Q = C I A
| |||
Where:
| |||
Q
|
=
|
design discharge in cubic feet per second
| |
C
|
=
|
runoff coefficient (see Table I below)
| |
I
|
=
|
intensity of rainfall, inches per hour (see
Tables II of III below)
| |
A
|
=
|
tributary watershed area in acres
|
Table I. Runoff Coefficients.
| ||
---|---|---|
Type of Area
|
Runoff Coefficients
| |
Rural, park, forested, agricultural
|
.10—.30
| |
Low residential (single-family dwellings)
|
.30—.50
| |
High residential (multiple family dwellings)
|
.60
| |
Business and commercial
|
.80
| |
Industrial
|
.80
| |
Impervious
|
.90
| |
Schools
|
.50
|
Table II.
| ||
---|---|---|
10-Year Design Rainfall
| ||
Intensity—Duration Data
| ||
Duration in Minutes
|
Intensity (in/hours)
| |
5.0
|
2.46
| |
6.0
|
2.31
| |
7.5
|
2.04
| |
10.0
|
1.73
| |
12.5
|
1.53
| |
15.0
|
1.46
| |
20.0
|
1.16
| |
25.0
|
1.02
| |
30.0
|
0.94
| |
45.0
|
0.69
| |
60.0
|
0.59
| |
90.0
|
0.45
| |
120.0
|
0.35
| |
180.0
|
0.27
| |
240.0
|
0.20
| |
300.0
|
0.14
| |
360.0
|
0.12
|
Table III.
| ||
---|---|---|
100-Year Design Rainfall
| ||
Intensity—Duration Data
| ||
Duration in Minutes
|
Intensity (in/hours)
| |
5.0
|
4.28
| |
6.0
|
4.03
| |
7.0
|
3.69
| |
8.0
|
3.41
| |
9.0
|
3.19
| |
10.0
|
3.00
| |
12.5
|
2.64
| |
15.0
|
2.55
| |
20.0
|
2.02
| |
25.0
|
1.77
| |
30.0
|
1.63
| |
45.0
|
1.26
| |
60.0
|
1.02
| |
90.0
|
0.94
| |
120.0
|
0.72
| |
180.0
|
0.52
| |
240.0
|
0.36
| |
300.0
|
0.18
| |
360.0
|
0.15
| |
420.0
|
0.14
| |
480.0
|
0.12
|
The time of concentration shall be based on
an initial lot to street time of ten minutes for lots smaller than
one-half acre, and fifteen minutes for lots equal to or greater than
one-half acre.
|
Where the size of the watershed is too large
for the application of the rational method in one step, the waterways
shall be subdivided into reaches of reasonable length, and the rational
formula applied to each reach step-by-step, properly accumulating
parameters and the time of concentration.
|
For all transport facilities the engineer shall
determine, using a design storm of one hundred years, the impact and/or
surcharging that would occur in all proposed storm drainage facilities.
|