The Town Engineer shall be given at least 24 hours notice of work scheduled in order that he may make inspections at the following stages:
A. 
After excavation and trenching, before placement of utilities of foundation materials;
B. 
Foundation gravel to be approved before placement;
C. 
After placement of drainage structures, before backfilling;
D. 
After placing gravel, before placing paving;
E. 
As required for confirmation of extent of completion for release of security verifying:
(1) 
Placement of finish coat.
(2) 
Sidewalks.
(3) 
Curbing.
(4) 
Street signs.
(5) 
Grading outside traveled way.
(6) 
Trees.
(7) 
Monuments.
(8) 
Clean-up.
F. 
As required to advise on requested departures from plans as approved.
Strict compliance with the requirements of these rules and regulations may be waived when, in the judgment of the Planning Board, such action is in the public interest and not inconsistent with the Subdivision Control Law. Written requests for waivers of strict compliance with these rules shall accompany the definitive plan, and shall indicate the specific regulation sought to be waived and the nature, location, and intent of the waiver sought. Such request shall also include a demonstration certified by the applicants' engineer that such waiver is consistent with each of the purposes set forth in the purpose statement of these rules and regulations,[1] and is in the public interest.
[1]
Editor's Note: See § 320-1B.
Failure of the developer to record the definitive plan within six months of its endorsement, or to either initiate construction of improvements or sell lots in a subdivision or portion thereof within seven years of the approval of the definitive plan, shall constitute sufficient reason for the rescission of such approval in accordance with the requirements of MGL c. 41 § 81-W.
For matters not covered by these rules and regulations, reference is made to MGL c. 41 §§ 81-K to 81-GG, inclusive.
If any section, paragraph, sentence, clause or provision of these regulations shall be adjudged not valid, the adjudication shall apply only to the material so adjudged, and the remainder of these regulations shall be deemed valid and effective.