§ 2. Each city, town or public agency shall designate 1 board or officer to issue permits for the excavation of trenches on privately owned land and for the excavation of a public way of a city or town.
|
§ 5-107. Fees and charges by municipal agencies.
| ||
A.
|
Any municipal agency which is otherwise authorized to
issue a license, certificate or permit, or to render a service or
to perform work for a person or class of persons, may from time to
time fix a reasonable fee for the license, certificate, permit or
for rendering the service or for performing the work in the manner
provided in MGL C. 40, § 22F.
|
Permits issued under this regulation shall expire thirty (30)
calendar days from the date of issue. Prior to the expiration date,
they may be renewed for an additional thirty (30) calendar days without
additional permit fee. Thereafter, each subsequent thirty-day renewal
shall require the payment of an additional permit fee.
| |
If the construction period is anticipated to be of extended
duration, the permit may be issued for the entire construction period.
The permit fee for the entire period shall be calculated as follows:
$25.00 for the initial 60 calendar days and $25.00 for each additional
30 calendar day period or portion thereof. Applicants must notify
the permitting authority within three (3) calendar days when all work
under the permit has been completed.
|