A. 
Inspecting agent.
(1) 
At least one week prior to commencement of street construction, the DPW Director shall be notified by certified mail of the intended commencement. The DPW Director shall, upon receipt of notification, appoint an agent and instruct said agent to make continuing inspections of the work to insure compliance with the Town's specifications and approved subdivision roadway construction plans. The wages of said agent are to be determined by the DPW Director and paid to the Town by the developer. If the agent is an employee of the Town, the wages will be the employee's standard pay scale plus 50% for indirect payroll costs. If the agent is a consultant, the wages will be in accordance with the agreement for services.
(2) 
Depending on the complexity of the project, the Board may use multiple inspection agents including, but not limited to, its reviewing engineer.
(3) 
The DPW Inspector or Engineer requested by the Planning Board (inspecting agent) shall act as the Board's inspecting agent to ensure that the construction of roadways and all utilities depicted on the definitive subdivision plan are carried out in accordance with these rules and regulations and Town standards. All elements of work are to be at all times subject to inspection. The inspecting agent and/or the Board may order tests and interim as-built plans to be prepared by the developer, at his expense, as may be needed to demonstrate that these rules and regulations and the construction standards contained herein have been met.
B. 
Pre-construction meeting.
(1) 
Following endorsement of the approved definitive subdivision plan, the developer shall notify the inspecting agent, Department of Public Works, and Planning Board, in writing, no later than seven days prior to the start of construction, to schedule a pre-construction meeting with the developer and his contractor(s). Any problems contemplated during the construction and the inspection schedule shall be discussed as well as procedures to be followed. At the pre-construction meeting, the developer shall provide a copy of the final stormwater pollution prevention plan (SWPPP) as filed with the Massachusetts Department of Environmental Protection and a detailed construction schedule. The schedule should be for each street along with an overall project time line. The schedule should be updated no less than every two weeks to show actual versus planned progress and submitted to the inspector and Planning Board.
(2) 
The developer shall notify the inspector, the Department of Public Works, and the Planning Board at least 48 hours prior to the time at which each one of the required construction observations/inspections should take place.
(3) 
The developer shall provide safe and convenient access to all parts of work for observation by the inspecting agent and/or the Board's members or agents. No work shall be approved that has been undertaken and covered before the required inspection/observation.
(4) 
To assure compliance, the following procedure must be followed:
(a) 
The developer must notify inspecting agent, Department of Public Works and Fire Department when underground infrastructure, such as but not limited to sewer, perimeter drain, fire alarm and drainage, are installed to allow for inspection of the installation by the respective department before the excavation is backfilled.
(b) 
The subgrade in the roadway and/or right-of-way must be approved by the inspecting agent before the application of the gravel base course.
(c) 
The gravel base course must be approved by inspecting agent before the application of hot mix asphalt (street or sidewalk) pavement, subject to compaction results provided by an independent testing lab, for depth and compaction.
(d) 
Each application of hot mix asphalt on the street and sidewalk and placement of curbing must be approved by inspecting agent for depth and temperature.
(e) 
The developer must keep the inspecting agent informed when materials and other items of work are ready for inspection and approval such as the installation of bounds, loam, and seeding, and general cleanup. No substitutions without approval of the Planning Board and either the inspecting agent or Department of Public Works Director.
(5) 
The inspecting agent shall complete Inspection Report (Form I[1]) and shall provide copies to the developer and/or contractor and the Planning Board.
[1]
Editor's Note: A copy of Form I is included as an attachment to this chapter.
(6) 
Failure to comply with the construction observation/inspection procedures shall result in the Board requiring any uninspected work to be exposed in order that the proper inspection may be made. This may necessitate removal of improvements, at the expense of the applicant. The Board may rescind its approval of the definitive subdivision plan in accordance with M.G.L. ch. 41, § 81W, or withhold approval of additional partial releases of covenant.
Strict compliance with the requirements of these rules and regulations may be waived when, in the judgment of the Planning Board, such action is in the public interest and not inconsistent with the Subdivision Control Law.
For matters not covered by these rules and regulations, reference is made to M.G.L. ch. 41, §§ 81K to 81GG, inclusive.