apply to the rear wheels. There shall be a minimum of four passes per layer. A "pass" is defined as one passage of a compacting wheel over the entire surface of the layer.
[2] 
Pneumatic tire rollers having a load of not less than 225 pounds per inch of width of tire surface in contact with the ground, with the tires on the front and rear axles staggered with respect to each other so that they cover the entire strip over which the roller travels. There shall be a minimum of five passes per layer. A "pass" is defined as one passage of one tire over the entire surface of the layer.
[3] 
Tamping-type or sheepsfoot roller, each unit of which shall consist of one or more cylindrical sections having studs or feet projecting not less than 6 1/2 inches from the surface of the drums and developing a load of not less than 200 pounds per square inch of bearing surface when a complete row of tampers is in contact with a level surface. There shall be a minimum of eight passes per layer. A "pass" is defined as one passage of such a unit over the entire surface of the layer.
[4] 
Fifty-ton compactor. A pneumatic tire-type roller capable of being loaded in increments to a gross weight of 50 tons. The tires shall be spaced so that the clear width between adjacent tire treads on the same axle shall be not more than the width of the tire. When operating at a gross weight of 50 tons, the tire inflation shall be not less than 90 pounds per square inch, and the load on each tire shall be not less than 25,000 pounds. There shall be a minimum of five passes per layer by the compactor loaded to a gross weight of not less than 50 tons. A "pass" is defined as one passage of a wheel of the compactor over the entire surface of the layer.
[5] 
Dynamic compactor. A vibratory compactor, acceptable to the Township Engineer, capable of operating at the optimum frequency vibration required for the size and type of the compactor in use and the material being compacted. There shall be not less than two and not more than five passes per layer, and the actual number, within this range, shall be as directed by the Township Engineer, depending upon the type of material being compacted. A "pass" is defined as one passage of the vibrating unit over the entire surface of the layer.
(7) 
Water shall be applied to the loose layers of embankment when directed by the Township Engineer.
A. 
Materials. The materials for large aggregate and screenings shall be broken stone or blast furnace slag conforming to the types and requirements of the New Jersey State Highway Department. The large aggregate shall be 2 1/2 inches in size.
B. 
Methods of construction.
(1) 
Dynamic compactors shall be vibratory compactors, acceptable to the Township Engineer, capable of operating at the optimum frequency of vibration required for the size and type of compactor in use and material being compacted.
(2) 
Three-wheel rollers shall be power driven, shall have a total weight of not less than 10 tons and a weight on the rear rolls of not less than 250 pounds per inch of width of roll.
(3) 
Two-axle tandem rollers shall be power driven, shall have a total metal weight of not less than eight tons and a weight of not less than 250 pounds per inch of width on the drive roll.
(4) 
Three-axle tandem rollers shall be power driven and shall conform to the requirements specified in Subsection B(4)(a) or (b) below:
(a) 
Rollers having two guide rolls of equal diameter and a larger diameter drive roll, all rolls having equal width. The drive roll shall have a compression of not less than 250 pounds per inch of width of tread when all rolls are in contact with a level surface. The rollers shall have a total metal weight of not less than 12 tons and a wheel base of not less than 17 feet measured from the center of the front guide roll to the center of the drive roll. The rolls, when locked in position for all treads to be in the same plane, shall conform to the rigidity requirements prescribed under the following tests, with full load:
[1] 
With the weight of the roller supported on the central roll and drive roll, the tread of the central roll shall be not more than 1/8 inch above the plane tangent to the treads of the end rolls; and
[2] 
With the weight of the roller supported on the end rolls, the tread of the central roll shall be not more than 1/4 inch below the plane tangent to the treads of the end rolls.
(b) 
Rollers as described in Subsection B(4)(a) above which, when the rolls are in a semilocked position, will meet the rigidity test described in Subsection B(4)(a)[1] above and which shall be so designed that, with the rolls in a semilocked position and with the weight of the roller supported on the end rolls, the central roll will ride freely on the surface being rolled and there will be no transfer of weight from any one roll to another.
(5) 
Trench rollers, for use in areas inaccessible to the larger compacting equipment described above, shall be of acceptable design and shall have a load of not less than 300 pounds per inch of width of tread of drive roll.
