The Plan Commission shall review the referred plans within 60 days following their submittal. The Plan Commission will approve said plans only after determining that the proposed development or redevelopment will not impair an adequate supply of light and air to adjacent property or substantially increase the danger of fire or traffic congestion or otherwise endanger the public health or safety and meets the purpose and intent set forth in §
435-66.
The Plan Commission may impose time schedules
for the completion of buildings, parking and loading areas, open space
utilization, utilities, and landscaping. The Plan Commission may require
appropriate financial sureties to guarantee that such improvements
will be completed on schedule.
Any person aggrieved by any decision of the
Plan Commission related to plan review may appeal the decision to
the Zoning Board of Appeals. Such appeal shall be filed with the Village
Clerk within 30 days after filing of the decision with the Building
Inspector.
All plan approvals by the Plan Commission shall
expire if the proposed project has not started construction within
12 months of the date of approval and finished construction within
18 months of the construction date, unless the date is extended by
mutual consent.