The purpose of the steep slope protection district
is to minimize the impacts of development activities on steep slopes
in the Town of Brighton by regulating activities in these areas and
by requiring review and permit approval prior to project commencement.
The developmental impacts include soil erosion and sedimentation,
destruction of vegetation, increased runoff rates and slope failure.
The regulations contained in this district are designed to minimize
the disturbance or removal of existing vegetation, prevent increased
erosion and runoff, maintain established drainage systems, locate
development where it is less likely to cause future slope failures
and to retain, as much as possible, the natural character of these
areas.
The boundaries of the steep slope protection
district shall be delineated on the Official Town of Brighton EPOD
Maps and shall include all areas of 15% or greater slopes, and all
areas within 50 feet of the toe or top of such slopes. The authorized
official or Town Engineer may consult other information, including
but not limited to the Soil Survey of Monroe County, topographic maps
produced by the United States Geological Survey, field surveys and
other appropriate sources, in order to more accurately locate and
delineate steep slope protection district boundaries within the Town.
No person shall conduct any of the following
regulated activities within any steep slope protection district in
the Town of Brighton unless such person has first applied for and
obtained an EPOD development permit pursuant to the requirements of
this section:
A. Construction of new buildings or structures or additions
and modifications to existing buildings and structures in areas of
slopes exceeding 15%.
B. Clearing of or constructing on any land area within
the district including construction or clearing activities related
to providing equipment access on the site, except for those activities
exempted from the permit requirements of this section as indicated
in the excavation regulations of the Town Code.
C. The construction or placement of any sewage disposal
system, including individual sewage disposal systems, septic tanks,
septic drainage or leach fields.
D. Filling, cutting or excavating operations.
E. Discharge of stormwater and/or construction and placement
of stormwater runoff systems.