All trees shall be cleared at a minimum distance
of eight feet on each side of the proposed roadway (total of 36 feet
for a twenty-foot road) and all brush throughout the required right-of-way.
On curves, an additional amount shall be cleared wherever necessary
to maintain a minimum visibility of 150 feet at the paving edge along
the inside of the curve. The Town Superintendent of Highways may waive
the clearing of certain trees within the right-of-way.
Shoulders shall be of compacted gravel or crushed
stone, not less than four feet in width or as may be required by the
Town Superintendent of Highways. Shoulders shall be a slope of 5/8
inch per one foot.
All slopes shall be finish graded from the edge
of the shoulder to the toe or top of the slope with a minimum of four
inches of topsoil and shall be sown with hearty grass seed in sufficient
quantity to produce turf that will stabilize the slope, unless otherwise
directed by the Town Superintendent of Highways.
Sufficiently reinforced concrete or granite
markers, at least four inches square on top and 4 1/2 feet long, must
be set located at all changes in direction of rights-of-way, including
points of tangent of curves and points of tangent at corners and at
the intersection of lot lines with rights-of-way. Monuments shall
also be placed every 100 feet on tangents and every 50 feet on curves.
All underground utilities which are to be in
the right-of-way, including water, sewer, drain, gas, electricity,
telephone and cable television, including junction boxes, risers,
manhole, catch basins and all pull boxes, shall be completely installed
prior to construction of the subbase. When underground utilities must
cross the road, they shall be run through conduit for electric and
plastic for all other utilities so removal and repairs may be made
without disturbing the road. All excavations shall be suitably filled
and tampered with vibratory tampers. All utility lines shall be buried
a minimum of 30 inches to the top of the pipes and cables and 18 inches
to the top of boxes, except for culverts designed to carry stormwater.
Manhole and catch basin frames shall be a minimum of six inches deep
and shall be designed to carry H-20 loading.
Approved road name signs shall be installed
when the road has been completed. Mailboxes shall be in a cluster
set back eight feet from the traveled way of the road in a thirty-foot
pull-off. The mailbox pull off shall be topped with the same material
used on the traveled way of the road, and the ditch line shall be
set back four feet from the edge of the pull-off or the water may
be piped under the pull-off with approved culverts. Any additional
right-of-way necessary for the construction of mailbox clusters shall
be provided by the developer and shown on the subdivision plans. (See
Diagram No. 5, Mailbox Cluster.)