(6) 
Small vibratory compactors, for use in areas inaccessible to the larger compacting equipment specified above, shall be of a design acceptable to the Township Engineer.
(7) 
Stone spreaders shall be equipped with a strike-off bar or screed capable of being adjusted to the required grade and crown and shall be subject to the approval of the Township Engineer.
(8) 
Pressure distributing trucks shall conform to the requirements of the New Jersey State Highway Department.
(9) 
The subgrade shall be in a properly finished condition and not wet or frozen when the base course is about to be placed thereon.
C. 
Where the macadam base course will be constructed adjacent to proposed curbs, the construction, curing and backfilling of the curbs shall be completed before the macadam aggregate is spread adjacent thereto.
D. 
The surface of the completed base course shall be, at all points, within 1/2 inch of the prescribed grade of the base course. Within any distance of 16 feet, the sum of the departures from the prescribed base course grade of any two points, one of which is above and other below the prescribed grade, shall not exceed 1/2 inch, except that the base course shall conform to its prescribed grades where it adjoins curbs. There shall be no projections or depressions in the surface of the base course such as to form waves exceeding 1/2 inch in any distance of 16 feet.
E. 
The completed base course shall be of sufficient stability that no perceptible movement is produced in it by the passage of a wheel load of eight tons concentrated on a width of not more than 24 inches. It shall be smooth and even and at the prescribed grade, within the tolerances hereinabove specified, free from voids, ruts, loose aggregate and raveled areas, surplus binder that hides the top of the coarse aggregate, dirt and other foreign matter and shall be in this condition at the time an intermediate or a surface course is to be constructed thereon. The contractor shall repair or replace all such defective areas and shall clean the surface and put it in the prescribed condition without additional compensation.
F. 
Prior to the construction of a bituminous concrete surface on the macadam base course, the base course shall be given a bituminous prime coat. The materials, rate of application and quantity for the prime coat shall be as provided therefor in the plan.
A. 
Vibrating method.
(1) 
The macadam base course shall be constructed in one layer.
(2) 
The large aggregate shall be spread by means of a stone spreader in a layer or layers of proper thickness and shall be shaped so that, after ultimate binding and compaction, the base course will conform to the prescribed thickness, grade and crown. The aggregate shall not be deposited in piles on any areas of the subgrade over which it will be spread. When so ordered by the Township Engineer, the thickness of the course shall be measured by wood blocks of the required depth placed on the subgrade or on the previously laid course. These blocks shall be removed when they have served their purpose for testing, and the holes shall be filed with aggregate which shall be thoroughly compacted. Only sufficient aggregate for a day's work shall be spread in advance of compacting and binding. All segregated or poorly graded aggregate shall be removed and replaced with properly graded aggregate.
(3) 
After the large aggregate has been spread, it shall be compacted over its entire area by the vibratory compaction equipment hereinbefore specified. Vibration shall continue until the aggregate is sufficiently keyed to permit its being rolled with the specified rollers; provided, however, that there shall be not less than two and not more than five passes, the exact number to be determined by the Township Engineer during construction. The entire area of the base course shall then be rolled longitudinally with three-wheel rollers or with two-axle or three-axle tandem rollers and, where practicable, diagonally with three-wheel rollers. Longitudinal rolling shall start at the edges and progress towards the center, except that on superelevated curves, the rolling shall begin on the low side and progress to the high side. On each pass of the roller, the drive rolls shall uniformly overlap their preceding tracks.
(4) 
Where the macadam course is constructed against a prepared berm, the longitudinal rolling shall proceed back and forth over the edge of the aggregate and on the adjacent berm for a width of not less than 18 inches until the berm is compacted thoroughly and will provide sufficient lateral support to prevent sidewise displacement of the aggregate during subsequent operations.
(5) 
As the rolling progresses, any irregularities in the surface of the base course shall be corrected by the addition or removal of aggregate, where necessary, and reshaping and rerolling. The process shall continue until the base course has been brought to an even surface, free from excessive projections and depressions, and does not creep or wave under the operation of the roller.
