Approvals issued and actions taken under this Part 1 do not
relieve the applicant of the responsibility to secure required permits
or approvals for activities regulated by any other code, law, regulation
or ordinance.
Volume controls will mitigate increased runoff impacts, protect stream channel morphology, maintain groundwater recharge, and contribute to water quality improvements. Stormwater runoff volume control methods are based on the net change in runoff volume for the two-year storm event. Volume controls shall be implemented using the Design Storm Method in Subsection A or the Simplified Method in Subsection B below. For regulated activities equal to or less than one acre, this Part
1 establishes no preference for either methodology; therefore, the applicant may select either methodology on the basis of economic considerations, the intrinsic limitations of the procedures associated with each methodology, and other factors. All regulated activities greater than one acre must use the Design Storm Method.
A. Design Storm Method (any regulated activity). This method requires detailed modeling based on site conditions. For modeling assumptions refer to §
172-14A.
(1) Post-development total runoff should not be increased from predevelopment
total runoff for all storms equal to or less than the two-year twenty-four-hour
duration precipitation.
(2) The following applies in order to estimate the increased volume of
runoff for the two-year twenty-four-hour duration precipitation event:
(a)
To calculate the runoff volume (cubic feet) for existing site
conditions (predevelopment) and for the proposed developed site conditions
(post-development), it is recommended to use the Soil Cover Complex
Method as shown below. Table B-3 in Ordinance Appendix B is available to guide a qualified professional and/or
an applicant to calculate the stormwater runoff volume. The calculated
volume shall be either reused, evapotranspired, or infiltrated through
structural or nonstructural means.
|
Soil Cover Complex Method:
|
|
Step 1: Runoff (inches) = Q = (P - 0.2S)2/(P + 0.8S) where
|
|
|
P = 2-year rainfall (inches)
|
|
|
S = (1,000/CN) - 10, the potential maximum retention (including
initial abstraction, Ia)
|
|
Step 2: Runoff Volume (cubic feet) = Q x Area x 1/12
|
|
|
Q = Runoff (inches)
|
|
|
Area = SWM Area (square feet)
|
B. Simplified Method (regulated activities less than or equal to one
acre):
(1) Stormwater facilities shall capture the runoff volume from at least
the first two inches of runoff from all new impervious surfaces.
|
Volume (cubic feet) = (2-inch runoff/12 inches) * impervious
surface (square feet)
|
(2) At least the first inch of runoff volume from the new impervious
surfaces shall be permanently removed from the runoff flow, i.e.,
it shall not be released into the surface waters of the commonwealth.
The calculated volume shall be either reused, evapotranspired or infiltrated
through structural or nonstructural means.
|
Volume (cubic feet) = (1-inch runoff/12 inches) * impervious
surface (square feet)
|
(3) Infiltration facilities should be designed to accommodate the first
half inch of the permanently removed runoff.
(4) No more than one inch of runoff volume from impervious surfaces shall
be released from the site. The release time must be over 24 hours
to 72 hours.
C. Stormwater control measures. The applicant must demonstrate how the
required volume is controlled through stormwater best management practices
(BMPs) which shall provide the means necessary to capture, reuse,
evaporate, transpire or infiltrate the total runoff volume.
(1) Stormwater management site area.
(a)
If natural resources exist on the site and a SWM site plan submission
is required for the regulated activity, the applicant shall determine
and display the total acreage of protected area where no disturbance
is proposed on the plan. The acreage of the protected area should
be subtracted from the total site area and not included in the stormwater
management site area acreage used in determining the volume controls.
|
Stormwater Management Site Area =
|
---|
|
{Total Site Area (for both pre- and post-development conditions)
- Protected Area}
|
(b)
Natural resource areas should be calculated based upon the municipality's
own natural resource protection ordinance. If no ordinance exists,
see Table B-2 in Ordinance Appendix B for guidance to assess the total protected area. For additional
reference, see Chapter 5, Section 5.4.1, of the PA BMP Manual.
(2) Calculate the volume controls provided through nonstructural BMPs.
Table B-5 in Ordinance Appendix B is recommended as guidance.
(3) Volume controls provided through nonstructural BMPs should be subtracted
from the required volume to determine the necessary structural BMPs.
|
Required
Volume Control (ft3)
|
-
|
Nonstructural
Volume Control (ft3)
|
=
|
Structural Volume
Requirement (ft3)
|
(4) Calculate the volume controls provided through structural BMPs. Table
B-6 in Ordinance Appendix B is recommended as guidance. See PA BMP Manual Chapter
6 for a description of the BMPs.
(5) Infiltration BMPs intended to receive runoff from developed areas
shall be selected based on the suitability of soils and site conditions.
(See Table B-6 in Ordinance Appendix B for a list of Infiltration BMPs.) Infiltration BMPs shall
be constructed on soils that have the following characteristics:
(a)
A minimum soil depth of 24 inches between the bottom of the
infiltration BMPs and the top of bedrock or seasonally high water
table.
