[Amended 6-11-1998]
The subdivider shall, within six months after the approval of
the preliminary plat, file with the Planning Board an application
of the subdivision plat in final form, using the approved application
blank available from the Clerk of the Planning Board. All applications
for plat approval for major subdivisions shall be accompanied by a
fee of $50. If the final plat is not submitted within six months after
the approval of the preliminary plat, the Planning Board may refuse
to approve the final plat and require resubmission of the preliminary
plat, or such time requirement may be waived by the Planning Board.
[Amended 8-23-1988]
A subdivider intending to submit a proposed subdivision plat
for the approval of the Planning Board shall provide the Clerk of
the Board with a copy of the application and three Mylar prints and
three paper prints of the plat, the original and one true copy of
all offers of cession, covenants and agreements and two prints of
all construction drawings.
The time of submission of the subdivision plat shall be considered to be the date on which the application for approval of the subdivision plat, complete and accompanied by the required fee and all data required by §
174-74 of these regulations, has been filed with the Clerk of the Planning Board.
Water and sewer facility proposals contained in the subdivision
plat shall be properly endorsed and approved by the New York State
Department of Environmental Conservation and/or New York State Department
of Health. Applications for approval of plans for sewer or water facilities
will be filed by the subdivider with all necessary Town, county and
state agencies.
Within 45 days of the submission of a plat in final form for approval, a hearing shall be held by the Planning Board. This hearing shall be advertised at least once in a newspaper of general circulation in the Town at least five days before such hearing; provided, however, that when the Planning Board deems the final plat to be in substantial agreement with a preliminary plat approved under Article
IV and modified in accordance with requirements of such approval, if such preliminary plat has been approved with modification, the Planning Board may waive the requirement for such public hearing.