(6) 
After completion of the shaping, vibrating and rolling specified above, screenings shall be spread over the aggregate in three applications, by means of stone spreaders, sufficient in total quantity to completely fill the voids in the stone course. Approximately 50% of the total quantity of screenings shall be placed in the first application, approximately 25% in the second application and the remainder in the third application. The screenings of each application shall be spread uniformly over the aggregate course and shall be vibrated into the voids by a single pass of the dynamic compactor over the entire area. No further mechanical vibration shall be performed unless directed by the Township Engineer. If there be any visible voids after the completion of the operations specified above, they shall be filled by hand spreading, brooming and rolling. All screenings shall be dry when vibrated into the voids. A mechanical dryer shall be used to dry the screenings if and when necessary. The quantity of screenings, the vibrating equipment and the regulation of the vibrating shall be such that all voids in the stone aggregate will be filled without causing floating of the aggregate. The entire surface shall be rolled with three-wheel and tandem rollers, as specified hereinabove for rolling of the aggregate prior to its filling, until the base course shows no perceptible movement under the roller.
(7) 
Areas of the base course that are inaccessible to the large rollers and dynamic compactors shall be vibrated by small vibratory compactors and rolled with trench rollers in a manner acceptable to the Township Engineer.
(8) 
In small, narrow or irregular shape areas where the use of stone spreaders is not practicable, the large aggregate and screenings may be applied, spread and shaped by hand methods.
B. 
Rolling method. The requirements and provisions hereinabove specified for the vibrating method shall apply, except as otherwise hereinafter specified:
(1) 
Macadam base courses shall be in one layer.
(2) 
The keying and compaction of the layer or layers of large aggregate shall be accomplished by rolling, using three-wheel rollers and two-axle or three-axle tandem rollers.
(3) 
After the large aggregate has been compacted and surface irregularities have been corrected, screenings shall be spread in thin uniform layers by means of stone spreaders and shall be broomed into all visible voids and rolled. The screenings shall not be applied in such quantity as to completely cover or form a layer or coating over the large aggregate. Screenings that do not properly work into the voids and all excess screenings shall be removed. Where a deficiency of screenings develops during the rolling operations, more shall be added and swept into all visible voids. This procedure shall continue until all the voids are filled. Rolling shall be performed with the same type of rollers and in the same general manner as specified for the vibrating method.
(4) 
Screenings shall be dry when rolled. A mechanical dryer shall be used to dry the screenings when necessary.
(5) 
In areas inaccessible to the specified stone spreaders and the larger rollers, the large aggregate and screenings may be spread by hand methods and shall be rolled with trench rollers.
C. 
Measurements. The base course large aggregate shall have a minimum compacted weight in place of 360 pounds per square yard.
A. 
Paved streets. The type of paving shall be for a seven-inch improved pavement. It shall have a base of four inches, compacted, of macadam base course bound up completely with Grade B screenings. The pavement surface shall be one of the following types:
(1) 
Two inches of one-and-one-half-inch crushed stone penetrated with 1.90 gallons per square yard (cold measure) of tar Grade RT-11 or 12 or asphalt OA-4, covered with three-fourths-inch or five-eighths-inch crushed stone chips and then covered with a one-and-one-half-inch compacted depth of Type A or T or FABC-1 premixed surface pavement. All work shall be done under the State Highway Specifications or equivalent approved by the Township Engineer.
(2) 
Three inches of one-and-one-half-inch crushed stone penetrated with two applications of the same grades of bituminous material as mentioned in Subsection A(1) above, the first application being two gallons per square yard (cold measure) and covered with three-fourths-inch or five-eighths-inch crushed stone chips; the second application being approximately 0.75 gallon per square yard (cold measure) and covered with three-eighths-inch crushed stone chips. All operations are to be completely rolled. After 30 days, a seal coat of 1/3 gallon per square yard (cold measure) of tar Grade RT-7 or 8 or asphalt RC-250 or 800 is applied and covered with 25 pounds per square yard of three-eighths-inch crushed stone chips and is rolled. All work shall be done under the State Highway Specifications or equivalent approved by the Township Engineer. The type of bituminous material used in the seal coat must agree with that used in penetration, i.e., tar or asphalt.
B. 
The street shall be graded and improved in accordance with these specifications and shall conform to a typical cross section drawing which has been prepared by the Township Engineer and annexed hereto as Exhibit A.[1] The road typical section shown without curbs shall be used in all cases where curbs are not required.
[1]
Editor's Note: Exhibit A is on file in the office of the Township Engineer.
