For any proposed development a phased stormwater management plan
shall be submitted to the Town for review and approval. Unless otherwise
determined by the Town, plans shall be submitted for the concept,
site design, and final stormwater management construction. When deemed
appropriate by the Town due to minor cumulative impacts of the development
and when the applicant has demonstrated that ESD standards have been
met to the MEP, the site design and final stormwater management construction
phases may be combined. Site plans, subdivisions, and building permits
with a total proposed lot coverage of 15% and total land disturbance
less than 20,000 square feet may combine all review phases when the
applicant has demonstrated that ESD standards have been met to the
MEP using the standard plan. Sites plans and building permits that
meet the criteria outlined on the Kent County Standard Stormwater
Plan may utilize the standard stormwater management plan.