A. 
For all regulated activities, unless preparation of an SWM site plan is specifically exempted in § 149-15:
(1) 
Preparation and implementation of an approved SWM site plan is required.
(2) 
No regulated activities shall commence until the municipality issues written approval of an SWM site plan which demonstrates compliance with the requirements of this chapter.
B. 
All SWM site plans for regulated activities shall include such measures as necessary to:
(1) 
Protect health, safety, and property.
(2) 
Meet the water quality goals of this chapter, as stated in § 149-3, by including measures that:
(a) 
Minimize disturbance to floodplains, wetlands, wooded areas, and existing vegetation.
(b) 
Maintain or extend riparian buffers.
(c) 
Avoid erosive flow conditions in natural flow pathways.
(d) 
Minimize thermal impacts to waters of the commonwealth.
(e) 
Disconnect impervious surfaces by directing runoff to pervious areas.
(f) 
Minimize soil disturbance and compaction.
(3) 
Incorporate the techniques for low-impact development practices described in the Pennsylvania Stormwater Best Management Practices Manual (BMP Manual).
C. 
Stormwater flows onto adjacent property shall not be created, increased, decreased, relocated, or otherwise altered without the written notification of the adjacent property owner(s) by the developer. Copies of all such notifications shall be included in the SWM site plan submission.
D. 
For all regulated activities where erosion and sediment control is required in accordance with Title 25 of the Pennsylvania Code and the Clean Streams Law, 35 P.S. § 691.1 et seq., the SWM site plan shall include the required erosion and sedimentation control measures. Necessary E&S BMPs shall be designed in accordance with the Erosion and Sediment Pollution Control Program Manual (E&S Manual) 2, No. 363-2134-008 (April 15, 2000), as amended and updated. Approval of the SWM site plan by the Township shall be conditioned on the applicant obtaining erosion and sedimentation control approval from the appropriate agency(ies), when applicable.
E. 
For all regulated activities where NPDES permitting is required in accordance with the Clean Water Act (33 U.S.C. § 1251 et seq. [1972], as amended), the SWM site plan shall include the information required in the applicant's NPDES permit application. Approval of the SWM site plan by the Township shall be conditioned on the applicant obtaining NPDES permit approval from the appropriate agency(ies), when applicable.
F. 
For all regulated activities, implementation of the volume controls in § 149-17 is required.
G. 
Special management areas. SWM site plans involving regulated activities within special management areas shall be prepared in a manner consistent with the guidance provided in Chapter 7 of the BMP Manual. The SWM site plan submission shall include design details for SWM BMPs within said special management area.
H. 
An SWM site plan may propose that stormwater related to the proposed regulated activities be accommodated by existing stormwater management facilities on adjoining or nearby properties provided that the SWM site plan documents the following.
(1) 
The use of the stormwater management facilities located on said adjoining or nearby property is approved, in writing, by the owner of the property.
(2) 
The stormwater management facilities located on said adjoining or nearby property are designed in a manner that can accommodate the stormwater management needs of the regulated activity in a manner consistent with all requirements of this chapter. The SWM site plan shall include all documentation necessary for the Township to confirm such compliance.
I. 
The design storm volumes to be used in the analysis of peak rates of discharge shall be obtained from the Precipitation-Frequency Atlas of the United States, Atlas 14, Volume 2, Version 3.0, as amended and updated, United States Department of Commerce, National Oceanic and Atmospheric Administration (NOAA), National Weather Service, Hydrometeorological Design Studies Center, Silver Spring, Maryland. NOAA's Atlas 14 can be accessed at: http://hdsc.nws.noaa.gov/hdsc/pfds/.
J. 
SWM site plans, once approved by the Township, shall remain on site throughout the duration of the regulated activity and be available for review as may be necessary by representatives of the Township.
K. 
The design of all facilities over karst shall include an evaluation of measures to minimize adverse effects.
L. 
The Township may, after consultation with DEP, approve measures for meeting the state water quality requirements other than those in this chapter, provided that they meet the minimum requirements of, and do not conflict with, state law, including, but not limited to, the Clean Streams Law, 35 P.S. § 691.1 et seq. The municipality shall maintain a record of consultations with DEP pursuant to this subsection.
A. 