(b)
An infiltration rate sufficient to accept the additional stormwater
load and dewater completely as determined by field tests. A minimum
of 0.2 inch per hour should be utilized and for acceptable rates a
safety factor of 50% should be applied for design purposes (e.g.,
for soil which measured 0.4 inch per hour, the BMP design should use
0.2 inch per hour to insure safe infiltration rates after construction).
(c)
All open-air infiltration facilities shall be designed to completely
infiltrate runoff volume within three days (72 hours) from the start
of the design storm.
(6) Soils. A soils evaluation of the project site shall be required to
determine the suitability of infiltration facilities. All regulated
activities are required to perform a detailed soils evaluation by
a qualified design professional which at minimum addresses soil permeability,
depth to bedrock, and subgrade stability. The general process for
designing the infiltration BMP shall be:
(a)
Analyze hydrologic soil groups as well as natural and man-made
features within the site to determine general areas of suitability
for infiltration practices. In areas where development on fill material
is under consideration, conduct geotechnical investigations of subgrade
stability; infiltration may not be ruled out without conducting these
tests.
(b)
Provide field tests such as double-ring infiltrometer or hydraulic
conductivity tests (at the level of the proposed infiltration surface)
to determine the appropriate hydraulic conductivity rate. Percolation
tests are not recommended for design purposes.
(c)
Design the infiltration structure based on field-determined
capacity at the level of the proposed infiltration surface and based
on the safety factor of 50%.
(d)
If on-lot infiltration structures are proposed, it must be demonstrated
to the municipality that the soils are conducive to infiltrate on
the lots identified.
(e)
An impermeable liner will be required in detention basins where
the possibility of groundwater contamination exists. A detailed hydrogeologic
investigation may be required by the municipality.
Peak rate controls for large storms, up to the one-hundred-year
event, are essential in order to protect against immediate downstream
erosion and flooding. The following peak rate controls have been determined
through hydrologic modeling of the Neshaminy Creek Watershed.
A. Standards for managing runoff from each subarea in the Neshaminy
Creek Watershed for the two-, five-, ten-, twenty-five-, fifty-, and
one-hundred-year design storms are shown in Table 172-13. Development
sites located in each of the management districts must control proposed
development conditions runoff rates to existing conditions' runoff
rates for the design storms in accordance with Table 172-13 below.
|
Table 172-13
Peak Rate Runoff Control Standards by Stormwater Management
Districts
in the Neshaminy Creek Watershed
(includes Little Neshaminy Creek)
|
---|
|
District
|
Design Storm Post-Development
(Proposed Conditions)
|
Design Storm Predevelopment
(Existing Conditions)
|
---|
|
A
|
2-year
5-year
10-year
25-year
50-year
100-year
|
1-year
5-year
10-year
25-year
50-year
100-year
|
|
B
|
2-year
5-year
10-year
25-year
50-year
100-year
|
1-year
2-year
5-year
10-year
25-year
50-year
|
|
C
|
2-year
5-year
10-year
25-year
50-year
100-year
|
2-year
5-year
10-year
25-year
50-year
100-year
|
B. General. Proposed conditions' rates of runoff from any regulated
activity shall not exceed the peak release rates of runoff from existing
conditions for the design storms specified on the Stormwater Management
District Watershed Map (Ordinance Appendix D) and in this section of this Part
1.
C. District boundaries. The boundaries of the Stormwater Management
Districts are shown on Official Maps and are available for inspection
at the municipal office and county planning offices. A copy of the
map at a reduced scale, and four other maps with zoomed-in extents,
are included in Ordinance Appendix D. The exact location of the Stormwater Management District
boundaries as they apply to a given development site shall be determined
by mapping the boundaries using the two-foot topographic contours
(or most accurate data required) provided as part of the SWM site
plan.
D. Sites located in more than one district. For a proposed development
site located within two or more stormwater management district category
subareas, the peak discharge rate from any subarea shall meet the
management district criteria for the district in which the discharge
is located.
E. Off-site areas. When calculating the allowable peak runoff rates,
developers do not have to account for runoff draining into the subject
development site from an off-site area. On-site drainage facilities
shall be designed to safely convey off-site flows through the development
site.
F. Site areas. The stormwater management site area is the only area
subject to the management district criteria. Nonimpacted areas or
nonregulated activities bypassing the stormwater management facilities
would not be subject to the management district criteria.
G. Alternate criteria for redevelopment sites. For redevelopment sites,
one of the following minimum design parameters shall be accomplished,
whichever is most appropriate for the given site conditions as determined
by Lower Moreland Township:
(1) Meet the full requirements specified by Table 172-13 and §
172-13A through
F; or
(2) Reduce the total impervious surface on the site by at least 20% based
upon a comparison of existing impervious surface to proposed impervious
surface.
H. Areas covered by a release rate map from an alternative approved
Act 167 Stormwater Management Plan.
I. For the one-, two-, five-, ten-, twenty-five-, fifty-, and one-hundred-year
storms, the post-development peak discharge rates will follow the
applicable approved release rate maps. For any areas not shown on
the release rate maps, the post-development discharge rates shall
not exceed the predevelopment discharge rates.