[Amended 12-13-2011 by L.L. No. 9-2011]
A. In the event of any actual or threatened noncompliance with the terms of this Part
2 or any actual or threatened endangerment of the health or welfare of persons, wildlife species, vegetation or the environment, the Board may act according to the terms of this article. The various enforcement techniques and sanctions set forth in this article are not mutually exclusive, and the Board may pursue all, one or any combination of the powers in this article.
B. An industrial
user is in significant noncompliance if its violation meets one or
more of the following criteria:
(1) Chronic
violations of wastewater discharge limits, defined here as those in
which 66% or more of all of the measurements taken during a six-month
period exceed (by any magnitude) as a numeric pretreatment standard
or requirement, including instantaneous limits as defined by 40 CFR
403.3(i);
[Amended 8-23-2016 by L.L. No. 2-2016]
(2) Technical
review criteria (TRC) violations, defined here as those in which 33%
or more of all the measurements taken for the same pretreatment parameter
during a six-month period equal or exceed the product of the numeric
pretreatment standard or requirement, including instantaneous limits
as defined by 40 CFR 403.3(i) multiplied by applicable TRC (TRC equals
1.4 for BOD, TSS, fats, oil and grease and 1.2 for all other pollutants
except pH);
[Amended 8-23-2016 by L.L. No. 2-2016]
(3) Any
other violation of a pretreatment standard or requirement as defined
by 40 CFR 403.3(i) (daily maximum, long-term average, instantaneous
limit, or narrative standard) that the POTW determines has caused,
alone or in combination with other discharges, interference or pass-through
(including endangering the health of the POTW personnel or the general
public);
[Amended 8-23-2016 by L.L. No. 2-2016]
(4) Any discharge of a pollutant that has caused imminent endangerment to human health, welfare or to the environment or has resulted in the POTW's exercise of its emergency authority under §
177-82, to halt or prevent such a discharge;
(5) Failure
to meet, within 90 days after the schedule date, a compliance schedule
milestone contained in a local control mechanism or enforcement order
for starting construction, completing construction, or attaining final
compliance;
[Amended 8-23-2016 by L.L. No. 2-2016]
(6) Failure
to provide, within 30 days after the due date, required reports such
as baseline monitoring reports, ninety-day compliance reports, periodic
self-monitoring reports, and reports on compliance with compliance
schedule;
(7) Failure
to accurately report noncompliance;
(8) Any
other violation or group of violations, which may include a violation
of best management practices, that the Superintendent determines will
adversely affect the operation or implementation of the local pretreatment
program.
[Amended 8-23-2016 by L.L. No. 2-2016]
The Board shall have the power to bring an action to enjoin the industrial user from continuing a violation(s) of this Part
2. The Board may pursue preliminary injunctive relief, such as a temporary restraining order and preliminary injunction, prior to the seeking of a permanent injunction against the violator(s).