Where required by the plan, curbs shall be of portland cement construction or Belgian block construction as follows:
A. 
Portland cement construction.
(1) 
Materials. Concrete shall be Class B as specified in Article 4.1.2 of the Standard Specifications and shall be air-entrained.
(a) 
Joint filler of the preformed bituminous cellular type shall conform to the requirements specified therefor in Article 8.5.31 of the Standard Specifications.
(b) 
Curing material of clear or translucent liquid compound shall conform to the requirements therefor specified in Article 8.5.29 of the Standard Specifications.
(2) 
Excavation and backfill. The foundation for the curb, and backfilling, shall be well compacted by means of flat-faced mechanical tampers or by other means approved by the Township Engineer.
(3) 
Driveways and entrances. Curbs at driveways and entrances shall be depressed so that the top is two inches above the adjacent pavement or shoulder surface. The width of opening shall be approved by the Township Engineer, and in no case shall a single opening be wider than 20 feet for a residence or 40 feet for other uses.
(4) 
Preparation and placing. Preparation of the concrete shall be as specified in Article 3.12.3 of the Standard Specifications, except that the consistency shall be as specified in Article 4.1.3 of the Standard Specifications.
(a) 
Wood or metal forms may be used and shall be constructed to conform to the lines and grades established by the plan, as approved, except that minor grade and line adjustments shall be permitted in the field with the prior approval of the Township Engineer. The materials and methods used for lubricating the forms shall be such that will not discolor or stain the concrete. Forms shall be removed when the concrete has hardened sufficiently to be self-supporting yet in ample time to allow for finishing as hereinafter specified.
(b) 
The concrete shall be tamped and spaded or vibrated so that the forms are completely filled, the concrete is thoroughly compacted and mortar is flushed to the face and top. The top and face shall be finished with a wood float to an even, smooth and dense surface to form a neat and workmanlike appearance.
(5) 
Joints. Expansion joints shall be provided at approximate equal distances of not more than 20 feet and shall be filled with preformed bituminous cellular type joint filler, 1/4 inch thick, which shall be inset 1/4 inch from the top and face. Curb joints shall be neatly rounded to a one-fourth-inch radius.
(6) 
Curing. Concrete curbs shall be cured with clear or translucent liquid compound which shall be applied as soon as the concrete has been finished. The rate of application and workmanship shall in all ways agree with § 136-10G of this Article.
(7) 
Existing curbing. Gradual transitions shall be constructed where changes in the size or shape of curbs occur in a continuous section.
(8) 
Measurements. All curbs shall be constructed and located as shown on the Construction Detail for Concrete Curbs.
B. 
Belgian block construction.
(1) 
Belgian (granite) block curb shall be constructed to the lines and grades shown on the plan, and the dimensions shown on the detail shall govern. Granite blocks shall be of uniform quality, structure and texture and with a percentage of wear of not more than 4.5%. The blocks shall be dressed so that all faces are approximately rectangular and so that the blocks can be set with the greatest dimension vertical, with joints not more than 1/4-inch wide. The dimension of the blocks shall be as follows:
Dimension
Not Less Than
(inches)
Not More Than
(inches)
Height
10
14
Width
5
7
Depth
4
5
(2) 
The blocks shall be all from one quarry and of the same color and texture. All edges shall be parallel with and at right angles to each other.
(3) 
Setting Belgian block curb. The granite blocks shall be set with the greatest dimension vertical, the next greatest dimension parallel with the line of the curb and the least dimension perpendicular to the line of the curb. The blocks shall be set in concrete, Class C of the Department of Transportation specifications. When the blocks are in final position, the dimensions for the Class C concrete shown on the detail shall govern. The bottom of the trench shall be excavated to such a depth as will provide not fewer than eight inches of concrete under the longest block. All curbing shall be set accurately to line and grade and shall present an even, unbroken line for the entire length of the work. Where shown on the plan or where directed by the Township Engineer, the curb shall be lowered to within two inches of the surface of the roadway pavement (gutter) to provide for driveways and entrances. When set in final position, the curb shall have a uniform batter of one inch per foot. Within five feet of each inlet, blocks of at least 12 inches in height shall be used to conform to the eight-inch curb piece of the inlet casting. Articles 5.5.3 and 8.5.28 of the Standard Specifications for Roads and Bridge Construction, 1961, shall govern this work and these materials unless specifically altered by the subsections above.
