A. 
All construction within the right-of-way or lands to be dedicated to the town shall be complete with final site reviews and written approvals of the construction by the following:
(1) 
Superintendent of Water Utilities.
(2) 
Building Department.
(3) 
Superintendent of Highways.
(4) 
Town Engineer.
B. 
In addition to the field review, the Town Attorney shall notify the town, in writing, that all legal aspects of the project have been satisfied.
Monuments shall have been set in their required locations and certified to the town.
Final grading shall be completed within the right-of-way and all spoil removed from the site.
All street and traffic signs shall be properly set in their designated locations.
A. 
Record drawings and all testing results shall be supplied to the town and are subject to its review and approval at least 15 calendar days prior to any dedication procedures.
B. 
Record maps shall be prepared by a licensed professional, and eight prints and a reproducible (Mylar) print shall be submitted to the Town Building Department. The record drawings shall contain, at a minimum, the following information:
(1) 
The locations, sizes, elevations, lengths, slopes and invert and top elevations of all structures in the sewer system.
(2) 
The elevations of any drainage swales and drainage structures to be dedicated to the town.
(3) 
The locations, including ties to all valves, curb boxes and hydrants to permanent structures.
(4) 
The locations at the property or easement line of each individual lot:
(a) 
Sanitary lateral cleanouts.
(b) 
Storm laterals.
(c) 
Water service curb box.
(5) 
Any other significant details affecting the operation or maintenance of any system by the town.
(6) 
The location of all facilities shall be tied to visible and reproducible objects.
The submission and acceptance of the two-year maintenance bonds for all improvements to be offered to the town for dedication is required. Maintenance bonds shall be written by a surety licensed to do business in New York State and they shall be in the amount of 10% of the final construction cost. Bonds shall be approved as to form and content by the Town Attorney prior to any dedication procedure.
The Town Board, upon signature recommendation of the design engineer, owner, Town Engineer, receipt of the Town Attorney's written opinion of legal status, receipt of the two-year maintenance bond, record drawings accepted by the town departments and a final field review report, shall then authorize release of moneys retained in the letter of credit.