Prior to any excavation, the pavement shall be cut vertically
and in a straight line, preferably with a pavement saw, equal to the
width of the trench. The trench shall be as narrow as possible to
provide adequate working space, but shall not exceed the outside diameter
of the barrel of the pipe plus 16 inches. Side walls of the trench
shall be as nearly vertical as possible.
In order to receive a certificate of completion, the following
work items must be inspected during construction.
A. Work zone traffic control.
F. Utility backfill (compaction tests required).