Where required by the plan, the following specifications shall be applicable:
A. 
Materials. All sidewalk construction shall be of portland cement concrete. Concrete shall be Class C, as specified in Article 4.1.2 of the Standard Specifications, and shall be air-entrained. The materials for concrete and the materials and methods used for air entrainment shall be as specified in Article 3.12.2 of the aforementioned Standard Specifications and preformed bituminous cellular type and preformed bituminous-type joint fillers shall conform to the requirements specified respectively therefor in Article 8.5.31 of the same aforementioned Standard Specifications.
B. 
Subgrade. The subgrade for all sidewalks shall be constructed smooth and even and at the prescribed grade. It shall be compacted by not less than three passes of a tandem roller [3 1/2 to five tons]. Areas inaccessible to a roller shall be compacted by an approved flat-faced mechanical tamper acceptable to the Township Engineer.
C. 
Base. All sidewalks shall have a four-inch gravel or cinder base suitably compacted at the direction of the Township Engineer. The base shall be dampened prior to placing of the concrete to prevent loss of water to the base and subgrade.
D. 
Measurements. All sidewalks shall be four feet wide and four inches thick and shall be located and constructed as shown on the Construction Detail for Concrete Sidewalks. All sidewalks at driveways shall be at least six inches thick.
E. 
Concrete work. Preparation of the concrete shall be as specified in Article 3.12.3 of the Standard Specifications. After being placed, the concrete shall be tamped, screeded and finished to true grade and surface. The finish shall be made with a wood float, followed by brushing with a wet soft-hair brush to a neat and workmanlike surface.
F. 
Joints. Transverse expansion joints, 1/2 inch wide, shall be provided at intervals of not more than 16 feet and filled with preformed bituminous cellular-type joint filler. Longitudinal points, 1/4 inch wide, shall be provided between curbs and abutting sidewalks and shall be filled with preformed bituminous-type joint filler. The top of all joint filler material shall be 1/4 inch below the top of the sidewalk. Transverse surface grooves shall be cut into the sidewalk surface between expansion joints at intervals equal to the sidewalk width. All edges shall be neatly rounded with a one-fourth-inch radius.
G. 
Curing. Sidewalks shall be cured with clear or translucent liquid compound which shall be applied as soon as the concrete has been finished. The compound shall be applied in one application at a rate of one gallon per 200 square feet of surface and in a continuous uniform film. If the film becomes damaged in any way, the contractor shall apply a new coat of material to the affected areas equal in curing value to that specified for the original coat. The treated surface shall be protected from all vehicular and pedestrian traffic for a period of at least three days.
H. 
Finishing. Sidewalks shall be finished with a slightly roughened surface using a wood float or broomed with a hair broom.
I. 
Where the words "Standard Specifications" are mentioned herein, these are the Standard Specifications for Road and Bridge Construction, 1961, New Jersey State Highway Department.
A. 
Provision shall be made for adequate drainage facilities, including, by way of example and not by way of limitation, cross-drains, runoffs, culverts, storm sewers, catch basins, drop inlets and, if required, a storm sewer system with adequate drop inlets and catch basins. All drainage facilities must be approved by the Township Engineer so as to ensure adequate disposal of surface water.
B. 
All driveway pipes and drainage facilities must be of cast-iron pipe or reinforced concrete pipe of standard strength. All sizes of pipe are to be approved in advance of installation by the Township Engineer, but in no case shall the owner, developer or builder install a pipe of less than 12 inches inside diameter. Drainage calculations must be submitted by the developer's engineer.
Installations shall follow the standard design of culs-de-sac, annexed hereto as Exhibit B, and State of New Jersey Department of Transportation Standard Details, annexed hereto as Exhibit C.[1]
[1]
Editor's Note: Exhibits B and C are on file in the office of the Township Engineer.
[Added 12-10-1971 by Ord. No. 132]
Roads constructed in accordance with Exhibit A, entitled "Class 1 Road Detail"[1] and otherwise constructed in accordance with §§ 136-5 through 136-11, both inclusive, of this Article shall, subject to the provisions of all other applicable ordinances of the township, be eligible for acceptance into the road system of the township.