A property owner or developer of any regulated activity that meets the following exemption criteria is, upon approval from the Township, exempt from the formal SWM plan submission requirements of this chapter as specified herein. However, the property owner or developer shall be subject to all other requirements of this chapter other than the formal SWM plan submission requirements for which an exemption or exemptions have been authorized. The criteria for exemption in this section apply to the total development proposed, including instances in which the development is proposed to take place in phases. The date of enactment of this chapter shall be the starting point from which future development and the respective exemption criteria shall be cumulatively considered and regulated.
(1) 
Regulated activities that involve (1) equal to or less then 500 square feet of impervious surface for lots having an area of 20,000 square feet or less; or (2) equal to or less than 1,000 square feet of impervious surface for lots having an area of greater than 20,000 square feet may be exempted from the peak rate control, volume control and the SWM site plan preparation and submission requirements of this chapter. The applicant shall complete the Municipal Stormwater Management Worksheet from the Stormwater Management Design Assistance Manual and file said Worksheet with the Township.
(2) 
Regulated activities that involve greater than 1,000 square feet and equal to or less than 10,000 square feet of impervious area, and where the all the proposed impervious area can be entirely disconnected, may be exempted from the peak rate control, volume control, and the SWM site plan preparation and submission requirements of this chapter. The applicant shall complete the Stormwater Management Worksheets from the Stormwater Management Design Assistance Manual and file said Worksheets with the Township.
(3) 
Regulated activities that involve greater than 1,000 square feet and equal to or less than 5,000 square feet of impervious area may be exempted from the peak rate control and volume control preparation and submission requirements of this chapter. A minor stormwater site plan, as detailed in the Stormwater Management Design Assistance Manual, shall be submitted to the Township instead of the submission of a full SWM site plan in accordance with Article IV of this chapter.
(4) 
Agricultural activities shall be exempt from the rate control, volume control and SWM site plan preparation and submission requirements of this chapter, provided the agricultural activities are performed in accordance with the requirements of 25 Pa. Code Chapter 102. Further, such activities shall not be subject to the exemption approval process of § 149-15B of this chapter.
(5) 
Forest management and timber operations are exempted from the rate control, volume control and SWM site plan preparation and submission requirements of this chapter provided the forest management and timber operations are performed in accordance with the requirements of 25 Pa. Code Chapter 102.
(6) 
Regulated activities involving domestic gardening for single-family consumption shall be exempted from volume control, rate control, and SWM site plan preparation and submission requirements of this chapter, and shall not be subject to the exemption approval process of § 149-15B of this chapter.
(7) 
In-kind repair, in-kind replacement, and maintenance of existing surfaces, and structures shall be exempted from volume control, rate control, and SWM site plan preparation and submission requirements of this chapter, and shall not be subject to the exemption approval process of § 149-15B of this chapter.
(8) 
New subdivisions or land developments, as referenced to in § 149-5B of this chapter, are not exempt from volume control, rate control, and SWM plan preparation and submission requirements of this chapter, and shall not be exempt under the approval process of § 149-15B of this chapter.
B. 
Authorization of exemptions. The Township shall determine, in accordance with the following requirements and process, whether a proposed regulated activity may be exempted from any of the requirements of this chapter.
(1) 
The property owner or developer proposing the regulated activity shall submit, in writing on a form supplied by the Township, a request for said proposed regulated activity to be exempted from allowable requirements of this chapter pursuant to Subsection A. The written request shall identify the project and shall indicate the specific exemption criteria, as listed in § 149-15A, that apply to the project, and shall be submitted in accordance with the Stormwater Management Worksheets from the Stormwater Management Design Assistance Manual.
(2) 
Within 45 days of the receipt of the exemption request form, the Township or its designee shall either approve or deny the exemption request. If the exemption request is denied, the Township or its designee shall direct the property owner or developer to submit the information required to demonstrate that the proposed regulated activity complies with the requirements of this chapter or meets the exemption criteria.
(3) 
Exemption request approval shall be at the discretion of the Township, and shall be subject to the following:
(a) 
The Township may deny any exemption request or suspend or revoke any approved exemption request at any time for any project where the Township believes that the proposed regulated activity poses a threat to public health, safety, property, or the environment.
(b) 
Approval of an exemption request does not relieve the property owner or developer from other applicable requirements of this chapter or of other Township ordinance or regulations.
(c) 
The Township reserves the right to deny an exemption request if a drainage problem is known or identified by the Township to exist or is expected to exist downstream from the proposed regulated activity.
