The Township of Rostraver may require the submittal
of a letter of credit or cash bond prior to issuance of a permit in
order to insure that the stormwater practices are installed by the
permit holder as required by the approved stormwater management plan.
The amount of the installation performance security shall be the total
estimated construction cost of the stormwater management practices
approved under the permit, plus 10%. The performance security shall
contain forfeiture provisions for failure to complete work specified
in the stormwater management plan. The installation performance security
shall be released in full only upon submission of as-built plans and
written certification by a registered professional engineer that the
stormwater practice has been installed in accordance with the approved
plan and other applicable provisions of this chapter. The Township
of Rostraver will make a final inspection of the stormwater practice
to ensure that it is in compliance with the approved plan and the
provisions of this chapter. Provisions for a partial pro rata release
of the performance security based on the completion of various development
stages can be done by the Township of Rostraver.
[Added 12-2-2020 by Ord. No. 733]
A. The
developer shall be responsible for providing record drawings of all
stormwater management facilities and BMPs as built and included in
the approved stormwater management plan. The record drawings and an
explanation of any discrepancies with the construction plans shall
be submitted to the Municipality and/or WCD.
B. The
record drawing submission shall include a certification of completion
signed by a qualified professional verifying that all permanent stormwater
management facilities and BMPs have been constructed according to
the approved plans and specifications. The latitude and longitude
coordinates for all permanent stormwater management facilities and
BMPs must also be submitted, at the central location of the BMPs.
If any licensed qualified professionals contributed to the construction
plans, then a licensed qualified professional must sign the completion
certificate.
C. After
receipt of the completion certification by the municipality, the municipality
and/or WCD may conduct a final inspection.