Type of Work
|
Base Fee
|
Additional Fee
| ||
---|---|---|---|---|
1.
|
Underground (first 1,000 linear feet)
|
$1 per linear foot
| ||
A.
|
Trenching, jacking or direct boring
|
$1 per linear foot
| ||
B.
|
Bell holes
|
$100 each
| ||
C.
|
Residential subdivisions (see A and B above)
|
$1 per linear foot
| ||
Underground (for any amount over 1,000 feet)
| ||||
D.
|
If the installation of underground facilities exceeds 1,000
linear feet, in total or in part, an inspection fee, in addition to
the base fee, will be required. This additional fee will be calculated
at $5 per linear foot of trench required to install facilities, and
is payable to the County prior to the issuance of the permit.
|
$5 per linear foot of trench required to install facilities
| ||
E.
|
After original service installation
|
$1 per linear foot
| ||
Note: No charge for servicing single residential homes.
| ||||
2.
|
Overhead Facilities
| |||
A.
|
Install poles, towers, etc.
|
$100 per unit
| ||
B.
|
Overhead wires
|
$1 per linear foot
| ||
C.
|
Attachments (i.e., transformers, switches, etc.)
|
$100
| ||
Note: No charge for servicing single residential homes.
| ||||
Note: For #1 and #2, fees will be waived for County-requested
relocations.
| ||||
3.
|
Utility Installations on Bridges or Culverts
| |||
A.
|
Nonrequired structural change
|
$1 per linear foot
| ||
B.
|
Installation requiring structural change
|
$1,000
|
Review fee of not less than $1,000 per day or any portion thereof
for DPW staff review
| |
4.
|
Maintenance
| |||
A.
|
Repairs
|
$100 per job
| ||
B.
|
Annual tree work or trimming for overhead lines
|
$5,000 per year
| ||
5.
|
Telecommunications Transmission (nondistribution or local)
| |||
A.
|
Underground conduit (ducts), cables, inner duct, wires and manholes
|
$5 per linear foot of trench
|
$1 per linear foot of trench annually thereafter
| |
6.
|
Public Telephones
| |||
A.
|
Public telephones are not permitted within the County right-of-way.
|
NA
|
Number of Vehicles in Highest Two-Way Peak Hour
|
Fee
| |
---|---|---|
0 to 49 vehicles generated
|
$200
| |
50 to 99 vehicles generated
|
$400
| |
100 to 199 vehicles generated
|
$800
| |
200 to 299 vehicles generated
|
$1,200
| |
300 to 399 vehicles generated
|
$1,600
| |
400 to 499 vehicles generated
|
$2,200
| |
500 to 749 vehicles generated
|
$3,300
| |
750 and over vehicles generated
|
$10 per vehicle generated
|
Note: There is no review fee for non-subdivision singular residential
homes.
|
Map Sale Prices
| ||
---|---|---|
Size
(inches)
|
Price
| |
8 1/2 x 11
|
$1.50
| |
8 1/2 x 18
|
$3
| |
8 1/2 x 36
|
$3
| |
18 x 17
|
$4
| |
17 x 36
|
$5
| |
22 x 36
|
$5
| |
24 x 36
|
$5
| |
Printed County road map (small)
|
$2.50
| |
County road map (8 feet)
|
$5
|
Number of Vehicles in Highest
Two-Way Peak Hour
|
Impact Assessment Fee
| |
---|---|---|
0 to 10
|
$0
| |
11 to 25
|
$25 x vehicles generated
| |
26 to 99
|
$40 x vehicles generated
| |
100 to 199
|
$100 x vehicles generated
| |
200 to 299
|
$120 x vehicles generated
| |
300 to 399
|
$160 x vehicles generated
| |
400 to 499
|
$200 x vehicles generated
| |
500 to 549
|
$285 x vehicles generated
| |
550 to 599
|
$370 x vehicles generated
| |
600 to 649
|
$455 x vehicles generated
| |
650 to 699
|
$540 x vehicles generated
| |
700 to 749
|
$625 x vehicles generated
| |
750 to 799
|
$710 x vehicles generated
| |
800 and over
|
$800 x vehicles generated
|
Note: The impact assessment calculation shall be a straight
calculation based upon ITE (Institute of Traffic Engineers) data and
will not utilize any trip credits.
|