A. 
Impervious area.
(1) 
The measurement of impervious areas shall include all of the impervious areas in the total proposed development, even if development is to take place in phases.
(2) 
For development taking place in phases, the total proposed impervious area within the SWM site plan must be used in determining conformance with this chapter.
(3) 
For projects that add impervious area to a parcel, the total impervious area on the parcel is subject to the requirements of this chapter; except that the volume controls in § 149-17 and the peak rate controls of § 149-18 do not need to be retrofitted to existing impervious areas that are not being altered by the proposed regulated activity.
(4) 
For new residential subdivisions, 5,000 square feet of impervious area shall be used for each residential lot when preparing the stormwater management plan for the subdivision, unless the Township requires or allows that a different amount of impervious area be used. If the impervious area, during development, should exceed 5,000 square feet, the property owner will be required to submit a stormwater management plan showing how the additional impervious area will be controlled.
B. 
Normally dry, open-top storage facilities, designed as such, shall completely drain both the volume control and rate control capacities over a period of time not less than 24 hours and not more than 72 hours from the end of the design storm. However, any designed infiltration volume at such facilities is exempt from the minimum twenty-four-hour standard, i.e., may infiltrate in a shorter period of time, so long as none of the stormwater intended for infiltration is discharged into the surface waters of the commonwealth.
C. 
Infiltration BMPs shall be spread out, made as shallow as practicable, and located to maximize use of natural on-site infiltration features while still meeting the other requirements of this chapter.
D. 
The stormwater management plan shall also meet the design criteria of Chapter 160, Subdivision and Land Development.
The low impact development practices provided in the BMP Manual shall be utilized for all regulated activities. Water volume controls shall be implemented using the Design Storm Method in § 149-17A or the Simplified Method in § 149-17B. For regulated activity involving less than one acre of impervious coverage that does not require hydrologic routing to design the stormwater facilities, the applicant may select either methodology on the basis of economic considerations, the intrinsic limitations on applicability of the analytical procedures associated with each methodology, and/or other factors. The Design Storm Method in § 149-17A shall be used for all regulated activity involving greater than one acre of impervious coverage.
A. 
The Design Storm Method (CG-1 in the BMP Manual) may be used for any size of regulated activity. This method requires detailed modeling to achieve the following standards.
(1) 
The post-development total runoff volume shall not increase for all storms equal to or less than the two-year twenty-four-hour duration precipitation.
(2) 
For modeling purposes:
(a) 
Existing (pre-development), nonforested, pervious areas must be considered meadow.
(b) 
20% of existing impervious area, when present, shall be considered meadow in the model for existing conditions.
B. 
The Simplified Method (CG-2 in the BMP Manual) is independent of site conditions and may be used for projects involving regulated activities proposing equal to or less than one acre of impervious coverage and that do not require design of stormwater storage facilities. When the Simplified Method is used to address stormwater management needs of new impervious surfaces, the following design standards shall be achieved:
(1) 
Stormwater facilities shall capture at least the first two inches of runoff from all new impervious surfaces.
(2) 
At least the first one inch of runoff from new impervious surfaces shall be permanently removed from the runoff flow and shall not be released into the surface waters of the commonwealth. Removal options for the first one inch of runoff include, but are not necessarily limited to, reuse and infiltration.
(3) 
Infiltration facilities shall be designed to accommodate infiltration of as much of the permanently removed runoff as site conditions will allow. If the soils within the project area do not allow for infiltration of the entire first one inch of runoff from new impervious surfaces, other forms of runoff volume control shall be used to achieve the required removal volume. Such measures may include, but are not limited to, vegetated roofs, biorention, and capture-and-reuse systems. In addition, the infiltration alternative authorized in § 149-17C may be employed.
(4) 
This method is exempt from the requirements of § 149-18, Rate controls.
C. 
Infiltration alternative. Where infiltration is not possible due to soil characteristics or is not desirable given other characteristics, water quality control may be proposed as an alternative to strict adherence to the volume control standards of § 149-17 of this chapter. Where water quality control is proposed, the following standards shall be achieved:
(1) 
At a minimum, the following documentation shall be provided to justify the proposal to reduce the infiltration requirements:
(a) 
Description of and justification for field infiltration/permeability testing with respect to the type of test and test locations.