[1]
Editor's Note: Exhibit A is on file in the office of the Township Engineer.
[Added 12-10-1971 by Ord. No. 132; amended 6-25-1976 by Ord. No. 171]
Installation of roads designated as Class II and Class III roads in the Zoning and Subdivision Ordinances of the township[1] shall be constructed, respectively, in accordance with the design standards set forth in Exhibits D and E annexed hereto.[2] The Township Committee, within its sole discretion and authority, upon the advice and recommendation of the Township Planning Board and the Township Engineer, may provide for the acceptance of Class II roads into the road system of the township. Class III roads shall in no event be eligible for acceptance into the road system of the township.
[1]
Editor's Note: See Ch. 102, Land Use and Development.
[2]
Editor's Note: Exhibit D, as amended 12-30-1977 by Ord. No. 187, and Exhibit E are on file in the office of the Township Engineer.
A. 
All improvements, including electric, gas and water lines, shall be installed under the supervision and inspection of the Township Engineer, the cost thereof to be borne by the developer or road contractor. Inspection costs shall be computed based upon the following schedule by the Township Engineer, and such amount, in the form of cash, shall be deposited with the Clerk of the Township of Bethlehem before the commencement of any construction. No refund of inspection deposits shall be made.
Schedule of Inspection Costs
Estimated Improvement Cost, Exclusive of Electric and Gas and Inclusive of Water Lines
Inspection Fees
Less than $5,000
$350.00
$5,000 to $10,000
$350.00 plus 5% of excess over $5,000
$10,000 to $50,000
$600.00 plus 4% of excess over $10,000
Over $50,000
$2,200.00 plus 3% of excess over $50,000
B. 
No construction work shall commence without notice to the Township Engineer at least 72 hours before the commencement of work, and the Township Engineer shall be so notified as to permit full-time inspection of all phases of the work. Where required by the Township Engineer, samples of concrete or any other materials used in the course of construction may be taken and tested in an approved testing laboratory, with the cost of said lab analysis to be paid by the developer or road contractor, independent of the inspection deposit.
C. 
The developer shall provide, if required by the Township Engineer, and file with the Township Engineer one set of as-built improvement plans and profiles, showing actual construction as approved, prior to the release of any performance guaranties.
D. 
Upon completion of all works required by the performance bond and the certification by the Township Engineer of such completion in accordance with plans and specifications, the performance bond may be released, provided that the developer or road contractor shall have filed a cash maintenance performance guaranty sufficient in amount to guarantee that the completed works will be maintained for a period of 18 months, but in no event shall said cash maintenance performance guaranty be less than 5% of the performance bond. The Township Engineer shall determine the amount of the cash maintenance performance guaranty, which shall be approved by the Township Attorney as to form, sufficiency and execution and approved by the Township Committee, which said guaranty shall provide that the township shall have the right to use all or any part thereof for the maintenance of said road and appurtenant works and/or the reconstruction of the same if the same be necessary, as said Township Committee shall, in its sole discretion, upon recommendation of the Township Engineer, deem necessary and proper.
E. 
Upon the passage of 18 months from the date of approval of the Township Engineer of the completion of such works and the filing of the cash maintenance performance guaranty and upon certification of the Township Engineer that said works have been satisfactorily maintained and are in compliance with all specifications set forth in this Article, said road shall be accepted into the public road system of the Township of Bethlehem, and the balance of said cash maintenance performance guaranty, if any, shall be returned without interest to the developer or road contractor. The Township of Bethlehem shall not accept into its public road system any roadway less than 18 months after completion of the same as herein described, and the developer or road contractor does, by the posting of said cash maintenance performance guaranty, specifically authorize necessary maintenance and snow removal, all at the expense of the developer or road contractor for said eighteen-month period, and does further release the Township of Bethlehem from any liability as may be caused by other than willful damage to the works of said developer or road contractor on the roadway not then accepted into the public road system of the Township of Bethlehem.
F. 
A building permit shall not be issued until the complete installation of all underground works, including but not limited to sanitary sewers, water, gas, storm drains and the installation of road subbase, road base and curbs, all as specified in the plan. Upon certification by the Township Engineer that said installation is complete, building permits shall be authorized.