(b) 
An interpretive narrative describing existing soils of the site and their structure as these relate to the interaction between soils and water characteristics of the site. In addition to providing soil and soil profile descriptions, this narrative shall identify depth to seasonal water tables and depth to bedrock and provide a description of all subsurface elements (restrictive layers, geology, etc.) that influence the direction and rate of subsurface water movement.
(c) 
A qualitative assessment of the site's contribution to annual aquifer recharge shall be made, along with the identification of any restrictions or limitations associated with the use of designed infiltration facilities.
(d) 
The provided documentation must be signed and sealed by a professional engineer or geologist.
(2) 
Water quality BMPs shall be implemented on all permanent stormwater discharges from the proposed project site to achieve pollutant removal efficiencies in accordance with the Table 147-17.
Table 147-17. Required Pollutant Removal Efficiencies for Infiltration Alternatives
Pollutant Load
Units
Required Removal Efficiency
(%)
Total suspended solids (TSS)
Pounds
85%
Total phosphorus (TP)
Pounds
85%
Total nitrate (NO3)
Pounds
50%
(3) 
Design guidance from the most current version of the Pennsylvania Stormwater Best Management Practices Manual, or equivalent resource as precoordinated with the Township shall be consulted when choosing design criteria for water quality BMPs.
A. 
Post-development discharge rates shall not exceed the pre-development discharge rates for the one-, two-, five-, ten-, twenty-five-, fifty-, and one-hundred-year twenty-four-hour storms. If it is shown that the peak rates of discharge indicated by the post-development analysis are less than or equal to the peak rates of discharge indicated by the pre-development analysis for one-, two-, five-, ten-, twenty-five-, fifty-, and one-hundred-year, twenty-four-hour storms, then the requirements of this section have been met. Otherwise, the applicant shall provide additional controls as necessary to satisfy the peak rate of discharge requirement.
B. 
For computation of pre-development peak discharge rates, 20% of existing impervious areas, when present, shall be considered meadow.
Where an applicant proposes to utilize riparian buffers as the means to meet the requirements of this chapter, said riparian buffers shall be established and/or maintained in accordance with the BMP Manual or the publication Riparian Forest Buffer Guidance, published November 2010 by the Pennsylvania Department of Environmental Protection, and as may be amended or updated.
A. 
Any drain or conveyance, whether on the surface or subsurface, that allows any non-stormwater discharge, including sewage, process wastewater, and wash water, to enter the waters of the commonwealth is prohibited.
B. 
No person shall allow, or cause to allow, discharges into surface waters of the commonwealth which are not composed entirely of stormwater, except (1) as provided in Subsection C below and (2) discharges allowed under a state or federal permit.
C. 
The following discharges are authorized unless they are determined to be significant contributors to pollution to the waters of the commonwealth:
(1) 
Discharges from firefighting activities.
(2) 
Potable water sources, including water line flushing.
(3) 
Irrigation drainage.
(4) 
Air-conditioning condensate.
(5) 
Springs.
(6) 
Water from crawl space pumps.
(7) 
Pavement wash waters where spills or leaks of toxic or hazardous materials have not occurred (unless all spill material has been removed) and where detergents are not used.
(8) 
Diverted stream flows.
(9) 
Flows from riparian habitats and wetlands.
(10) 
Uncontaminated water from foundations or from footing drains.
(11) 
Lawn watering.
(12) 
Dechlorinated swimming pool discharges.
(13) 
Uncontaminated groundwater.
(14) 
Water from individual residential car washing.
(15) 
Routine external building wash-down (which does not use detergents or other compounds).
(16) 
Water discharged in well testing for potable water supplies.
D. 
In the event that the municipality or DEP determines that any of the discharges identified in Subsection C significantly contribute to pollution of the waters of the commonwealth, the municipality or DEP will notify the responsible person(s) to cease the discharge.
Roof drains, sump pumps, and footer drains should discharge to infiltration or vegetative BMPs and, to the maximum extent practicable, satisfy the criteria for DIAs. Discharges of each should be conveyed in such a manner as to not cause water problems for adjoining property owners. Roof drains, sump pumps and footer drains shall not discharge to roadways, curblines, or storm sewer systems without written approval of the Township.
No person shall modify, remove, fill, landscape, or alter any SWM BMPs, facilities, areas, or structures in a manner, without the written approval of the Township, with the exception of necessary maintenance activities such as mowing.